6.1.1
Site
inspections were carried out weekly to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project. A summary
of the mitigation measures implementation schedule is provided in Appendix
J.
6.1.2
In
the reporting month, five site inspections were
carried out on 2, 9, 16, 23 and 30
October 2019.
Two of them, held on 2 and 16 October
2019 was
the joint inspections with the IEC, ER, the Contractor and the ET.
6.1.3
One
outstanding issue was reported on September 2019, contractor was recommended
that hoarding should be erected around the site area in Zone 4. The issue was
rectified in the following weekly site inspection on 2 October 2019.
6.1.4
No
outstanding issues were reported during the reporting month. Details of
observations recorded during the site inspections are summarized in Appendix
M.
6.1.5
All
the follow-up actions requested by Contractor’s ET and IEC during the site inspections
were undertaken as reported by the Contractor and confirmed in the following
weekly site inspection conducted during the reporting month.