Summary
of Site Audit in the Reporting Month
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Air Quality |
14 November 2018 |
Dust was observed on the ground. Contractor should clean up
the dust. (Portion I) |
The item was rectified by the Contractor and inspected on
21 November 2018. |
Noise |
7 November 2018 |
Contractor was reminded to use acoustic fabric during breaking. (zone 3) |
NA |
21 November 2018 |
Acoustic fabric should be used during breaking to
reduce noise. (zone 3) |
The item was rectified by the Contractor and inspected on
28 November 2018. |
|
Water Quality |
21 November 2018 |
Contractor was reminded to clear the sediments in the
sedimentation tank regularly. (zone 1) |
NA |
28 November 2018 |
Broken water pipe shall be repaired as soon as possible. (zone 1) |
NA |
|
Chemical and Waste Management |
NA |
||
Land Contamination |
NA |
||
Landscape and Visual Impact |
NA |
||
General Condition |
NA |