4.1.1
As per the Trunk
Road T2 EM&A Manual, the landscape and visual mitigation measures during
the construction phase shall be audited by a Registered Landscape Architect, as
a member of the Environmental Team, at least once every two weeks to ensure
compliance with the intended aims of the measures.
4.1.2
According to the Kai
Tak Development EM&A Manual, measures to mitigate landscape and visual
impacts during construction should be checked to ensure compliance with the
intended aims of the measures. The progress of the engineering works shall be
regularly reviewed onsite to identify the earliest practical opportunities for
the landscape works to be undertaken. The ET shall report on the Contractor’s
compliance on a weekly basis.
4.2.1
To monitor and audit
the implementation of landscape and visual mitigation measures, four weekly
Landscape and Visual Site audits were carried out on 4, 11, 18 and 24 December
2019 and two of them 4 and 18 December 2019 were carried out by a Registered
Landscape Architect. The weekly Landscape and Visual Impact reports were
counter-signed by IEC as according to the requirement of EM&A Manual (AEIAR-130/2009).
4.2.2
Should non-compliance
of the landscape and visual impact occur, action in accordance to the event
action plan presented in Appendix H shall be carried out.