Table
of contents
Page
Summary of Main Works Undertaken and Key Measures
Implemented
Summary of Exceedances, Investigation and
Follow-up
Complaint Handling, Prosecution and Public
Engagement
Construction Activities undertaken during the
Reporting Month
Status of Environmental Licensing and Permitting
Monitoring Parameters and
Frequency
Comparison of EM&A Result
with EIA Prediction
Monitoring Parameters,
Frequency and Duration
Monitoring Methodology and
QA/QC Procedure
Comparison of EM&A Result
with EIA Prediction
Implementation Status of Environmental Mitigation
Measures
Implementation Status of Event and Action Plans
Status of Required Submission under Environmental
Permit
11 Environmental non-conformance
Summary of Complaint, Warning, Notification of any
Summons and Successful Prosecution
13 Conclusions and recommendations
lIST OF
TABLES
Table I Summary of Complaint/Summons/Prosecution in the Reporting Month
Table II Summary Table for Site Activities in the next Reporting Period
Table 1.1 Key
Project Contacts
Table 1.3 Summary of Environmental License and Permit
Table
2.1 Air
Quality Monitoring Locations
Table
2.2 Frequency and Parameters of
Air Quality Monitoring
Table
2.3 Air
Quality Monitoring Equipment
Table
2.4 Major
Dust Source during Air Quality Monitoring
Table 2.5 Comparison of 1-hr TSP Monitoring Data
with Predictions in EIA Report (not used)
Table
2.6 Comparison
of 24-hr TSP Monitoring Data with Predictions in EIA Report
Table
3.1 Noise
Monitoring Stations
Table
3.2 Frequency and Parameters of Noise Monitoring
Table 3.3 Noise Monitoring Equipment
Table
3.4 Major
Noise Source during Noise Monitoring
Table
3.5 Baseline Noise Level and
Noise Limit Level for Monitoring Stations
Table
3.6 Comparison of Noise
Monitoring Data with Predictions in EIA Report
Table
7.1 Construction Phase Landscape
and Visual Mitigation Measures
Table
7.2 Construction Phase Audit
Checklist for Landscape and Visual Mitigation Measures
Table
10.1 Observations
and Recommendations of Site Audit
Table
10.2 Status of Required Submission
under Environmental Permit
lIST OF FIGUREs
Figure 1.1 Layout Plan of the
Project Site
Figure 1.2 Project
Organisation for Environmental Monitoring and Audit
Figure 2 Locations
of Air Quality and Construction Noise Monitoring Stations
lIST OF APPENDIces
Appendix A Action and Limit Levels
Appendix B Environmental Monitoring Schedules
Appendix C Copies of Calibration Certificates for Air Quality Monitoring
Appendix D Weather Information
Appendix E 1-hour TSP Monitoring Results and Graphical Presentations (not used)
Appendix F 24-hour TSP Monitoring Results and Graphical Presentations
Appendix G Copies of Calibration Certificates for Noise Monitoring
Appendix H Noise Monitoring Results and Graphical Presentations
Appendix J Event and Action Plans
Appendix K Environmental Mitigation Implementation Schedule (EMIS)
Appendix M Summary of Exceedance
Appendix N Tentative Construction Programme
1. This is the 6th Environmental Monitoring and Audit (EM&A) Report prepared by the Environmental Team (ET), Cinotech Consultants Ltd., for Contract No. ED/2018/04 “Trunk Road T2 and Infrastructure Works for Developments at the Former South Apron”. This report summarized the monitoring results and audits findings of the EM&A programme under the issued Environmental Permit (EP) No. EP-451/2013 and in accordance with the EM&A Manual (AEIAR-174/2013) during the reporting month of August 2020.
2. The main works undertaken during the reporting period are as follows:
Kai Tak:
· Contractor’s and SOR(MIC) Site Offices in Portion A3
· CLC building fabrication
· GI Works for the D-wall works at the Depressed Road
· Depressed Road – Sheet Piling
· Depressed Road – Diaphragm Wall
· Launching Shaft / C&C Tunnel CSM
· Launching Shaft / C&C Tunnel Diaphragm Wall
· Ground improvement works for PWCL at Portion N3
· Road S20 – Road & Drain
· 132kV substation ELS and Structure Construction at Portion M1
· Pre-boring and Sheet Pilling Works
· Guide wall Construction and D-wall Construction
Cha Kwo
Ling:
· East Portal – Site Setup
· East Portal – Blast door (EB) installation completed.
· Portal rock bolt installation completed.
· Horizontal GI for EB completed.
·
CKL Junction Improvement Works
3. Implementation of the key mitigation measures during the reporting period are as follows:
Air Quality
· Water spraying regularly on construction site area to avoid dust generation.
· Excavated dusty materials were covered by impervious sheets.
Noise
· Air compressor was operated with door closed and have valid noise labels.
· Use of Quality Powered Mechanical Equipment (QPME)
Water Quality
· WetSep was constructed to treat the surface runoff prior to discharge.
Landscape and Visual
· Tree protection zone were fenced off to protect the existing tree.
4.
Exceedance of Action/Limit levels
during the reporting month (August 2020) and the investigation results and/or
follow-up actions:
Air Quality Monitoring
· No Action/Limit Level exceedance for 24-hour TSP was recorded.
Construction Noise Monitoring
· No Action/Limit Level exceedance for construction noise was in this reporting month.
Landscape and Visual
Monitoring and Audit
·
No non-compliance of the
landscape and visual impact was recorded in the reporting month. The
implementation of landscape and visual and mitigation measures was checked by a
Registered Landscape Architect (RLA) during the environmental site inspections.
Table I Summary of Complaint/Summons/Prosecution in
the Reporting Month
Event |
Event Details |
Follow-up/
Remedial Actions |
Status/
Remarks |
|
Number |
Brief
Description |
|||
Complaints Received |
0 |
- |
- |
- |
Notification of Summons and Prosecutions
Received |
0 |
- |
- |
- |
Public Engagement Activities |
0 |
- |
- |
- |
5. Since the major parts of Works under Contract no. KL/2014/03 has been completed, the environmental monitoring works of EM&A monitoring station: KTD1a, KTD2c and KER1b was then handed over to the ET of Contact no. ED/2018/04 in August, 2020. As to obtain the environmental impact monitoring data with higher representative based on several conditions, such as distance between monitoring location and the sensitive receiver, non-project related interference, obstruction to the construction works on site and the power supply problem, the monitoring location KTD1a and KER1b has been updated to KTD1 and KER1 respectively on 3 August 2020, where are the original location as proposed in the EM&A manual (AEIAR-174/2013). And the monitoring location KTD2c was remained unchanged after the aforementioned review.
6. The key works or activities will be anticipated in the next reporting period are as follows:
Table II
Summary Table for Site Activities in the next Reporting Period
Site Activities (September 2020) |
Key
Environmental Issues |
|
1. Pump Test and
Dewatering Well 2. TAM Grouting
Works 3. Existing Slab
Breaking |
(A) / (B) / (C) / (D) |
|
Note: (A) Dust
generation from haul road, stockpile of dusty materials, exposed site area, excavation
works and rock breaking activities; (B) Noisy construction activity such as
rock-breaking activities and piling works; (C) Runoff from exposed slope or site area;
and (D) Wastewater and runoff discharge from
site. |
1.1
In 2009, Civil
Engineering and Development Department (CEDD) commissioned a Kai Tak Development
(KTD) – Trunk Road T2 and Infrastructure at South Apron Investigation. The assignment covers the provision of the Trunk Road T2 and its
connections with the Central Kowloon Route (CKR) at the north apron area and
the Tseung Kwan O – Lam Tin Tunnel (TKOLTT) to the
south in the Cha Kwo Ling area.
1.2
The Trunk Road T2 Project
is one of the designated Projects under Schedule 2 of the EIAO proposed in the
KTD. CEDD submitted the Project Profile (No. PP-379/2009) on 24 March 2009 for
application for an EIA study brief for the Trunk Road T2 Project under the
EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2 Project
was issued on 30 April 2009. The Environmental Impact Assessment (EIA) Report for the Trunk Road T2
Project was approved under the Environmental Impact Assessment Ordinance (EIAO)
on 19 September 2013. The corresponding Environmental Permit (EP) was issued on
19 September 2013 (EP no.: EP-451/2013).
1.3
The Contract No.
ED/2018/04 is the main contract of Trunk Road T2 (“T2 Main Works”) which
comprises mainly the design and construction of a dual two-lane trunk road of
approximately 3.0km long with about 2.7km of the trunk road in form of tunnel;
ventilation and administration buildings, environmental protection and
mitigation works and etc. The EM&A programme at
Kai Tak area under this Contract is governed by the
EP-451/2013 and EM&A Manual (AEIAR-174/2013). The work areas of the T2 Main
Works are shown in Figure 1 and the
works to be executed under this Contract and corresponding EP is summarized as
follows:
Environmental
Permit |
Works
Description |
EP-451/2013 – Trunk Road T2 |
Trunk Road T2 · Construction of highway and sub-sea tunnel
connecting between Central Kowloon Route and Cha Kwo
Ling Tunnel · Western & Eastern Ventilation Buildings |
Monitoring
Works in Kai Tak under EP-451/2013
1.4
Under
Contract No. KL/2014/03 - Kai Tak Development - Stage
3 Infrastructure Works for Development at the Southern Part of the Former
Runway (“T2 Advance Works”), the baseline monitoring works in Kai Tak under the EM&A Manual (AEIAR-174/2013) were
conducted by the Environmental Team (ET) for
the Contract No. KL/2014/03 at the approved relocated monitoring locations (EPD
reference: EP2/K19/A/21 pt.5), namely KTD1a, KTD2a & KER1a. During the
impact monitoring period, monitoring locations KTD 2a and KER 1a were relocated
to new locations, i.e. KTD 2b and KER 1b (EPD reference: ( ) in EP2/K19/A/21
pt. 6 and ( ) in EP2/K19/A/21 pt. 5) respectively. Location
KTD2b was then further relocated to location KTD2c, the proposal of such
relocation was submitted to EPD on 24 March 2020 and was approved by EPD on 6
April 2020 (EPD reference: ( ) in EP2/K19/A/21 pt.7). The aforementioned
relocation was effective from 9 April 2020. Since the major part of work under
Contract No. KL/2014/03 has been completed and monitoring works conducted by the ET of Contract No. KL/2014/03 was determined to be ceased, the impact monitoring within the Kai Tak area was
then handed over to the ET of Contract No. ED/2018/04 on 1 August 2020.The
monitoring location has been reviewed and updated to obtain the data with
higher representative based on several conditions, such as distance between
monitoring location and the sensitive receiver, non-project related
interference, obstruction to the construction works on site and the power
supply problem. The monitoring location KTD1a and KER1b has been updated to the
monitoring location KTD1 and KER1 on 3 August 2020, where are the original
location as proposed in the EM&A manual (AEIAR-174/2013). And the
monitoring location KTD2c was remained unchanged after the aforementioned
review. The impact monitoring for the three
stations KTD1, KTD2c and KER1 are currently conducted by the ET of T2 Main
Works
Monitoring Works in Cha Kwo Ling under EP-451/2013
1.5
The environmental impact of the remaining works
in Cha Kwo Ling, under EP-451/2013, shall be
monitored at the two proposed stations, namely CKL1, CKL2, in accordance to the
EM&A Manual (AEIAR-174/2013).
The impact monitoring for the two proposed stations shall be conducted by the
ET of T2 Main Works.
1.6
Cinotech Consultants
Ltd. was designated as
the Environmental Team (ET) to
undertake the EM&A works for “Trunk
Road T2 and Infrastructure Works for Developments at the Former South Apron”
(hereinafter called the “Project”).
1.7
This is
the 6th Monthly EM&A Report which summarises the impact monitoring results and audit
findings for the EM&A programme during the
reporting period in August 2020.
1.8 Different Parties with different levels of involvement in the Project organization include:
· Permit Holder – Civil Engineering and Development Department (CEDD)
·
Supervisor
Representative – Hyder-Meinhardt Joint Venture (HMJV)
· Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
· Independent Environmental Checker (IEC) – Ramboll Hong Kong Limited (Ramboll)
· Contractor – Bouygues Travaux Publics (BTP)
1.9 The key contacts of the Project are shown in Table 1.1.
Table 1.1 Key Project Contacts
Party |
Role |
Contact
Person |
Phone No. |
CEDD |
Permit Holder |
Mr. Wong Chi Wai, Tommy |
3842 7111 |
HMJV |
Supervisor Representative |
Mr. Joe Nam |
3742 3820 |
Cinotech |
Environmental Team |
Mr. KS Lee (ETL) |
2151 2091 |
Ms. Karina Chan |
2157 3880 |
||
Ramboll |
Independent Environmental Checker |
Mr. Manson Yeung |
3465 2888 |
BTP |
Contractor |
Mr. Bryan Lee |
5588 3891 |
1.10
The Organizational Structure for Environmental Management is shown in Figure 1.2.
1.11 The major site activities undertaken in the reporting month included:
Kai Tak:
· Contractor’s and SOR(MIC) Site Offices in Portion A3
· CLC building fabrication
· GI Works for the D-wall works at the Depressed Road
· Depressed Road – Sheet Piling
· Depressed Road – Diaphragm Wall
· Launching Shaft / C&C Tunnel CSM
· Launching Shaft / C&C Tunnel Diaphragm Wall
· Ground improvement works for PWCL at Portion N3
· Road S20 – Road & Drain
· 132kV substation ELS and Structure Construction at Portion M1
· Pre-boring and Sheet Pilling Works
·
Guide wall Construction and
D-wall Construction
Cha Kwo
Ling:
· East Portal – Site Setup
· East Portal – Blast door (EB) installation completed.
· Portal rock bolt installation completed.
· Horizontal GI for EB completed.
·
CKL Junction Improvement Works
1.12 The EM&A programme requires construction noise, air quality monitoring and environmental site audit, etc. The EM&A requirements for each parameter are described in the following sections, including:
· All monitoring parameters;
· Action and Limit levels for all environmental parameters;
· Event Action Plans;
· Environmental mitigation measures, as recommended in the Project EIA Report.
1.13 The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 10 of this report.
1.14 This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the monitoring parameters of the required environmental monitoring works and audit works for the Project in August 2020.
1.15 All permits/licenses obtained for the Project are summarized in Table 1.3.
Table 1.3 Summary of Environmental License and
Permit
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental
Permit (EP) |
|||
EP-451/2013 |
19 Sep 2013 |
N/A |
Valid |
Notification pursuant to Air Pollution
(Construction Dust) Regulation |
|||
Ref. No.: 451120 |
20 Nov 2019 |
N/A |
Valid |
Billing Account for Construction Waste
Disposal |
|||
A/C No.: 7036016 |
09 Dec 2019 |
N/A |
Valid |
Construction Noise Permit |
|||
CNP No. (For Portion Depressed Road): GW-RE0287-20 |
28 Apr 2020 |
24 Oct 2020 |
Valid |
CNP No. (For Portion A3): GW-RE0293-20 |
28 Apr 2020 |
25 Oct 2020 |
Valid |
CNP No. (For Launching Shaft and Barging Point):
GW-RE0326-20 |
11 May 2020 |
25 Oct 2020 |
Valid |
CNP No. (For Launching Shaft and Barging Point):
GW-RE0459-20 |
15 Jun 2020 |
10 Dec 2020 |
Valid |
CNP No. (For Launching Shaft and Barging Point):
GW-RE0653-20 |
5 Aug 2020 |
29 Dec 2020 |
Valid |
CNP No. (For Site Office and Support Area): GW-RE0588-20 |
15 Jul 2020 |
14 Jan 2021 |
Valid |
Wastewater Discharge License |
|||
WT00036183-2020 (For Depressed Road Area) |
27 Jul 2020 |
31 Jul 2025 |
Valid |
WT00036228-2020 (For Launching Shaft) |
27 Jul 2020 |
31 Jul 2025 |
Valid |
Chemical Waste Producer License |
|||
WPN: 5213-286-B2557-03 |
09 Mar 2020 |
N/A |
Valid |
2.1 According to the EM&A Manual (AEIAR-174/2013), 24-hour Total Suspended Particulates (TSP) monitoring was conducted to monitor the air quality for this Project. For regular impact monitoring, a sampling frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP monitoring. In case of complaints, 1-hour TSP monitoring should be conducted at least three times in every six days when the highest dust impacts are likely to occur. Appendix A shows the established Action/Limit Levels for the environmental monitoring works.
2.2 Five designated monitoring stations were selected for air quality monitoring programme. Table 2.1 describes the air quality monitoring locations, which are also depicted in Figure 2.
2.3 The monitoring location at Kai Tak area has been reviewed and updated to obtain the data with higher representative based on several conditions, such as distance between monitoring location and the sensitive receiver, non-project related interference, obstruction to the construction works on site and the power supply problem. The monitoring location KTD1a and KER1b has been updated to KTD1 and KER1 respectively, where are the original location as proposed in the EM&A manual (AEIAR-174/2013). And the monitoring location KTD2c was remained unchanged after the aforementioned review.
Table 2.1 Air Quality Monitoring Locations
Monitoring
Stations |
Location |
KTD1 |
Centre of Excellence in Paediatrics
(Children’s Hospital) |
KTD2c |
G/IC Zone next to Kwun
Tong Bypass (Next to the Kowloon Bay Sewage Interception Station) |
KER1 |
Future Residential Development at Kerry Godown |
CKL1 |
Flat 121 Cha Kwo
Ling Village |
CKL2 |
Flat 103 Cha Kwo
Ling Village |
2.4
Table 2.2 summarizes the monitoring
parameters, monitoring period and frequencies of impact air quality monitoring.
The monitoring schedule is shown in
Appendix B.
Table 2.2
Frequency and Parameters of Air Quality Monitoring
Monitoring Stations |
Parameter |
Period |
Frequency |
KTD1, KTD2c,
KER1, CKL1 & CKL2 |
1-hour TSP |
0700 – 1900 |
3 times per 6 days (as required in
case of complaints) |
KTD1, KTD2c, KER1,
CKL1 & CKL2 |
24-hour TSP |
24 hours |
Once every 6
days |
2.5 High Volume Samplers (HVS) in compliance with the specification stipulated in the EM&A Manual (AEIAR-174/2013), Section 2.2.1.4, were used to carry out 24-hour TSP monitoring. Direct reading dust meter were also used to measure 1-hour average TSP levels. The 1-hour sampling was determined by HVS to check the validity and accuracy of the results measured by direct reading method.
2.6 Wind data monitoring equipment was set at rooftop (about 41/F) of Yau Lai Estate Bik Lai House, Lam Tin for logging wind speed and wind direction such that the wind sensors were clear of obstructions or turbulence caused by building. The wind data monitoring equipment was re-calibrated at least once every six months and the wind directions were divided into 16 sectors of 22.5 degrees each. Wind data is attached in Appendix D.
2.7 Table 2.3 summarizes the equipment used for air quality monitoring. Copies of calibration certificates are attached in Appendix C.
Table
2.3 Air Quality Monitoring
Equipment
Equipment |
Model |
Quantity |
HVS Sampler |
TISCH Model: TE-5170 (Serial no. 0723, 1956, 10595, 1316, 5280) |
5 |
Calibrator |
TISCH Model: TE-5025A (Serial no. 3746) |
1 |
Wind Anemometer |
Davis Weather Monitor II, Model no. 7440 |
1 |
1-hour TSP Monitoring
Measuring Procedures
2.8 The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(Sibata Model No.: LD-3B/LD-5R)
· The 1-hour dust meter is placed at least 1.3 meters above ground.
· Set POWER to “ON” and make sure that the battery level was not flash or in low level.
· Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet has been released.
· Push the knob at MEASURE position.
· Set time/mode setting to [BG] by pushing the time setting switch. Then, start the background measurement by pushing the start/stop switch once. It will take 6 sec. to complete the background measurement.
· Push the time setting switch to change the time setting display to [MANUAL] at the bottom left of the liquid crystal display. Finally, push the start/stop switch to stop the measuring after 1 hour sampling.
· Information such as sampling date, time, count value and site condition were recorded during the monitoring period.
Maintenance/Calibration
2.9 The following maintenance/calibration is required for the 1-hour dust meter:
· Check and calibrate the meter by HVS to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.
24-hour TSP Monitoring
Instrumentation
2.10 High volume samplers (HVS) (TISCH Model: TE-5170) complete with appropriate sampling inlets was employed for 24-hour TSP monitoring. The sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complied with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50). Moreover, the HVS also met all the requirements in Section 2.2 of the Annex II Specification.
2.11 The positioning of the HVS samplers are as follows:
·
A
horizontal platform with appropriate support to secure the samplers against
gusty wind shall be provided;
·
No
two samplers shall be placed less than 2 meter apart;
·
The
distance between the sampler and an obstacle, such as buildings, must be at
least twice the height that the obstacle protrudes above the sampler;
·
A
minimum of 2 metres of separation from walls, parapets and penthouses is
required for rooftop samplers;
·
A
minimum of 2 metres of separation from any supporting structure, measured
horizontally is required;
·
No
furnace or incinerator flue is nearby;
·
Airflow
around the sampler is unrestricted;
·
The
sampler is more than 20 metres from the dripline;
·
Any
wire fence and gate, to protect the sampler, shall not cause any obstruction
during monitoring;
·
Permission
must be obtained to set up the samplers and to obtain access to the monitoring
stations; and
·
A
secured supply of electricity is needed to operate the samplers.
Operating/analytical
procedures for the operation of HVS
2.12 Operating/analytical procedures for the air quality monitoring are highlighted as follows:
·
Prior to the commencement of
the dust sampling, the flow rate of the high volume sampler was properly set (between 0.6 m3/min.
and 1.7 m3/min.) in accordance with the EM&A manual (AEIAR-174/2013). The flow rate shall be indicated on the
flow rate chart.
·
For
TSP sampling, fiberglass filters with a collection efficiency of > 99% for
particles of 0.3μm diameter were used.
·
The
power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5
minutes to establish thermal equilibrium before placing any filter media at the
designated air monitoring station.
·
The
filter holding frame was then removed by loosening the four nuts and a weighted
and conditioned filter was carefully centered with
the stamped number upwards, on a supporting screen.
·
The
filter was aligned on the screen so that the gasket formed an airtight seal on
the outer edges of the filter. Then the
filter holding frame was tightened to the filter holder with swing bolts. The
applied pressure should be sufficient to avoid air leakage at the edges.
·
The
shelter lid was closed and secured with the aluminum
strip.
·
The
timer was then programmed. Information
was recorded on the record sheet, which included the starting time, the weather
condition and the filter number (the initial weight of the filter paper can be
found out by using the filter number).
·
After
sampling, the filter was removed and sent to the HOKLAS laboratory (ALS Technichem (HK) Pty Ltd. and Wellab
Ltd.) for weighing. The elapsed time was
also recorded.
· Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25°C and 30°C and not vary by more than ±3°C; the relative humidity (RH) should be < 50% and not vary by more than ±5%. A convenient working RH is 40%.
Maintenance/Calibration
2.13 The following maintenance/calibration is required for the HVS:
·
The
high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor
brushes replacement and electrical wiring checking were made to ensure that the
equipment and necessary power supply are in good working condition.
· High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the air quality monitoring.
2.14 Impact air quality monitoring was conducted at five monitoring stations as scheduled. The monitoring schedule is shown in Appendix B.
2.15 No Action/Limit Level exceedance was recorded for all 24-hour TSP monitoring in the reporting month.
2.16 The air temperature, relative humidity, and the precipitation data were obtained from daily extracts of Hong Kong Observatory Climate Information Service. This weather information for the reporting month is summarized in Appendix D.
2.17 The monitoring data and graphical presentations of 24-hour TSP monitoring results are shown in Appendix F.
2.18 According to field observations observed in the reporting period, the major dust source identified at the designated air quality monitoring stations are as follows:
Table 2.4 Major Dust Source
during Air Quality Monitoring
Monitoring Stations |
Major Dust Source |
KTD 1 - Centre of Excellence in Paediatrics
(Children’s Hospital) |
·
Loading and
unloading of C&D wastes in the site; ·
Vehicle movement
in the site; ·
Construction activities
at the nearby construction sites of New Acute Hospital; and, ·
Road traffic
along Sing Fung Road, Shing Cheong Road, Cheung Yip
Street, Kai Hing Road and Kwun
Tong Bypass. |
KTD 2c - G/IC Zone next to Kwun Tong Bypass (Next to the Kowloon Bay Sewage Interception Station |
|
KER 1 – Future Residential Development at Kerry Godown |
|
CKL1 - Flat 121 Cha Kwo
Ling Village |
Road Traffic
along Cha Kwo Ling Road |
CKL2 - Flat 103 Cha Kwo Ling Village |
Road Traffic
along Cha Kwo Ling Road |
2.19
The air monitoring data was
compared with the predictions in Table 4.14 of EIA Report, AEIAR-174/2013 (as
approved in 2013) as summarised in Table
2.6 for 24-hour TSP.
Table 2.6 Comparison of 24-hr TSP Monitoring Data
with Predictions in EIA Report
Monitoring Stations |
ASR ID |
Predicted Maximum 24-hr TSP Concentration in EIA Report (AEIAR-174/2013), μg/m3 |
Maximum 24-hr TSP Concentration in the Reporting Month |
KTD 1 - Centre of Excellence
in Paediatrics (Children’s Hospital) |
KTD3 |
126 |
56.9 |
KTD 2c - G/IC Zone next
to Kwun Tong Bypass (Next to the Kowloon Bay Sewage
Interception Station |
N/A(1) |
N/A(1) |
150.0 |
KER 1 – Future
Residential Development at Kerry Godown |
KTD6 |
169 |
164.4 |
CKL1 - Flat 121 Cha Kwo
Ling Village |
N/A(1) |
N/A(1) |
82.0 |
CKL2 - Flat 103 Cha Kwo
Ling Village |
N/A(1) |
N/A(1) |
80.6 |
Remarks:
(1)
No 24-hr TSP concentration was predicted in EIA
Report (AEIAR-174/2013)
2.20 In the reporting month the 24-hour TSP concentration at KTD1 and KER1 were lower than the prediction in the EIA Report, AEIAR-174/2013 (as approved in 2013) .No Action/Limit level exceedance for 24-hour TSP was recorded in the reporting period.
3.1 According to the EM&A Manual (AEIAR-174/2013), construction noise monitoring was conducted to monitor the construction noise arising from the construction activities. The regular monitoring frequency for each monitoring station shall be on a weekly basis and conduct one set of measurements between 0700 and 1900 hours on normal weekdays. Appendix A shows the established Action and Limit Levels for the environmental monitoring works.
3.2 Noise monitoring was conducted at five designated monitoring stations, namely KTD1, KTD2c, KER1, CKL1 and CKL2 in the reporting period. Table 3.1 and Figure 2 show the locations of these stations.
3.3 The monitoring location at Kai Tak area has been reviewed and updated to obtain the data with higher representative based on several conditions, such as distance between monitoring location and the sensitive receiver, non-project related interference, obstruction to the construction works on site and the power supply problem. The monitoring location KTD1a and KER1b has been updated to KTD1 and KER1 respectively, where are the original location as proposed in the EM&A manual (AEIAR-174/2013). And the monitoring location KTD2c was remained unchanged after the aforementioned review.
Table 3.1 Noise Monitoring Stations
Monitoring
Stations |
Location |
KTD1 |
Centre of Excellence in Paediatrics
(Children’s Hospital) |
KTD2c |
G/IC Zone next to Kwun
Tong Bypass (Next to the Kowloon Bay Sewage Interception Station) |
KER1 |
Future
Residential Development at Kerry Godown |
CKL1 |
Flat 121 Cha Kwo
Ling Village |
CKL2 |
Flat 103 Cha Kwo
Ling Village |
3.4
Table 3.2 summarizes the monitoring
parameters, frequency and total duration of monitoring. The noise monitoring schedule is shown in Appendix B.
Table 3.2 Frequency and Parameters of Noise
Monitoring
Monitoring
Stations |
Time Period |
Duration |
Frequency |
Parameter |
Measurement |
KTD1 |
0700-1900 hrs on normal weekdays |
30 minutes |
Once per week |
L10(30 min.) dB(A) L90(30 min.) dB(A) Leq(30 min.) dB(A) |
Façade Measurement |
KTD2c |
Free Field Measurement |
||||
KER1 |
Free Field Measurement |
||||
CKL1 |
Free Field Measurement |
||||
CKL2 |
Free Field Measurement |
3.5
Integrating Sound Level Meter was
used for impact noise monitoring. The meters were Type 1 sound level meter
capable of giving a continuous readout of the noise level readings including
equivalent continuous sound pressure level (Leq)
and percentile sound pressure level (Lx) that also complied with
International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Table 3.3
summarizes the noise monitoring equipment being used within the reporting
period. Copies of calibration certificates are attached in Appendix G.
Table
3.3 Noise Monitoring Equipment
Equipment |
Model |
Quantity |
Integrating Sound Level Meter |
BSWA308 (Serial no. 570187, 570183) |
2 |
SVAN 979 (Serial no. 27190) |
1 |
|
SVAN 957 (Serial no. 23852) |
1 |
|
Calibrator |
ST-120 (Serial no. 181001637, 181001608, 181001636) |
3 |
B&K4231 (Serial no. 2326353) |
1 |
3.6 The monitoring procedures are as follows:
· The monitoring station was normally be at a point 1m from the exterior of the sensitive receivers building façade and be at a position 1.2m above the ground.
· For free field measurement, the meter was positioned away from any nearby reflective surfaces. All records for free field noise levels were adjusted with a correction of +3 dB(A).
· The battery condition was checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- Frequency weighting: A
- Time weighting: Fast
- Time measurement: 30 minutes
· Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.
· The wind speed was frequently checked with the portable wind meter.
· At the end of the monitoring period, the Leq, L90 and L10 were recorded. In addition, site conditions and noise sources were recorded on a standard record sheet.
·
Noise monitoring would be
cancelled in the presence of fog, rain, and wind with a steady speed exceeding
3.7 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals.
3.8 The sound level meter and calibrator were checked and calibrated at yearly intervals.
3.9 Immediately prior to and following each noise measurement the accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements were accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.
3.10 Impact noise monitoring was conducted at five monitoring stations as scheduled. The monitoring schedule is shown in Appendix B. No Action/Limit Level exceedance was recorded for all construction noise monitoring in the reporting month.
3.11 Noise monitoring results and graphical presentations are shown in Appendix H.
3.12 According to field observations observed in the reporting period, the major noise sources identified at the noise monitoring stations are shown in Table 3.4.
Table 3.4 Other Noise Source Identified during
Noise Monitoring
Monitoring Stations |
Major Noise Source |
KTD 1 |
·
Project related construction
activities (Loading and unloading of C&D waste, travel of vehicles, use
of PME and other plants, and other construction activities); ·
Vehicle movement
in the site; ·
Road traffic
along Shing Fung Road; and, ·
Non-project
related construction activities at the nearby construction site of New Acute
Hospital. |
KTD 2c |
·
Project related
construction activities (Loading and unloading of C&D waste, travel of
vehicles, use of PME and other plants, and other construction activities); ·
Vehicle movement
in the site; ·
Road traffic alongKwun Tong By-pass; and, ·
Non-project
related construction activities at the nearby construction site of New Acute
Hospital |
KER 1 |
Road traffic along Kai Hing Road. |
CKL1 |
Road traffic along Cha Kwo Ling Road. |
CKL2 |
Road traffic along Cha Kwo Ling Road |
.
3.13 The baseline noise level and the Noise Limit Level at each designated noise monitoring station are presented in Table 3.5.
Table 3.5 Baseline Noise
Level and Noise Limit Level for Monitoring Stations
Monitoring Stations |
Baseline Noise Level, dB
(A) |
Noise Limit Level, dB (A)
(at 0700 – 1900 hrs on normal weekdays) |
KTD1 |
78 |
75 |
KTD2c |
64 |
|
KER1 |
65 |
|
CKL1 |
72.4 |
|
CKL2 |
71.4 |
3.14 The noise monitoring data was compared with the predictions in Table 5.13 of EIA Report (AEIAR-174/2013) as summarised in Table 3.6.
Table 3.6 Maximum Predicted Mitigated Construction
Noise Levels in EIA Report
Monitoring Stations |
NSR ID |
Maximum Predicted Mitigated Construction Noise Levels in EIA Report (AEIAR-174/2013), dB(A) |
Maximum Construction Noise Levels in the Reporting
Month |
KTD 1 - Centre of
Excellence in Paediatrics (Children’s Hospital) |
KTD1 |
74 |
73.2 |
KTD 2c - G/IC
Zone next to Kwun Tong Bypass (Next to the Kowloon
Bay Sewage Interception Station |
N/A(1) |
N/A(1) |
72.4 |
KER 1 – Future
Residential Development at Kerry Godown |
KER1 |
75 |
74.1 |
CKL1 - Flat 121 Cha Kwo Ling Village |
CKL4 |
71 |
72.9 |
CKL2 - Flat 103 Cha Kwo Ling Village |
CKL5 |
69 |
71.7 |
Remarks:
(1)
No Maximum Predicted Mitigated Construction Noise
Levels was predicted in EIA Report (AEIAR-174/2013)
3.15 The results at CKL1 and CKL2 were higher than the maximum predicted mitigated construction noise level in the EIA Report, AEIAR-174/2013 (as approved in 2013), this may be due to fluctuations of traffic flow along Cha Kwo Ling Road throughout the day. The results at KTD1 and KER1 were lower than the maximum predicted noise level in the EIA Report. No Limit level exceedance was recorded in the reporting period.
4.1 According to Section 4.3.1.1 of EM&A Manual (AEIAR-174/2013), no water quality monitoring is required during the construction phase.
4.2 According to Section 4.3.1.5 of EM&A Manual (AEIAR-174/2013), compliance site audits are to be undertaken by the Engineer and ET and escorted by the Contractor to ensure that a valid discharge license has been issued by the EPD prior to the discharge of the effluent from the construction activities of the Project site. Monitoring of the quality of the treated effluent from the works areas should be carried out in accordance with the Water Pollution Control Ordinance (WPCO) license. The audit results reflect whether the effluent quality is in compliance with the discharge license requirements, the summaries of site audits are attached in Appendix I.
4.3 In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event / Action plan attached in Appendix J.
5.1 According to Section 5.3.1.1 of EM&A Manual (AEIAR-174/2013), ET will be required to undertake audit of good site practice for habitat protection as detailed below. The summaries of site audits are attached in Appendix I.
·
Avoid damage and disturbance to the remaining
and surrounding natural habitat;
·
Ensure placement of equipment is within
designated areas within the existing disturbed land;
·
Ensure construction activities are restricted
to within the proposed works boundary;
·
Ensure spoil heaps are be covered at all
times;
·
Ensure that disturbed areas are reinstated
immediately after completion of the works; and
· Ensure enhancement planting works undertaken.
6.1 According to Section 6.3.1.2 of EM&A Manual (AEIAR-174/2013), no specific fisheries monitoring and audit programme is required during the construction phase.
6.2 The implementation of the water quality mitigation measures stated in the Water Quality Impact Assessment (Refer to Section 6 of the EIA Report (AEIAR-174/2013)) will be audited as part of the EM&A procedures during the construction period and the details are presented in Section 4.2 of this Report. The summaries of site audits are attached in Appendix I.
7.1 According to the EM&A Manual (AEIAR-174/2013), a series of mitigation measures were recommended to ameliorate the landscape and visual impacts of the Project. The mitigation measures for construction stage are summarized in Table 7.1 below and provided in Appendix K:
Table 7.1 Construction Phase Landscape and Visual
Mitigation Measures
ID No. |
Landscape and Visual Mitigation Measure |
CM1 |
All works shall
be carefully designed to minimize impacts on existing landscape
resources
and visually sensitive receivers. Existing trees within works area shall
be
retained and protected. |
CM2 |
Existing trees of good quality and condition that
are unavoidably affected by the works should be transplanted. |
CM3 |
Not used. |
CM4 |
Not used. |
CM5 |
Large temporary
stockpiles of excavated material shall be covered with unobtrusive
sheeting to prevent dust and dirt spreading to adjacent landscape areas and
vegetation, and to create a neat and tidy visual appearance. |
CM6 |
Construction
plant and building material shall be orderly and carefully stored in order to create a
neat and tidy visual appearance |
CM7 |
Erection of
decorative screen hoarding should be designed to be compatible with the existing
urban context. |
CM8 |
All lighting in
construction site shall be carefully controlled to minimize light pollution and
night-time glare to nearby residences and GIC user. The contractor shall consider
other security measures, which shall minimize the visual impacts. |
7.2 A specialist Landscape Sub-Contractor should be employed by the Contractor for the implementation of landscape construction works and subsequent maintenance operations during the establishment period. It is proposed that the planting works will be on-site and the planting should be completed during the construction contract. The monitoring of the planting establishment should be undertaken for a 12 month period which could extend throughout the Contractor’s one-year maintenance period, which will be within the first operational year of the Project.
7.3 All measures undertaken by both the Contractor and the specialist Landscape Sub-Contractor during the construction phase and first year of the operational phase shall be audited by a Registered Landscape Architect (RLA), as a member of the Environmental Team (ET), on a regular basis to ensure compliance with the intended aims of the measures. To fulfil the aforementioned requirements, on-site landscape and visual mitigation measures were audited by RLA in the reporting month.
7.4 According to Section 7.3.1.2 of the EM&A Manual (AEIAR-174/2013), site audits shall be undertaken at least once every two weeks throughout the construction period to monitor and audit the timely implementation of landscape and visual mitigation measures within the site boundaries of this Project.
7.5 The broad scope of the audit is detailed below but should also be undertaken with reference to the more specific checklist provided in Table 7.2. The summaries of site audits are attached in Appendix I:
·
The extent of the agreed works areas should be
regularly checked during the construction phase. Any trespass by the Contractor
outside the limit of the works, including any damage to existing trees and soft
landscape areas shall be prohibited;
· the progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken;
·
all existing trees and vegetation within the
study area which are not directly affected by the works are retained and
protected;
· the methods of protecting existing vegetation proposed by the Contractor are acceptable and enforced;
· preparation, lifting transport and re-planting operations for any transplanted trees;
· all landscaping works are carried out in accordance with the specifications;
· the planting of new trees, shrubs, groundcover, climbers, ferns, grasses and other plans, together with the replanting of any transplanted trees are carried out properly and within the right season; and
· all necessary horticultural operations and replacement planting are undertaken throughout the Establishment Period to ensure the healthy establishment and growth of both transplanted trees and all newly established plants.
Table 7.2 Construction Phase Audit Checklist for Landscape and Visual Mitigation
Measures
Area of Works |
Items to be Monitored |
Advance planting |
Monitoring of implementation and maintenance of planting, and
against possible incursion, physical damage, fire, pollution, surface
erosion, etc. |
Protection of all trees and
existing soft landscape areas to be retained |
Identification and
demarcation of trees / vegetation to be retained, erection of physical
protection (e.g. fencing), monitoring against possible incursion, physical
damage, fire, pollution, surface erosion, etc. |
Clearance of existing
vegetation |
Identification and
demarcation of trees / vegetation to be cleared, checking of extent of works
to minimise damage, monitoring of adjacent areas against possible incursion,
physical damage, fire, pollution, surface erosion, etc. |
Pruning of trees |
Identification and
demarcation of trees / vegetation to be pruned, monitoring of extent of
pruning to minimise damage, timing of operations, implementation of all
stages of preparatory and pruning works, and maintenance of pruned
vegetation, etc. |
Plant supply |
Monitoring of operations
relating to the supply of specialist plant material (including the
collecting, germination and growth of plants from seed) to ensure that plants
will be available in time to be used within the construction works. |
Soiling, planting, etc. |
Monitoring of
implementation and maintenance of soiling and planting works and against
possible incursion, physical damage, fire, pollution, surface erosion, etc. |
Site fencing and
hoarding |
Implementation and
maintenance, to ensure compliance with agreed designs and check that it
matches the surrounding environment and does not cause visual intrusion. |
Architectural treatment
of engineering works. |
Implementation and
maintenance of mitigation measures, to ensure compliance with agreed designs
as applicable. |
Establishment Works |
Monitoring of
implementation of maintenance operations during Establishment Period. |
7.6 In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event / Action plan attached in Appendix J.
7.7 In the reporting month, no non-compliance of the landscape and visual mitigation measures was recorded by RLA.
8.1 According to Section 8.3.1.1 of EM&A Manual (AEIAR-174/2013), as a precautionary measure, it is recommended that if any antiquity or supposed antiquity is discovered during the course of the excavation works undertaken by the Contractor, the discovery shall be reported to the AMO immediately and all necessary measures taken to preserve it.
8.2 According to Section 8.3.1.2 of EM&A Manual (AEIAR-174/2013), no EM&A is required during the construction and operational phase.
9.1 According to Section 9.3.1.1 of EM&A Manual (AEIAR-174/2013), the effective management of waste arisings during the construction phase will be monitored through the site audit programme. Regular audits and site inspections should be carried out by the Engineer, ET and Contractor to ensure that the recommended good site practices and other mitigation measures are implemented by the Contractor. The summaries of site audits are attached in Appendix I.
9.2
According to Sections 9.3.1.3
and 9.3.1.4 of
EM&A Manual (AEIAR-174/2013),
documents including licenses, permits, disposal and recycling records should be
reviewed and audited during site audits for the compliance with the legislation
and contract requirements to ensure proper records are being maintained and
procedures undertaken in accordance with the Waste Management Plan.
10.1 Site audits were carried out on a weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Project site. The summaries of site audits are attached in Appendix I.
10.2 Site audits were conducted on 06, 13, 20, and 27 August 2020 in the reporting month. Site inspection of the IEC was conducted on 13 August 2020. No non-compliance was observed during the site audit.
10.3 According to Environmental Permits, the approved EIA Reports (Register No.: AEIAR-174/2013 and AEIAR-173/2013), and the EM&A Manuals of the Project (AEIAR-174/2013 and AEIAR-173/2013), the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An Environmental Mitigation Implementation Schedule (EMIS) is provided in Appendix K.
10.4
The ET weekly site inspections
were carried out during the reporting month and the observations and
recommendations are summarized in Table
10.1. Refer to Appendix I for
the site inspection summary reports in the reporting month.
Table 10.1 Observations and Recommendations of Site
Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
N/A |
There was no observation in the reporting period. |
N/A |
Noise |
N/A |
There was no observation in the reporting period. |
N/A |
Water Quality |
30 July 2020 |
Still water was observed near the Bar Bending Yard. |
Standing water was pumped out and discharged into appropriate watercourse after silt retention via the WetSep |
20 August 2020 |
Standing water within a skip at Launching Shaft was observed. |
Standing water was pumped out and discharged into appropriate watercourse after silt retention via the WetSep |
|
Spilled oil presented on the accumulated water was observed in the drip tray. |
Such accumulation and the spilled oil were cleared to avoid overflow from drip tray during heavy rain. |
||
Ecology |
N/A |
There was no observation in the reporting period. |
N/A |
Landscape and Visual |
N/A |
There was no observation in the reporting period. |
N/A |
Waste / Chemical Management |
N/A |
There was no observation in the reporting period. |
N/A |
Permits /Licences |
N/A |
There was no observation in the reporting period. |
N/A |
10.5 The Event and Action Plans for air quality, construction noise, and landscape and visual are presented in Appendix J.
Air Quality Monitoring
· No Action/Limit Level exceedance for 24-hour TSP monitoring was recorded.
Construction Noise
Monitoring
· No Limit Level exceedance for construction noise monitoring was recorded in the reporting month.
· No documented complaint on construction noise was received; no Action Level exceedance for construction noise was recorded.
Landscape and Visual
· No landscape and visual non-conformity was recorded.
10.6 According the Section 11.3.2.1 (c) of the EM&A Manual (AEIAR-174/2013), status of required submission under EP-451/2013 during the reporting period are summarized in Table 10.2.
Table 10.2 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission Date |
EP-451/2013 |
||
Condition 2.3 |
Management Organization of Main Construction Companies |
20 January 2020 |
Condition 2.4 |
Design Drawing of the Project |
20 January 2020 |
Condition 2.5 |
Landscape Mitigation Plan(s) |
7 May 2020 |
Condition 2.10 (a) |
Supplementary Contamination Assessment Plan |
18 December 2015 |
Condition 2.10 (b) |
Supplementary Contamination Assessment Report |
6 December 2016 |
Condition 3.3 |
Updated Baseline Monitoring Report |
11 August 2020 |
Condition 3.4 |
Monthly EM&A Report (July 2020) |
18 August 2020 |
11.1 The summaries of environmental complaint, warning, summon and notification of successful prosecution for the Project is presented in Appendix L.
11.2
The summary of exceedance
record in the reporting month is shown in Appendix
M.
11.3 No non-conformity was recorded for landscape and visual inspections conducted in the reporting month.
Tentative construction programmes for the next three months are provided in Appendix N.
12.1 Major site activities undertaken for the coming months are summarized as follows:
·
Pump Test and Dewatering Well
·
TAM Grouting Works
·
Existing Slab Breaking
12.2 Key environmental issues in the coming months include:
· Wheel washing bay at site exits;
· Temporary noise barriers for PMEs;
· Sedimentation tank for settling muddy water;
· Make sure open stockpiles are covered during rainstorm; and
· Make sure bypass is provided in the drainage system to prevent flooding during periods of heavy rain.
12.3 The tentative environmental monitoring schedule for the next three months are shown in Appendix B.
13.1 This is the 6th Monthly EM&A Report which presents the EM&A works undertaken during the reporting month in accordance with the EM&A Manual (AEIAR-174/2013) and the requirement under EP.
Air
Quality Monitoring
13.2 No Action/Limit Level exceedance was recorded for 24-hour TSP monitoring in the reporting month.
Construction Noise Monitoring
13.3 No Limit Level exceedance was recorded for all noise monitoring in the reporting month.
13.4 No Action Level exceedance was recorded in the reporting month.
Site Audit
13.5 4 ET joint weekly environmental site inspections were conducted in the reporting month.
Complaint,
Notification of Summons and Successful Prosecution
13.6
No environmental complaint was
received in the reporting month. No notifications of summons and successful
prosecutions were received in the reporting month.
13.7 According to the environmental audit performed in the reporting month, the following recommendations was made:
Water Quality
· Surface runoff from the construction site should be treated to meet the requirement prior to discharge;
· Conducting a regular inspection, especially after heavy rain, in order to avoid accumulation of water/ muddy water on site area or drip tray;
Waste/Chemical Management
·
Regular inspection of the equipment/ PME on site should be provided to
ensure equipment/ PME on site are operated under a good condition and conducted
a timely repairing.