10.1.1 24-hour TSP
impact monitoring and construction noise monitoring were carried out in the
reporting month, no Action / Limit Level exceedance was recorded during the
period.
10.1.2 No complaint of air quality was received. Therefore, no impact 1-hour TSP
monitoring was conducted in the reporting month.
10.1.3 Four environmental
site inspections were carried out in the reporting month. Recommendations on
mitigation measures for chemical and waste management were given to the
Contractor for remediating the deficiencies identified during the site
inspections.
10.1.4 Four weekly Landscape and Visual Site audits were
carried out on
6, 14, 20 and 27 November
2019 and two of them 6 and 20 November 2019 were carried out by a Registered Landscape Architect in the reporting
month. The weekly Landscape and Visual Impact reports were counter-signed by
IEC as according to the requirement of EM&A Manual (AEIAR-130/2009).
10.1.5 Referring to the Contractor’s information, no environmental
complaint, notification of summons and successful prosecution was received in
the reporting month.
10.2
Comment and Recommendations
10.2.1 The recommended environmental mitigation measures,
as proposed in the EIA reports and EM&A Manuals shall be effectively
implemented to minimize the potential environmental impacts from the Project. The
EM&A programme would effectively monitor the
environmental impacts generated from the construction activities and ensure the
proper implementation of mitigation measures.
10.2.2 According to the environmental audit performed in
the reporting month, the following recommendations were made:
Air Quality Impact
l No specific
observation was identified in the reporting month.
Construction Noise Impact
l No specific
observation was identified in the reporting month.
Water Quality Impact
l No specific
observation was identified in the reporting month.
Chemical
and Waste Management
l Drip
tray should be provided to prevent chemical leakage.
Land Contamination
l No
specific observation was identified in the reporting month.
Landscape and Visual Impact
l No specific
observation was identified in the reporting month.
General Condition
l No
specific observation was identified in the reporting month.
Permit / Licenses
l No
specific observation was identified in the reporting month.