7.            ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE

 

7.1         Environmental Exceedance

 

7.1.1     No Action / Limit Level exceedance was recorded for 24-hr TSP and construction noise at KTD1a, KTD2a and KER1b in the reporting month.

 

7.2         Complaints, Notification of Summons and Prosecution

 

7.2.1     A complaint received on 16 July 2017 was referred from the 1823 regarding the muddy water discharge at Kai Tak River by CEDD project.

 

The notification of complaint was received by ET on 27 July 2017.

 

7.2.2     No notification of summons and successful prosecution were received in the reporting month.

 

7.2.3     Cumulative complaint log, summaries of complaints, notification of summons and successful prosecutions are presented in Appendix L.