10.1.1 24-hour TSP impact
monitoring and construction noise monitoring were carried out in the reporting
month, no Action / Limit Level exceedance was recorded during the period.
10.1.2 No complaint of air quality was received. Therefore, no impact 1-hour TSP
monitoring was conducted in the reporting month.
10.1.3 Four environmental site
inspections were carried out in the reporting month. Recommendations on mitigation
measures on air quality, water quality, noise, waste management and landscape
and visual impact were given to the Contractor for remediating the deficiencies
identified during the site inspections.
10.1.4 Four weekly Landscape and Visual Site audits were carried out on 4, 11, 17 and 25
January 2018 and two of
them, 5 and 17 January 2018 were carried out by a Registered Landscape
Architect in the reporting month. The weekly Landscape and Visual Impact
reports were counter-signed by IEC as according to the requirement of EM&A
Manual (AEIAR-130/2009).
10.1.5 Referring to the Contractor’s information, no environmental complaint, notification
of summons and successful prosecution was received in the reporting month.
10.2
Comment and Recommendations
10.2.1 The recommended environmental mitigation measures, as proposed in the EIA
reports and EM&A Manuals shall be effectively implemented to minimize the
potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental
impacts generated from the construction activities and ensure the proper
implementation of mitigation measures.
10.2.2 According to the environmental audit performed in the reporting month,
the following recommendations were made:
Air Quality
Impact
l The load of dusty materials
carried by vehicle leaving the site should be covered by impervious sheeting.
l Broken concrete should be removed
promptly.
Construction
Noise Impact
l
No specific observation was
identified in the reporting month.
Water Quality Impact
l
Construction runoff should be treated before flow into the drainage.
Chemical and Waste Management
l
No specific observation was identified in the reporting month.
Land Contamination
l
No specific observation was identified in the reporting month.
Landscape
and Visual Impact
l
Broken concrete should be removed promptly.
General
Condition
l No
specific observation was identified in the reporting month.
Permit /
Licenses
l No
specific observation was identified in the reporting month.