7. ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE
8. IMPLEMENTATION STATUS
OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project General
Layout
Figure
2 Air and Noise Monitoring
Locations
LIST OF
APPENDICES
Appendix A |
|
Appendix B |
|
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
|
Appendix
K |
Weather and Meteorological
Conditions during Reporting Month |
Appendix L |
|
Appendix
M |
|
Appendix
N |
|
|
|
i.
The
Civil Engineering and Development Department HKSAR has appointed Fugro
Technical Services Limited (FTS) to undertake the Environmental Team services
for the Project and implement the EM&A works.
ii.
This
Monthly EM&A report presents the environmental monitoring and audit works
for the period between 1 August 2018 and 31 August 2018. As informed by the
Contractor, major activities in the reporting month were:
Excavation
and laying of drainage pipe and manhole;
Construction
of tunnel box structure;
Excavation
and ELS construction.
Breaches of the Action and Limit Levels
iii. No Action / Limit Level exceedance was
recorded for 24-hr TSP and construction noise at KTD1a, KTD2a, KTD2b and KER1b
in the reporting month.
Complaint,
Notification of Summons and Successful Prosecution
iv. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
v.
Due to the handover of the site to the
Hospital Authority in mid-July 2018 to become the future site of the New Acute
Hospital. The proposal of relocation of monitoring location KTD2a was submitted
to EPD on 20 July 2018 for approval under condition 3.1 of EP-337/2009,
EP339/2009/A and EP-451/2013 and Section 11.3.1.2 of the EM&A Manual,
AEIAR-174/2013, and was approved by EPD on 25 July 2018. Monitoring location
KTD2a was relocated to the approved location KTD2b, effective from 9 August
2018.
Future Key Issues
vi. The key issues to be considered in the
coming reporting month include:
Potential
environmental impacts arising from the above construction activities are mainly
associated with construction dust, construction noise, water quality, waste
management and landscape and visual impact.