5.1.1
The
effective management of waste arising during the construction phase will be
monitored through the site audit programme. Regular
audits and site inspections should be carried out to ensure that the
recommended good site practices and other mitigation measures are implemented
by the Contractor.
5.1.2
The
audit should look at all aspects of on-site waste management practices
including the waste generation, storage, recycling, transport and disposal. The
aims of waste audit are:
l
to
ensure the waste arising from the works are handled, stored, collected,
transferred and disposed of in an environmentally acceptable manner;
l
verify
the implementation status and evaluate the effectiveness of the mitigation
measures; and
l
to encourage the reuse and recycling of material.
5.2.1
C&D
materials and wastes sorting were carried out on site. Receptacles were
available for C&D wastes and general refuse collection.
5.2.2 The amount of wastes
generated by the site activities in the reporting month is shown in Appendix
I.
5.2.3
The
Contractor is advised to clean up the U-channel regularly to prevent
accumulation of slurry.
5.2.4
The
Contractor is reminded to clean the sediments inside the sedimentation tank
regularly and replace the NRMM Label of the mobile crane with proper label
color.