Summary of Site Audit in the Reporting Month

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

17 May 2017

Open stockpile shall be covered with impermeable sheeting to prevent dust emission. (Zone 4)

The item was rectified by the Contractor and inspected on 1 June 2017.

25 May 2017

Open stockpile shall be covered with impermeable sheeting to prevent dust emission. (Zone 4)

The item was rectified by the Contractor and inspected on 1 June 2017.

Noise

NA

Water Quality

4 May 2017

The muddy water in the entrance gate of Zone 2 shall be bunded to prevent leakage of muddy water to the public haul road. Bunding shall be provided. (Zone 2)

The item was rectified by the Contractor and inspected on 11 May 2017.

Chemical and Waste Management

25 May 2017

General refuse shall be stored in enclosed bin and removed regularly. (Zone 3)

The item was rectified by the Contractor and inspected on 1 June 2017.

Land Contamination

 

NA

 

Landscape and Visual Impact

 17 May 2017

Open stockpiles shall be covered by unobtrusive sheeting to prevent dust and dirt spreading to adjacent landscape areas and vegetation, and to create a neat and tidy visual appearance. (Zone 4)

The item was rectified by the Contractor and inspected on 1 June 2017.

25 May 2017

Open stockpiles shall be covered by unobtrusive sheeting to prevent dust and dirt spreading to adjacent landscape areas and vegetation, and to create a neat and tidy visual appearance. (Zone 4)

The item was rectified by the Contractor and inspected on 1 June 2017.

General Condition

11 May 2017

Stagnant water shall be removed. (Portion I and Zone1)

The item was rectified by the Contractor and inspected on 17 May 2017.

25 May 2017

Stagnant water shall be removed. (Portion I and Zone1)

The item was rectified by the Contractor and inspected on 1 June 2017.