7. ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE
8. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project
General Layout
Figure 2 Air
and Noise Monitoring Locations
LIST OF
APPENDICES
Appendix A |
|
Appendix B |
|
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
|
Appendix
K |
Weather and Meteorological
Conditions during Reporting Month |
Appendix L |
|
Appendix
M |
|
Appendix
N |
|
|
|
i.
The
Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the
Environmental Team services for the Project and implement the EM&A works.
ii.
This
Monthly EM&A report presents the environmental monitoring and audit works
for the period between 1 September 2017 and 30 September 2017. As informed by the
Contractor, major activities in the reporting month were:
Excavation and laying of drainage pipe and
manhole;
Seawall modification works;
Construction of tunnel box structure;
D-wall construction works;
Pumping test; and
Excavation and ELS construction.
Breaches of the Action and Limit Levels
iii. No Action / Limit Level exceedance was
recorded for 24-hr TSP and construction noise at KTD1a, KTD2a and KER1b in the
reporting month.
Complaint,
Notification of Summons and Successful Prosecution
iv. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
v. There was no reporting change in the
reporting month.
Future Key Issues
vi. The key issues to be considered in the coming
reporting month include:
Potential
environmental impacts arising from the above construction activities are mainly
associated with construction dust, construction noise, water quality, waste
management and landscape and visual impact.