Summary
of Site Audit in the Reporting Month
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Air Quality |
5 December 2018 |
Reminder: Water spray shall be provided during breaking. (zone 3) |
NA |
12 December 2018 |
Observation: Dust suppression measures should be applied at haul road. (zone 1) |
The item was rectified by the Contractor and inspected on
19 December 2018. |
|
19 December 2018 |
Reminder: Exposed area should be sprayed with water frequently. |
NA |
|
Noise |
5 December 2018 |
Reminder: Noise mitigation measures shall be provided during
breaking. (zone 3) |
NA |
Water Quality |
NA |
||
Chemical and Waste Management |
12 December 2018 |
Reminder: Waste should be cleaned up regularly. (zone 1) |
NA |
Land Contamination |
NA |
||
Landscape and Visual Impact |
NA |
||
General Condition |
NA |