1.1.1
The Kai Tak
Development is located in the south-eastern part of Kowloon Peninsula of the
HKSAR, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma
Tau Kok, Kowloon Bay, Kwun
Tong and Cha Kwo Ling.
1.1.2
Contract No. KL/2014/03 is the works package
to construct an approximately 420m long supporting underground structure (SUS)
underneath Shing Cheong Road and Cheung Yip Street.
The EM&A programme under this Contract is governed by three EPs (EP-337/2009, EP-339/2009/A and
EP-451/2013) and two EM&A Manuals (AEIAR-130/2009 and AEIAR-174/2013). The
Works to be executed under this Contract and corresponding EPs include but not
be limited to the following main items:
EP-451/2013 – Trunk
Road T2
(i)
Construction of approximately 420m long
supporting underground structure (SUS) including diaphragm walls, barrettes,
piled foundation, top and bottom slabs, end wall and adits
underneath Shing Cheong Road and Cheung Yip Street;
EP-337/2009 – New
Distributor Roads Serving the Planned Kai Tak
Development
(ii)
Widening and re-alignment of Cheung Yip
Street of approximately 330m long and associated footpaths;
(iii)
Demolition, reconstruction and widening of Shing Cheong Road of approximately 410m long and associated
footpaths;
(iv)
Construction of drainage outfall and
modification of existing seawall;
(v)
Construction of ancillary works including
surface drainage, sewerage, water, fire fighting,
street lighting, street furniture, road marking, road signage, utilities and
services, irrigation and landscape works.
EP-339/2009/A
– Decommissioning of the Remaining Parts (Ex-GFS Building, Radar Station and
Hong Kong Aviation Club) of the former Kai Tak
Airport
(vi)
Demolition of RADAR Tower and guard house;
Other works not
covered by any EP
(vii)
Construction of two subways between Phase II
of New Acute Hospital (Site A) and Hong Kong Children’s Hospital (Site C), and
between Phase I of New Acute Hospital (Site B) and Site C;
(viii)
Construction of District Cooling System (DCS)
along Cheung Yip Street and Shing Cheong Road
1.1.3
The location and boundary of the site is
shown in Figure 1.
1.2.1
The project proponent was the Civil
Engineering and Development Department, HKSAR (CEDD). Hyder
Meinhardt Joint Venture (HMJV) was commissioned by
CEDD as the Engineer for the Project. Ramboll Environ
Hong Kong Limited was commissioned as the Independent Environmental Checker
(IEC). China Road and Bridge Corporation (Hong Kong) (CRBC) was appointed as
the main contractor for the construction works under the contract KL/2014/03. MateriaLab Consultants Limited (MCL) was appointed as the
Environmental Team (ET) by CEDD to implement the EM&A programme
for the Project.
1.2.2
The organization structure is shown in Appendix B.
The key personnel contact names and numbers for the Project are summarized in Table
1.1.
1.3.1
The construction of the Project commenced in
February 2016 and is expected to complete in 2020. The construction programme is shown in Appendix
A.
1.3.2
A summary of the major construction activities undertaken in the
reporting month were:
Temporary utility diversion;
Implementation of Temporary Traffic Arragement (TTA);
Construction of Socket H piles;
Excavation and Earth Lateral Support (ELS) construction for
Supporting Underground Structure (SUS).
Construction of Subway B;
Construction of guide walls and D-walls; and
Construction of District Cooling System Works.
1.4.1
According to the construction activities in
the construction programme mentioned in Section
1.3.2, the following environmental protection/ mitigation measures including
Air Quality Impact, Construction Noise Impact, Water Quality Impact, Chemical
and Waste Management, Landscape and Visual Impact shall be implemented:
Sufficient
watering of the works site with the active dust emitting activities;
Limitation
of the speed for vehicles on unpaved site roads;
Properly
cover or enclosure of the stockpiles and dusty materials;
Good site
practices on loading dusty materials;
Providing
sufficient vehicles washing facilities at every vehicle exit point;
Good
maintenance to the plant and equipment;
Use of
quieter plant and Quality Powered Mechanical Equipment (QPME);
Use of
acoustic fabric and noise barrier;
Using the
approved Non-road Mobile Machineries (NRMMs);
Proper
storage and handling of chemical;
Appropriate
desilting, oil interceptors or sedimentation devices provided on site for
treatment before discharge;
Onsite
waste sorting and implementation of trip ticket system;
Training
of the site personnel in proper waste management and chemical waste handling
procedures;
Proper
storage of the construction materials;
Erection
of decorative screen hoarding;
Strictly
following the Environmental Permits and Licenses;
Provide
sufficient mitigation measures as recommended in Approved EIA Reports
1.5.1
A summary of the relevant environmental
licenses, permits and/or notifications on environmental protection for this
Contract is presented in Table
1.2.