9.            FUTURE KEY ISSUES

 

9.1         Construction Programme for the Next Two Months

 

ž   Setup of temporary barging point;

ž   Drainage works (CH100 to CH240);

ž   Sewerage works;

ž   Seawall Modification Works;

ž   Construction of tunnel box structure;

ž   D-wall construction works;

ž   Guide wall construction works;

ž   Construction of socket H-pile;

ž   Pumping test for Zone 4;

ž   Excavation and ELS construction; and

ž   Installation of dewatering, observation and recharging wells.

 

9.2         Key Issues for the Coming Month

 

9.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management and landscape and visual impact.

 

9.3         Monitoring Schedules for the Next Three Months

 

9.3.1     The tentative schedules for environmental monitoring in the coming three months are provided in Appendix E.