Table of contents
Page
Summary of Main Works
Undertaken and Key Measures Implemented
Environmental
Monitoring Works
Key Information in
the Reporting Month
Construction
Activities undertaken during the Reporting Month
Status of
Environmental Licensing and Permitting
Monitoring Parameters
and Frequency
Comparison of
EM&A Result with EIA Prediction
Monitoring
Parameters, Frequency and Duration
Monitoring
Methodology and QA/QC Procedure
Comparison of
EM&A Result with EIA Prediction
9. LANDSCAPE AND VISUAL IMPACT
Implementation Status
of Environmental Mitigation Measures
Implementation Status
of Event and Action Plans
13. ENVIRONMENTAL NON-COMFORMANCE
Summary of Complaint,
Warning, Notification of any Summons and Successful Prosecution
15. CONCLUSION AND RECOMMENDATION
lIST OF TABLES
Table I
Summary of Key Construction Work in the Reporting Month
Table II Summary of Key Mitigation Measures
Implemented in the Reporting Month
Table III Non-compliance (exceedance) Record for
the Project in the Reporting Month
Table V Summary
of Complaints Details in Reporting Month
Table VI Summary
Table for Site Activities in the next Reporting Period
Table
1.1 Key Project Contacts
Table 1.2 Summary of Key Construction Work in the Reporting Month
Table
1.3 Summary
of Environmental License and Permit
Table 2.1 Air Quality Monitoring Locations
Table
2.2 Frequency and Parameters of
Air Quality Monitoring
Table
2.3 Air Quality Monitoring
Equipment
Table 2.4 Major Dust Source during Air Quality Monitoring
Table
2.5 Comparison
of 1-hr TSP Monitoring Data with Predictions in EIA Report
Table 2.6 Comparison of 24-hr TSP Monitoring Data with Predictions in EIA Report
Table
3.1 Noise Monitoring
Stations
Table
3.2 Frequency and Parameters of
Noise Monitoring
Table
3.3 Noise Monitoring Equipment
Table
3.4 Other Noise Source Identified during Noise Monitoring
Table
3.5 Baseline
Noise Level and Noise Limit Level for Monitoring Stations
Table
3.6 Maximum
Predicted Mitigated Construction Noise Levels in EIA Report
Table 10.1 Landfill Gas Monitoring Equipment (not used)
Table
12.1 Observations
and Recommendations of Site Audit
Table 14.1 Site Activities and the Key Environmental Issues in the next Reporting Period
lIST OF FIGUREs
Figure 1.2 Organizational Structure for Environmental Management
Figure 2 Locations of Air
Quality and Construction Noise Monitoring Stations
lIST OF APPENDIces
Appendix A Action
and Limit Levels
Appendix B Copies of Calibration Certificates
Appendix C Weather Information
Appendix
D Environmental Monitoring Schedules
Appendix E 1-hour TSP Monitoring Results and Graphical
Presentations
Appendix F 24-hour TSP Monitoring Results and Graphical
Presentations
Appendix G Noise Monitoring Results and Graphical Presentations
Appendix
H Waste Generation in the Reporting Month
Appendix I Site Audit Summary
Appendix
J Environmental Mitigation Implementation Schedule
(EMIS)
Appendix K Record
of Landfill Gas Monitoring by Contractor (not used)
Appendix L Event
and Action Plans
Appendix N Summary of Exceedance
Appendix O Tentative
Construction Programme
1.
This is the 50th Environmental Monitoring and Audit
(EM&A) Report prepared by the Environmental Team (ET), Cinotech
Consultants Ltd., for Contract No. ED/2018/04 “Trunk Road T2 and Infrastructure
Works for Developments at the Former South Apron”, and Contract No. ED/2020/03
“Trunk Road T2 - Traffic Control And Surveillance
System (TCSS) and Associated Works”. This report summarized the monitoring
results and audits findings of the EM&A programme under the issued
Environmental Permit (EP) No. EP-458/2013/C and in accordance with the EM&A
Manual (AEIAR-173/2013) during the reporting month of June 2024.
2.
The main works undertaken during the reporting period are as follows:
Table
I
Summary of Key Construction Work in the Reporting Month
Contract No. |
Project Title |
Site Activities |
ED/2018/04 |
Trunk Road T2
and Infrastructure Works for Developments at South Apron |
·
East Ventilation Building RC Structure ·
East Ventilation Building ABWF ·
East Ventilation Building E&M ·
East Bound – Wall & Crown ·
West Bound – OHVD ·
West Bound –Bulkhead Construction |
ED/2020/03 |
Trunk Road
T2 - Traffic Control And Surveillance System (TCSS)
and Associated Works (1) |
N/A |
Notes: (1): No major construction work was undertaken
during reporting month. N/A: Not applicable |
3.
Implementation of the key mitigation measures during the reporting
period are as follows:
Table
II
Summary of Key Mitigation Measures Implemented in the Reporting Month
Contract No. and Project
Title |
Key Mitigation Measures Implemented |
ED/2018/04 - Trunk Road
T2 and Infrastructure Works for Developments at South Apron |
Construction Noise ·
Construction activities were scheduled to minimize
noise nuisance to the nearby sensitive receiver. ·
Use of Quality Powered Mechanical Equipment (QPME) on
site. ·
Erected the noise barrier on site. Air Quality ·
Regularly watering on site to avoid dust generation. Landscape and Visual ·
Tree protection zones were fenced off to protect the
existing trees on site. |
ED/2020/03 - Trunk Road
T2 - Traffic Control And Surveillance System (TCSS)
and Associated Works (1) |
N/A |
Notes: (1): No major construction work was undertaken
during reporting month. N/A: Not applicable |
4.
Environmental monitoring for the Project was performed in accordance
with the EM&A Manual and the monitoring results were checked and reviewed.
Site Inspections/Audits were conducted once per week. The implementation of the
environmental mitigation measures, Event Action Plans and environmental
complaint handling procedures were also checked.
5. Summary of the
non-compliance (exceedance) in the reporting month for the Project is tabulated
in Table I.
Table
III
Non-compliance (exceedance) Record for the Project in the Reporting
Month
Environmental Monitoring |
No. of Non-compliance (Exceedance) |
No. of Non-compliance (Exceedance) due to Construction Activities of this
Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
0 |
0 |
N/A |
Marine Water
Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
Groundwater Level
Monitoring (Piezometer Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
Landfill Gas |
N/A (1) |
N/A |
N/A (1) |
N/A |
N/A |
Note: (1): No Action Level for Landfill Gas Monitoring. |
Air Quality
Monitoring
6. No Action/Limit Level exceedance
for 1-hour TSP monitoring was recorded.
7.
No Action Level exceedance and no Limit Level exceedance was recorded
for 24-hour TSP monitoring in the reporting month.
Construction Noise Monitoring
8. No Action Level exceedance
was recorded due to documented complaint in the reporting month. The Summary of
Documented Complaints in the Reporting Month is tabulated in Table IV.
9. No Limit Level exceedance
for day time construction noise monitoring were recorded in the reporting
month. Detail shall refer to Appendix N.
Water Quality Monitoring
10.
Groundwater quality monitoring had been suspended since October 2019
upon the agreement by EPD. Further details should be founded at Section 4.1.
11.
No marine water quality monitoring is required as no marine works will
be conducted at the Cha Kwo Ling and Lam Tin areas for this project.
12.
As the construction activity is approximately 120m away from the
piezometer gate, no piezometer monitoring is required.
Waste Management
13.
Wastes generated from this Project include inert construction and
demolition (C&D) materials, and non-inert C&D materials. Details of
waste management data is presented in Appendix
H.
Ecological Monitoring
14. No coral monitoring is
required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin
areas for this project.
Fisheries Impact Monitoring
15.
No specific fisheries monitoring programme is required during the
construction phase.
Monitoring on Cultural Heritage
16.
As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road
T2 to the TKOLTT at the Eastern Ventilation Building are located more than 100m
away from the Cha Kwo Ling Tin Hau temple, no monitoring on cultural heritage
is required.
Landscape and Visual
Monitoring and Audit
17. The implementation of
landscape and visual mitigation measures was checked by a registered landscape
architect. Recommended follow-up actions have been discharged by the
Contractor. Details of the audit
findings and implementation status are presented in Section 12.
Landfill Gas Monitoring
18. Monitoring of landfill
gases was commenced in December 2016. Since no excavation activity for this
Project was carried out within the Sai Tso Wan Landfill Consultation Zone in
the reporting month, no landfill gas monitoring is required
Hazard to Life Monitoring
19.
No environmental monitoring and
audit are required as no hazard assessment was conducted.
Environmental Site Inspection
20.
Joint weekly site inspections were conducted by representatives of the
Contractor, Engineer and Environmental Team. Details of the audit findings and
implementation status are presented in Section
12.
21.
Summary of key information in the reporting month is tabulated in Table II.
Table IV Summary of Complaints, Notifications
of Summons and Successful Prosecutions in the Reporting Month
Event |
Event Details |
Action Taken |
Status |
|
Number |
Nature |
|||
Complaints Received |
0 |
-- |
N/A |
N/A |
Notifications of any summons & prosecutions
received |
0 |
-- |
N/A |
N/A |
22.
Summary of complaints received in the reporting month is tabulated in Table III.
Table
V Summary of Complaints Details in
Reporting Month
Complaint Type |
Investigation Findings |
Follow-up Action / Mitigation Measure |
-- |
-- |
-- |
23.
No reporting change is recorded in the reporting months.
24.
The key works or activities will be anticipated in the next reporting
period are as follows:
Table VI Summary Table for Site Activities in the next
Reporting Period
Contract
No. and Project Title |
Site Activities (July 2024) |
Key Environmental Issues |
ED/2018/04 - Trunk Road T2 and Infrastructure Works for Developments
at South Apron |
·
East Ventilation Building RC Structure ·
East Ventilation Building ABWF ·
East Ventilation Building E&M ·
East Bound – Wall & Crown ·
West Bound – OHVD ·
West Bound –Bulkhead Construction |
(A) / (B)
/ (C) / (D) |
ED/2020/03 - Trunk Road T2 - Traffic Control And
Surveillance System (TCSS) and Associated Works (1) |
N/A |
|
Notes: (1): No major construction work was undertaken during reporting month. N/A: Not applicable (A)
Dust generation
from haul road, stockpile of dusty materials, exposed site area,
excavation works and rock breaking activities; (B)
Noisy construction activity such as
rock-breaking activities and piling works (C)
Runoff from exposed slope or site area; and (D)
Wastewater and runoff discharge from site. |
1.1
In 2009, Civil Engineering
and Development Department (CEDD) commissioned a Kai Tak Development (KTD) – Trunk Road
T2 and Infrastructure at South Apron Investigation. The
assignment covers the provision of the Trunk Road T2 and its connections with
the Central Kowloon Route (CKR) at the north apron area and the Tseung Kwan O –
Lam Tin Tunnel (TKOLTT) to the south in the Cha Kwo Ling area.
1.2
The Trunk Road T2 Project is one of the
designated Projects under Schedule 2 of the EIAO proposed
in the KTD. CEDD submitted the Project Profile (No. PP-379/2009) on 24 March
2009 for application for an EIA study brief for the Trunk Road T2 Project under
the EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2
Project was issued on 30 April 2009. The Environmental Impact Assessment
(EIA) Report for the Trunk Road T2 Project was approved under the Environmental
Impact Assessment Ordinance (EIAO) on 19 September 2013. The corresponding
Environmental Permit (EP) was issued on 19 September 2013 (EP no.:
EP-451/2013).
1.3
The Contract No. ED/2018/04 is the main
contract of Trunk Road T2 (“T2 Main Works”) which comprises mainly the design
and construction of a dual two-lane trunk road of approximately 3.0km long with
about 2.7km of the trunk road in form of tunnel; ventilation and administration
buildings, environmental protection and mitigation works and etc. Moreover, the
Contract No. ED/2020/03 is the other contract under Truck Road T2 Project which
comprises mainly design and construction of the TCSS for this Project. The
EM&A programme under the Contract ED/2018/04 and ED/2020/03 are governed by
the two EPs (EP-451/2013 and EP-458/2013/C) and two EM&A Manuals
(AEIAR-174/2013 and AEIAR-173/2013). The work areas of the T2 Main Works are
shown in Figure 1 and the works to
be executed under these Contracts and corresponding EPs are summarized as
follows:
Environmental
Permit |
Works
Description |
EP-451/2013 – Trunk Road T2 |
ED/2018/04 ● Construction
of highway and sub-sea tunnel connecting between Central Kowloon Route and
Cha Kwo Ling Tunnel ● Western
& Eastern Ventilation Buildings ED/2020/03 Design and
construction of TCSS for Trunk Road T2 |
EP-458/2013/C – Tseung Kwan O – Lam Tin
Tunnel (TKOLTT) and Associated Works |
ED/2018/04 ● Construction
of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the
Eastern Ventilation Building ED/2020/03 ● Design
and construction of TCSS for Trunk Road T2 |
Monitoring
Works in Lam Tin under EP-458/2013/C
1.4
Under Agreement No. CE 59/2015 (EP) – Tseung Kwan O – Lam Tin Tunnel
(TKOLLT) and Associated Works, the baseline monitoring works in Lam Tin under
the EM&A Manual (AEIAR-173/2013) were conducted by the Environmental Team
(ET) for the Agreement No. CE 59/2015 (EP) at the approved monitoring
locations, namely AM1, AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5.
Impact monitoring within the Lam Tin area shall be conducted by the ET of
Contract No. ED/2018/04 upon cessation of Agreement No. CE 59/2015 (EP). The
data obtained from the impact monitoring works completed by the ET of Agreement
No. CE 59/2015 (EP) will be adopted in this report.
1.5
Cinotech Consultants Ltd. was
designated as the Environmental Team (ET) to undertake the EM&A works for
“Trunk Road T2 and Infrastructure Works for Developments at the Former South
Apron” (hereinafter called the “Project”).
1.6
This is the 50th Monthly EM&A Report which
summarises the impact monitoring results and audit findings for the EM&A
programme during the reporting period in June 2024.
1.7
Different Parties with different levels of involvement in the Project
organization include:
•
Permit Holder – Civil Engineering and Development Department (CEDD)
•
Supervisor Representative – Hyder-Meinhardt Joint Venture (HMJV)
•
Environmental Team (ET) – Cinotech Consultants
Limited (Cinotech)
•
Independent Environmental Checker (IEC) – Ramboll Hong Kong Limited
(Ramboll)
•
Contractor – Bouygues Travaux Publics (BTP) (For ED/2018/04) & GTECH
Services (Hong Kong) Limited (For ED/2020/03)
1.8
The key contacts of the Project are shown in Table 1.1.
Table
1.1 Key Project Contacts
Party |
Role |
Contact Person |
Phone No. |
CEDD |
Permit Holder |
Mr. Wong Chi Wai,
Tommy |
3842 7111 |
HMJV |
Supervisor
Representative |
Ms. Hazel Tang |
2149 8524 |
Cinotech |
Environmental Team |
Mr. KS Lee (ETL) |
2151 2091 |
Ms. Karina Chan |
2157 3880 |
||
Ramboll |
Independent
Environmental Checker |
Mr. YH Hui |
3465 2850 |
BTP |
Contractor
(ED/2018/04) |
Mr. Roy Leung |
6628 2685 |
GTECH |
Contractor
(ED/2020/03) |
Mr. Deacon Choi |
6038 3568 |
|
1.9
The Organizational Structure for Environmental Management is shown in Figure 1.2.
1.10
The major site activities undertaken in the reporting month included:
Table 1.2 Summary
of Key Construction Work in the Reporting Month
Contract No. |
Project Title |
Site Activities |
ED/2018/04 |
Trunk Road
T2 and Infrastructure Works for Developments at South Apron |
·
East Ventilation Building RC Structure ·
East Ventilation Building ABWF ·
East Ventilation Building E&M ·
East Bound – Wall & Crown ·
West Bound – OHVD ·
West Bound –Bulkhead Construction |
ED/2020/03 |
Trunk Road T2
– Traffic Control And Surveillance System (TCSS) and
Associated Works (1) |
N/A |
Notes: (1): No major construction work was undertaken
during reporting month. N/A: Not applicable |
1.11
The EM&A programme requires construction noise, air quality
monitoring and environmental site audit, etc. The EM&A requirements for
each parameter are described in the following sections, including:
•
All monitoring parameters;
•
Action and Limit levels for all environmental parameters;
•
Event Action Plans;
•
Environmental mitigation measures, as recommended in the Project EIA
Report.
1.12
The advice on the implementation status of environmental protection and
pollution control/mitigation measures is summarized in Section 12 of this report.
1.13
This report presents the monitoring results, observations, locations,
equipment, period, methodology and QA/QC procedures of the monitoring
parameters of the required environmental monitoring works and audit works for
the Project in June 2024.
1.14
All permits/licenses obtained for the Project are summarized
in Table 1.3.
Table 1.3 Summary of Environmental License and Permit
Permit / License No. |
Valid Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-451/2013 |
19 Sep 2013 |
N/A |
Valid |
EP-458/2013/C |
20 Jan 2017 |
N/A |
Valid |
Notification
pursuant to Air Pollution (Construction Dust) Regulation |
|||
Ref. No.: 451120 |
20 Nov 2019 |
N/A |
Valid |
Billing Account
for Construction Waste Disposal |
|||
A/C No.: 7036016 |
09 Dec 2019 |
N/A |
Valid |
Construction
Noise Permit |
|||
CNP No. (For
Portion T1): GW-RE0188-24 |
23 Feb 2024 |
18 Aug 2024 |
Valid |
CNP No. (For
Portion Q):GW-RE0309-24 |
21 Mar 2024 |
31 Aug 2024 |
Valid |
CNP No. (For
Portion U):GW-RE0314-24 |
1 Apr 2024 |
30 Sep 2024 |
Valid |
Wastewater
Discharge License |
|||
WT00036699-2020 |
14 Jan 2021 |
31 Jan 2026 |
Valid |
Chemical
Waste Producer License |
|||
WPN:
5213-286-B2557-03 |
09 Mar 2020 |
N/A |
Valid |
2.1
According to Section 2.2.4 of the EM&A Manual (AEIAR-173/2013),
1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was conducted
to monitor the air quality for this Project. For regular impact monitoring, a
sampling frequency of at least once in every six days at all of the monitoring
stations for 1-hour and 24-hour TSP monitoring. Appendix A shows the established
Action/Limit Levels for the environmental monitoring works.
2.2
Five designated monitoring stations were selected for air quality
monitoring programme. Table 2.1
describes the air quality monitoring locations, which are also depicted in Figure 2.
Table 2.1 Air Quality Monitoring Locations
Location |
Location of Measurement |
|
AM1 |
Tin Hau Temple |
Ground Level |
AM2 |
Sai Tso Wan Recreation
Ground |
Ground Level |
AM3 |
Yau Lai Estate Bik Lai
House |
Rooftop (41/F) |
AM4(1) |
Sitting-out Area at Cha
Kwo Ling Village |
Ground Level |
AM4(B)(2) (*)(**) |
Flat 103 Cha Kwo Ling
Village |
Ground Level |
Remarks:
(1) For 1-hour TSP monitoring;
(2) For 24-hour TSP monitoring
(*) Air quality monitoring at designated
station AM4 (24-hr TSP) was rejected by the premise owners.
Therefore, baseline and impact air quality monitoring works were carried
out at alternative air quality monitoring stations AM4 (A) (24-hr TSP only)
(**) AM4(A) is not available for conducing
monitoring due to the demolition of administrative office.
2.3
Table 2.2 summarizes the monitoring
parameters, monitoring period and frequencies of impact air quality monitoring.
The monitoring schedule is shown in
Appendix D.
Table 2.2 Frequency and Parameters of Air
Quality Monitoring
Monitoring Stations |
Parameter |
Period |
Frequency |
AM1,
AM2, AM3, AM4 |
1-hour
TSP |
0700 –
1900 |
3 times
per 6 days |
AM1,
AM2, AM3, AM4(B) |
24-hour
TSP |
24 hours |
Once
every 6 days |
|
2.4
High Volume Samplers (HVS) in compliance with the specification
stipulated in the EM&A Manual (AEIAR-173/2013), Section 2.3.1, were used to
carry out 24-hour TSP monitoring. Direct reading dust meter were also used to
measure 1-hour average TSP levels. The 1-hour sampling was determined by HVS to
check the validity and accuracy of the results measured by direct reading
method.
2.5
Wind data monitoring equipment was set at rooftop (about 41/F) of Yau
Lai Estate Bik Lai House for logging wind speed and wind direction such that
the wind sensors are clear of obstructions or turbulence caused by building.
The wind data monitoring equipment is re-calibrated at least once every six
months and the wind directions are divided into 16 sectors of 22.5 degrees
each. The location is shown in Figure 2.
This weather information for the reporting month is summarized in Appendix C.
2.6
Table 2.3 summarizes the equipment
used for air quality monitoring by the ET for Contract No. CE 59/2015 (EP).
Copies of calibration certificates are attached in Appendix B.
Table 2.3 Air Quality Monitoring Equipment
Equipment |
Model |
Quantity |
1-hour
TSP Dust Meter |
Sibata Model No. LD-3B (Serial
No.: 2Y6194) Sibata Model No. LD-5R (Serial
No.: 972777, 972778, 972780, 8Y2374, 8Y2373) |
6 |
HVS
Sampler |
GMW
model: GS2310 (Serial
No.: 1287, 10379, 10599) |
3 |
TE 5170 (Serial
No.: 1956) |
1 |
|
Calibrator |
TISCH
Model: TE-5025A (Serial
No.: 3864) |
1 |
Wind
Anemometer |
Davis
Weather Monitor II, Model no. 7440 (Serial
No.: MC01010A44) |
1 |
1-hour TSP Monitoring
Measuring Procedures
2.7
The measuring procedures of the 1-hour dust meter are in accordance with
the Manufacturer’s Instruction Manual as follows:
(Sibata Model No.: LD-5R)
●
The 1-hour dust meter is placed at least 1.3 meters above ground.
●
Set POWER to “ON” and make sure that the battery level was not flash or
in low level.
●
Allow the instrument to stand for about 3 minutes and then the cap of
the air sampling inlet has been released.
●
Push the knob at MEASURE position.
●
Set time/mode setting to [BG] by pushing the time setting switch. Then, start the background measurement by
pushing the start/stop switch once. It
will take 6 sec. to complete the background measurement.
●
Push the time setting switch to change the time setting display to
[MANUAL] at the bottom left of the liquid crystal display. Finally, push the
start/stop switch to stop the measuring after 1 hour sampling.
●
Information such as sampling date, time, count value and site condition
were recorded during the monitoring period.
Maintenance/Calibration
2.8
The following maintenance/calibration is required for the 1-hour dust
meter:
●
Check and calibrate the meter by HVS to check the validity and accuracy
of the results measured by direct reading method at 2-month intervals
throughout all stages of the air quality monitoring.
24-hour TSP Monitoring
Instrumentation
2.9
High volume samplers (HVS) (TISCH Model: TE-5170 and GMW Model: GS2310)
completed with appropriate sampling inlets were employed for 24-hour TSP
monitoring. The sampler was composed of
a motor, a filter holder, a flow controller and a sampling inlet and its
performance specification complied with that required by USEPA Standard Title
40, Code of Federation Regulations Chapter 1 (Part 50).
2.10
The positioning of the HVS samplers are as follows:
●
A horizontal platform with appropriate support to secure the samplers
against gusty wind shall be provided;
●
No two samplers shall be placed less than 2 meters apart;
●
The distance between the sampler and an obstacle, such as buildings,
must be at least twice the height that the obstacle protrudes above the
sampler;
●
A minimum of 2 metres of separation from walls, parapets and penthouses
is required for rooftop samplers;
●
A minimum of 2 metres of separation from any supporting structure,
measured horizontally is required;
●
No furnace or incinerator flue is nearby;
●
Airflow around the sampler is unrestricted;
●
The sampler is more than 20 metres from the dripline;
●
Any wire fence and gate, to protect the sampler, shall not cause any
obstruction during monitoring;
●
Permission must be obtained to set up the samplers and to obtain access
to the monitoring stations; and
●
A secured supply of electricity is needed to operate the samplers.
Operating/analytical
procedures for the operation of HVS
2.11
Operating/analytical procedures for the air quality monitoring are
highlighted as follows:
●
Prior to the commencement of the dust sampling, the flow rate of the
high-volume sampler was properly set (between 0.6 m3/min. and 1.7 m3/min.)
in accordance with the EM&A manual (AEIAR-173/2013). The flow rate shall be
indicated on the flow rate chart.
●
For TSP sampling, fiberglass filters with a collection efficiency of
> 99% for particles of 0.3μm diameter were used.
●
The power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5
minutes to establish thermal equilibrium before placing any filter media at the
designated air monitoring station.
●
The filter holding frame was then removed by loosening the four nuts and
a weighted and conditioned filter was carefully centered
with the stamped number upwards, on a supporting screen.
●
The filter was aligned on the screen so that the gasket formed an
airtight seal on the outer edges of the filter.
Then the filter holding frame was tightened to the filter holder with
swing bolts. The applied pressure should be sufficient to avoid air leakage at
the edges.
●
The shelter lid was closed and secured with the aluminium strip.
●
The timer was then programmed.
Information was recorded on the record sheet, which included the
starting time, the weather condition and the filter number (the initial weight
of the filter paper can be found out by using the filter number).
●
After sampling, the filter was removed and sent to the HOKLAS laboratory
(ALS Technichem (HK) Pty Ltd.) for weighing. The elapsed time was also recorded.
●
Before weighing, all filters were equilibrated in a conditioning
environment for 24 hours. The conditioning environment temperature should be
between 25°C and 30°C and not vary by more than ±3°C; the relative humidity
(RH) should be < 50% and not vary by more than ±5%. A convenient working RH
is 40%.
Maintenance/Calibration
2.12
The following maintenance/calibration is required for the HVS:
●
The high-volume motors and their accessories were properly maintained.
Appropriate maintenance such as routine motor brushes replacement and
electrical wiring checking were made to ensure that the equipment and necessary
power supply are in good working condition.
High volume samplers were
calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout
all stages of the air quality monitoring.
2.13
The impact monitoring works for air quality monitoring locations AM1,
AM2, AM3 and AM4 are completed by the ET of Agreement No. CE 59/2015 (EP), and
the data will be adopted in this report. As the proposal for relocation
approved, the monitoring at AM4(A) will be conducted at AM4(B). For the time
being, as the station CKL2 for the 24 hr TSP monitoring, carried out under
EM&A works for Trunk Road T2 Project (EP- 451/2013), is located in close
proximity to AM4(B); the results from CKL2 are adopted as reference for the 24
TSP monitoring at AM4(B), which has similar environment when compared with that
for CKL2. The location of monitoring station CKL2 is shown in Figure 2.
2.14
The impact air quality monitoring was conducted at all five monitoring
stations as scheduled. The monitoring schedule is shown in Appendix D.
2.15
No Action Level exceedance was recorded for 24-hour TSP
monitoring in the reporting month and No Limit Level exceedance was recorded
for 24-hour TSP monitoring in the reporting month.
2.16
No Action/Limit Level exceedance was recorded for 1-hour TSP monitoring
in the reporting month.
2.17
The monitoring data and graphical presentations of 1-hour and 24-hour
TSP monitoring results are shown in Appendix
E and Appendix F respectively.
2.18
According to field observations by ET for Agreement No. CE 59/2015 (EP)
in the reporting period, the major dust source identified at the designated air
quality monitoring stations are as follows:
Table 2.4 Major Dust Source during Air Quality Monitoring
Monitoring Stations |
Major Dust Source |
AM1 – Tin Hau Temple |
Road
Traffic at Cha Kwo Ling Road, non-project related influence and the
construction activity from other construction site (i.e
underground utility work in TKOLTT project) |
AM2 – Sai Tso Wan Recreation Ground |
Road
Traffic along Sin Fat Road |
AM3 – Yau Lai Estate Bik Lai House |
Road
Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related
influence and the construction activity from other construction site (i.e road paving work in TKOLTT project) |
AM4 - Sitting-out Area at Cha Kwo Ling Village |
Road
Traffic at Cha Kwo Ling Road |
AM4(B) (**) - Flat 103 Cha Kwo Ling Village |
Road
Traffic at Cha Kwo Ling Road (*) |
(*): Field observation observed at CKL2 during monitoring
is presented. Detail refers to S2.13. (**) AM4(A) is not available for conducing monitoring
due to the demolition of administrative office. |
2.19
The air monitoring data was compared with the predictions (with the
assessment height of 1.5 mAG) in Table 3.17 of EIA
Report, AEIAR-173/2013 (as approved in 2013) as summarised in Table 2.5 and Table 2.6.
Table 2.5 Comparison of 1-hr TSP Monitoring Data with Predictions in EIA
Report
Monitoring Stations |
ASR ID |
Predicted Maximum 1-hr TSP Concentration in EIA Report
(AEIAR-173/2013), μg/m3 |
Maximum 1-hr TSP Concentration in
the Reporting Month |
AM1 – Tin Hau Temple |
CL1 |
707 |
66.5 |
AM2 – Sai Tso Wan
Recreation Ground |
CL6 |
266 |
73.6 |
AM3 – Yau Lai Estate Bik
Lai House |
CL9 |
507 |
89.3 |
AM4 - Sitting-out Area at
Cha Kwo Ling Village |
CL16 |
430 |
79.8 |
Table 2.6 Comparison of 24-hr TSP Monitoring Data
with Predictions in EIA Report
Monitoring Stations |
ASR ID |
Predicted Maximum 24-hr TSP Concentration in EIA
Report (AEIAR-173/2013), μg/m3 |
Maximum 24-hr TSP Concentration in
the Reporting Month |
AM1 – Tin Hau Temple |
CL1 |
199 |
84.4 |
AM2 – Sai Tso Wan
Recreation Ground |
CL6 |
109 |
22.8 |
AM3 – Yau Lai Estate Bik
Lai House |
CL9 |
123 |
17.1 |
AM4(B) – Flat 103 Cha Kwo
Ling Village (*) |
N/A
(1) |
N/A
(1) |
180.7
(**) |
Remarks:
(1)
No 24-hr TSP concentration was predicted in
EIA Report (AEIAR-173/2013)
(*) Air quality monitoring at designated station AM4
(24-hr TSP) was rejected by the premise owners. Therefore, baseline and impact
air quality monitoring works were carried out at alternative air quality
monitoring stations AM4 (B) (24-hr TSP only)
(**): Monitoring results at CKL2 is presented. Detail
refers to S2.13
2.20
In the reporting month, the 1-hour TSP concentrations at AM1, AM2, AM3
and AM4 were lower than the prediction in the EIA Report, AEIAR-173/2013 (as
approved in 2013). No Action/Limit level exceedance was recorded in the
reporting period.
2.21
In the reporting month, the 24-hour TSP concentrations at AM1, AM2 and
AM3 were lower than the prediction in the EIA Report, AEIAR-173/2013 (as
approved in 2013). No Action Level exceedance was recorded for 24-hour TSP
monitoring in the reporting month and no Limit Level exceedance was recorded
for 24-hour TSP monitoring in the reporting month.
3.1
According to Section 3.2.1 of the EM&A Manual (AEIAR-173/2013),
construction noise monitoring was conducted to monitor the construction noise
arising from the construction activities. The regular monitoring frequency for
each monitoring station shall be on a weekly basis and conduct one set of
measurements between 0700 and 1900 hours on normal weekdays. Appendix A shows the established Action
and Limit Levels for the environmental monitoring works.
3.2
Noise monitoring was conducted at five designated monitoring stations,
namely CM1, CM2, CM3, CM4 and CM5 in the reporting period. Table 3.1 and Figure 2
show the locations of these stations.
Table 3.1 Noise Monitoring Stations
Monitoring Stations |
Location |
Location of Measurement |
CM1 |
Nga Lai House, Yau Lai Estate Phase 1, Yau Tong |
Rooftop
(41/F) |
CM2 |
Bik Lai House, Yau Lai Estate Phase 1, Yau Tong |
Rooftop
(41/F) |
CM3 |
Block S, Yau Lai Estate Phase 5, Yau Tong |
Rooftop
(40/F) |
CM4 |
Tin Hau Temple, Cha Kwo Ling |
Ground
Level |
CM5 |
CCC Kei Faat Primary School, Yau Tong |
Rooftop
(6/F) |
3.3
Table 3.2 summarizes the monitoring
parameters, frequency and total duration of monitoring. The noise monitoring schedule is shown in Appendix D.
Table 3.2 Frequency and Parameters of Noise Monitoring
Monitoring Stations |
Time Period |
Duration |
Frequency |
Parameter |
Measurement |
CM1 |
0700-1900
hrs on normal weekdays |
30
minutes |
Once
per week |
L10(30 min.)
dB(A) L90(30
min.) dB(A) Leq(30 min.) dB(A) |
Façade
Measurement |
CM2 |
Façade
Measurement |
||||
CM3 |
Façade
Measurement |
||||
CM4 |
Façade
Measurement |
||||
CM5 |
Façade
Measurement |
3.4
Integrating Sound Level Meter was used for impact noise monitoring. The
meters were Type 1 sound level meter capable of giving a continuous readout of
the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx)
that also complied with International Electrotechnical Commission Publications
651:1979 (Type 1) and 804:1985 (Type 1) specifications. Table 3.3 summarizes the noise monitoring equipment being used by
the ET for Agreement No. CE 59/2015 (EP) within the reporting period. Copies of
calibration certificates are attached in Appendix
B.
Table 3.3 Noise Monitoring Equipment
Equipment |
Model |
Quantity |
Integrating Sound Level Meter |
BSWA 308 (Serial No.: 580287,
570187, 570188, 570183) SVAN 957 (Serial No.: 23851) SVAN 979 (Serial No.: 27189) |
6 |
Calibrator |
AWA6021A
(Serial No.: 1023253) ST-120
(Serial No.: 181001636) Type 4231
(Serial No.: 2326353) |
3 |
3.5
The monitoring procedures are as follows:
●
The monitoring station was normally be at a point 1m from the exterior of
the sensitive receivers building façade and be at a position 1.2m above the
ground.
●
For free field measurement, the meter was positioned away from any
nearby reflective surfaces. All records for free field noise levels were
adjusted with a correction of +3 dB(A).
●
The battery condition was checked to ensure the correct functioning of
the meter.
●
Parameters such as frequency weighting, the time weighting and the
measurement time were set as follows:
-
Frequency weighting: A
-
Time weighting: Fast
-
Time measurement: 30 minutes
●
Prior to and after each noise measurement, the meter was calibrated
using a Calibrator for 94.0 dB at 1000 Hz.
If the difference in the calibration level before and after measurement
was more than 1.0 dB, the measurement would be considered invalid and repeat of
noise measurement would be required after re-calibration or repair of the
equipment.
●
The wind speed was frequently checked with the portable wind meter.
●
At the end of the monitoring period, the Leq,
L90 and L10 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
●
Noise monitoring would be cancelled in the presence of fog, rain, and
wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
Supplementary monitoring would be provided to ensure sufficient data would be
obtained.
3.6
The microphone head of the sound level meter and calibrator were cleaned
with a soft cloth at quarterly intervals.
3.7
The sound level meter and calibrator were checked and calibrated at
yearly intervals.
3.8
Immediately prior to and following each noise measurement the accuracy
of the sound level meter was checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements were accepted as
valid only if the calibration levels from before and after the noise
measurement agree to within 1.0 dB.
3.9
The data obtained from the impact monitoring works completed by the ET
of Agreement No. CE 59/2015 (EP) will be adopted in this report.
3.10
No Action Level exceedance was recorded due to the documented complaint
in the reporting month.
3.11
No Limit Level exceedance was recorded for day-time construction noise
monitoring in the reporting month.
3.12
Noise monitoring results and graphical presentations are shown in Appendix
G.
3.13
According to field observations by ET for Agreement No. CE 59/2015 (EP)
in the reporting period, the major noise sources identified at the noise
monitoring stations are shown in Table 3.4.
Table 3.4 Other Noise Source Identified during Noise Monitoring
Monitoring Stations |
Major Noise Source |
CM1 |
Road Traffic near
Eastern Cross Harbour Tunnel Toll Plaza, non-project related construction
activities (i.e road paving work in TKOLTT project) |
CM2 |
Road Traffic near Eastern
Cross Harbour Tunnel Toll Plaza, non-project related construction activities
(i.e road paving work in TKOLTT project) |
CM3 |
Road Traffic near
Eastern Cross Harbour Tunnel Toll Plaza non-project related construction
activities (i.e road paving work in TKOLTT project) |
CM4 |
Road Traffic at Cha Kwo Ling Road, non-project related
construction activities (i.e underground utility work
in TKOLTT project) |
CM5 |
Road Traffic near Eastern Cross Harbour Tunnel Toll
Plaza, Road Traffic at Yau Tong Road |
.
Table 3.5 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Monitoring Stations |
Baseline Noise Level, dB (A) |
Noise Limit Level, dB (A) (at 0700 – 1900 hrs on normal weekdays) |
CM1 |
65.5 |
75 |
CM2 |
63.6 |
|
CM3 |
65.6 |
|
CM4 |
62.0 |
|
CM5 |
68.2 |
70* |
(*) Noise
Limit Level is 65 dB(A) during school examination periods.
3.14
The noise monitoring data was compared with the predictions in Table
4.15 of EIA Report (AEIAR-173/2013) as summarised in Table 3.6.
Table 3.6 Maximum
Predicted Mitigated Construction Noise Levels in EIA Report
Monitoring Stations |
NSR ID |
Maximum Predicted Mitigated Construction Noise Levels
in EIA Report (AEIAR-173/2013), dB(A) |
Maximum Construction Noise Levels in the Reporting
Month |
CM1 – Nga
Lai House, Yau Lai Estate Phase 1, Yau Tong |
N1102 |
73 |
67.0 |
CM2 –
Bik Lai House, Yau Lai Estate Phase 1, Yau Tong |
N1204 |
75 |
68.0 |
CM3 – Block S, Yau
Lai Estate Phase 5, Yau Tong |
N2105 |
75 |
65.0 |
CM4 –
Tin Hau Temple, Cha Kwo Ling |
N3101a |
73 |
59.0 |
CM5 – CCC
Kei Faat Primary School, Yau Tong |
N4101 |
71 |
67.0 |
3.15 The results at CM1, CM2,
CM3, CM4 and CM5 were lower than the maximum predicted mitigated construction
noise level in EIA Report, AEIAR-173/2013 (as approved in 2013). No Limit level
exceedance was recorded in the reporting period.
Groundwater
Quality
4.1
The existing groundwater quality monitoring programme has been suspended
as the monitoring results had been deemed non-representative of the impact from
the project justified by two major factors: (1) influence on the monitoring
results from non-project related factors, such as anthropogenic activities and
natural phenomenon; and (2) large separation between the monitoring stations
and works area. In addition, as no alternative locations for the groundwater
quality monitoring were available, the groundwater quality monitoring has been
suspended since October 2019 upon the agreement by EPD.
Marine
Water Quality
4.2
According to Section 4.4.3 of EM&A Manual (AEIAR-173/2013), marine
water quality impact monitoring stations is carried out during marine
construction for TKOLTT reclamation. Since the construction of Cha Kwo Ling
Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation
Building does not involve reclamation, the marine water quality monitoring
programme stated in Section 4.4 of the EM&A Manual (AEIAR-173/2013) is
therefore not applicable to Contract No. ED/2018/04.
Groundwater
Level Monitoring (Piezometer Monitoring)
4.3
According to Section 4.1.2 of EM&A Manual (AEIAR-173/2013), daily
piezometer monitoring will be carried out on a daily basis when any tunnel
construction activities are carried out within +/- 50m of the piezometer gate
in plan. As the construction works of Cha Kwo Ling Tunnel from the end of Trunk
Road T2 to the TKOLTT at the Eastern Ventilation Building is approximately 120m
away from the piezometer gate in plan, the piezometer monitoring programme
stated in Section 4.2 of the EM&A Manual (AEIAR-173/2013) is therefore not
applicable to Contract No. ED/2018/04.
5.1
According to Section 5.1.2 of the EM&A Manual (AEIAR-173/2013),
Waste materials generated during construction activities, such as construction
and demolition (C&D) materials and general refuse, are recommended to be
audited at regular intervals (at least quarterly) to ensure that proper
storage, transportation and disposal practices are being implemented by the
Contractor. To fulfil this requirement, site audits are carried out on a weekly
basis. The summaries of site audits are attached in Appendix I.
5.2
With reference to relevant handling records of this Project, the
quantities of different types of waste generated in the reporting month are
summarised and presented in Appendix H.
Post-Translocation
Coral Monitoring
6.1
Post-translocation monitoring survey is recommended in Section 6.2.5 of
the EM&A Manual (AEIAR-173/2013), to audit the success of coral
translocation. Since the construction of Cha Kwo Ling Tunnel from the end of
Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not
involve any marine works in the concerned area mentioned in Section 6.1.2 of
the EM&A Manual (AEIAR-173/2013), the post-translocation monitoring survey
stated in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013) is therefore not
applicable to Contract No. ED/2018/04.
7.1
According to Section 7.1.3 of EM&A Manual (AEIAR-173/2013), no
specific fisheries monitoring programme is required during the construction
phase.
7.2
The implementation of the mitigation measures stated in the Water
Quality Impact Assessment (Refer to Section 5 of EIA Report (AEIAR-173/2013))
will be audited as part of the EM&A procedures during the construction
period. The summaries of site audits are attached in Appendix I.
8.1
According to Condition 3.7 of EP-458/2013/C and Section 8.2.1 of the
EM&A Manual (AEIAR-173/2013), monitoring of vibration impacts was
conducted when the construction works are less than 100m from the Built
Heritage in close proximity of the worksite, namely the Cha Kwo Ling Tin Hau
temple. Tilting and settlement monitoring should be applied on the Cha Kwo Ling
Tin Hau Temple.
8.2
As the construction works of Cha Kwo Ling Tunnel from the end of Trunk
Road T2 to the TKOLTT at the Eastern Ventilation Building are located more than
100m away from the Cha Kwo Ling Tin Hau temple, the vibration impact monitoring
stated in Section 8.3.1 of the EM&A Manual (AEIAR-173/2013) is not
applicable to Contract No. ED/2018/04.
Mitigation
Measures for Cultural Heritage
8.3
According to Condition 3.6 of EP-458/2013/C, to prevent damage to Cha
Kwo Ling Tin Hau Temple and its Fung Shui rocks (Child-given rocks) during the
construction phase, a temporarily fenced-off buffer zone (Rocks buffer zone is
5 m from the edge of Rocks and 15m from the edge of Rocks alter) with allowance
for public access (minimum 1 m) around the temple and the Fung Shui rocks shall
be provided. The open yard in front of the temple should be kept as usual for
annual Tin Hau festival.
8.4 As there is a large buffer
distance from the current works to Cha Kwo Ling Tin Hau Temple and the Fung
Shui rocks (Child-given rocks), the temporarily fenced-off rocks buffer zone
and from the edge of Rocks alter is not required. The fenced-off rocks buffer
zone would be implemented when there are construction activities in vicinity of
the cultural heritage.
9.1
According to Section 9.3 of the EM&A Manual (AEIAR-173/2013),
landscape and visual mitigation measures during the construction phase shall be
checked to ensure that they are fully realized and implemented on site.
9.2
Site audits were carried out on a weekly basis to monitor and audit the
timely implementation of landscape and visual mitigation measures listed in
“Environmental Mitigation Implementation Schedule (EMIS)” (shown in Appendix
J).
9.3
The implementation of landscape and visual mitigation measures was
checked by a registered landscape architect. No non-compliance of the landscape
and visual impact was recorded in the reporting month. Details of the audit
findings and implementation status are presented in Appendix I.
10.1
In accordance with Section 10.1.1 of the EM&A Manual
(AEIAR-173/2013), monitoring of landfill gas is required for construction works
within the Sai Tso Wan Landfill Consultation Zone during the construction
phase. Since no excavation activity for this Project was carried out within the
Sai Tso Wan Landfill Consultation Zone in the reporting month, no landfill gas
monitoring is required.
11.1
According to Section 11.1.1 of EM&A Manual (AEIAR-173/2013), as no
overnight storage of explosive on site is required for the construction of the
Project, the hazard assessment is deemed not necessary. Thus, environmental
monitoring and audit is not required.
12.1
Site audits were carried out on a weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures in the Project site. The summaries of site audits are attached in Appendix
I.
12.2
Site audits were conducted on 06, 13, 20 & 27 June 2024 in the reporting
month. Site inspection of the IEC was conducted on 27 June 2024. No non-compliance was
observed during the site audit.
12.3
According to Environmental Permits, the approved EIA Reports (Register
No.: AEIAR-174/2013 and AEIAR-173/2013), and the EM&A Manuals of the
Project (AEIAR-174/2013 and AEIAR-173/2013), the mitigation measures detailed
in the documents are recommended to be implemented during the construction
phase. An Environmental Mitigation Implementation Schedule (EMIS) is provided
in Appendix J.
12.4
The ET weekly site inspections were carried out during the reporting
month and the observations and recommendations are summarized in Table 12.1.
Refer to Appendix I for the site inspection summary reports in the
reporting month.
Table 12.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air
Quality |
N/A |
N/A |
N/A |
Noise |
N/A |
N/A |
N/A |
Water
Quality |
N/A |
N/A |
N/A |
Ecology |
N/A |
N/A |
N/A |
Landscape
and Visual |
N/A |
N/A |
N/A |
Waste/Chemical
Management |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Permits
/Licences |
N/A |
N/A |
N/A |
12.5
The Event and Action Plans for air quality and construction noise
monitoring, and the Limit Levels and Action Plan for landfill gas monitoring
are presented in Appendix L.
Air Quality
Monitoring
●
No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded
in the reporting month.
●
No Action Level exceedance for 24-hour TSP monitoring was recorded in
the reporting month and no Limit Level exceedance for 24-hour TSP monitoring
was recorded in the reporting month.
Construction Noise Monitoring
● No Action Level exceedance was
recorded due to the documented complaint in the reporting month.
● No Limit Level exceedance
for construction noise monitoring was recorded in the reporting month.
13.1
The summaries of environmental complaint, warning, summon and
notification of successful prosecution for the Project is presented in Appendix M.
13.2
The summary of exceedance record in the reporting month is shown in Appendix N.
14.1
Tentative construction programmes for the next three months are provided
in Appendix O.
14.2
Major site activities undertaken for the coming months are summarized as
follows:
Table 14.1 Site Activities and the Key Environmental Issues in
the next Reporting Period
Contract No. and Project Title |
Site
Activities (July 2024) |
Key Environmental Issues |
ED/2018/04 - Trunk Road T2 and Infrastructure
Works for Developments at South Apron |
1)
East Ventilation Building RC Structure 2)
East Ventilation Building ABWF 3)
East Ventilation Building E&M 4)
East Bound – Wall & Crown 5)
West Bound – OHVD 6)
West Bound – Bulkhead Construction |
·
Wheel washing bay at site exits; ·
Temporary noise barriers for PMEs; ·
Sedimentation tank for settling muddy water; and ·
Make sure open stockpiles are covered during rainstorm. |
ED/2020/03 - Trunk Road T2 - Traffic
Control And Surveillance System (TCSS) and
Associated Works (1) |
N/A |
|
Notes: (1): No major construction work was undertaken during reporting month. N/A: Not applicable |
14.3
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
15.1
This is the 50th Monthly EM&A Report
which presents the EM&A works undertaken during the reporting month in
accordance with the EM&A Manual (AEIAR-173/2013) and the requirement under
EP.
Air Quality Monitoring
15.2
No Action/Limit Level exceedance was recorded for 1-hour TSP monitoring
in the reporting month.
15.3
No Action Level exceedance for 24-hour TSP monitoring was recorded in
the reporting month and no Limit Level exceedance for 24-hour TSP monitoring
was recorded in the reporting month.
Construction Noise
Monitoring
15.4
No Action Level exceedance was recorded due to documented complaint in
the reporting month.
15.5
No Limit Level exceedance for construction noise monitoring was recorded
in the reporting month.
Site Audit
15.6
Four (4) ET joint weekly environmental site
inspections were conducted for the Contract No. ED/2018/04 in the reporting
month.
Complaint, Notification of Summons
and Successful Prosecution
15.7
No environmental complaint was received in the reporting period. No
notifications of summons and successful prosecutions were received in the
reporting month.
15.8
According to the environmental audit performed in the reporting month,
the following recommendations were made:
ED/2018/04
●
N.A.