Summary of Site Audit in the Reporting Month

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

14 November 2018

Dust was observed on the ground. Contractor should clean up the dust. (Portion I)

The item was rectified by the Contractor and inspected on 21 November 2018.

Noise

7 November 2018

Contractor was reminded to use acoustic fabric during breaking.  (zone 3)

NA

21 November 2018

Acoustic fabric should be used during breaking to reduce noise.

(zone 3)

The item was rectified by the Contractor and inspected on 28 November 2018.

Water Quality

21 November 2018

Contractor was reminded to clear the sediments in the sedimentation tank regularly.

(zone 1)

NA

28 November 2018

Broken water pipe shall be repaired as soon as possible.

(zone 1)

NA

Chemical and Waste Management

 

NA

 

Land Contamination

NA

Landscape and Visual Impact

 

NA

 

General Condition

 

NA