9.            FUTURE KEY ISSUES

 

9.1         Construction Programme for the Next Two Months

 

ž   Excavation and laying of drainage pipe and manhole

ž   Construction of SUS structure

ž   Construction of District Cooling System

ž   Utility laying

ž   Construction of road base and road pavement

 

9.2         Key Issues for the Coming Month

 

9.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management and landscape and visual impact.

 

9.3         Monitoring Schedules for the Next Three Months

 

9.3.1     The tentative schedules for environmental monitoring in the coming three months are provided in Appendix E.