Summary
of Site Audit in the Reporting Month
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Air Quality |
6 July 2017 |
Stockpile of excavated materials shall be covered with impervious
sheeting. (Zone 4) |
The item was rectified by the Contractor and inspected on
13 July 2017. |
13 July 2017 |
Spent bags of cement shall be stored properly. (Zone 3) |
The item was rectified by the Contractor and inspected on
19 July 2017. |
|
Noise |
27 July 2017 |
Contractor was reminded to close the door of the air compressor to
reduce noise emission. (Zone 4) |
The item was rectified by the Contractor and inspected on
3 August 2017. |
Water Quality |
6 July 2017 |
Seepage of muddy water shall be prevented. (Portion I) |
The item was rectified by the Contractor and inspected on
13 July 2017. |
Chemical and Waste Management |
6 July 2017 |
Chemical containers shall be
stored on drip tray. (Zone 2) |
The item was rectified by the Contractor and inspected on
13 July 2017. |
13 July 2017 |
Chemical containers shall be stored on drip tray. (Zone 4) Chemical containers shall be stored in good conditions. (Zone 1) |
The item was rectified by the Contractor and inspected on
19 July 2017. |
|
Land Contamination |
NA |
||
Landscape and Visual Impact |
6 July 2017 |
Stockpile of excavated materials shall be covered with impervious
sheeting. (Zone 4) |
The item was rectified by the
Contractor and inspected on 13 July 2017. |
General Condition |
19 July 2017 |
Stagnant water was observed at Portion I and Zone 1. Contractor shall
remove stagnant water frequently. (Portion I and Zone 1) |
The item was rectified by the Contractor and inspected on
27 July 2017. |