10.1.1 24-hour TSP
impact monitoring and construction noise monitoring were carried out in the
reporting month, no Action / Limit Level exceedance was recorded during the
period.
10.1.2 No complaint of air quality was received. Therefore, no impact 1-hour TSP
monitoring was conducted in the reporting month.
10.1.3 Four environmental
site inspections were carried out in the reporting month. Recommendations on
mitigation measures for air quality impact was given to the Contractor for remediating
the deficiencies identified during the site inspections.
10.1.4 Four weekly Landscape and Visual Site audits were
carried out 4, 11, 18 and 25 March
2020 and two of them 4 and 18 March 2020 were carried out by a Registered Landscape Architect
in the reporting month. The weekly Landscape and Visual Impact reports were
counter-signed by IEC as according to the requirement of EM&A Manual
(AEIAR-130/2009).
10.1.5 Referring to the Contractor’s information, no environmental
complaint, notification of summons and successful prosecution was received in
the reporting month.
10.2
Comment and Recommendations
10.2.1 The recommended environmental mitigation measures,
as proposed in the EIA reports and EM&A Manuals shall be effectively
implemented to minimize the potential environmental impacts from the Project. The
EM&A programme would effectively monitor the
environmental impacts generated from the construction activities and ensure the
proper implementation of mitigation measures.
10.2.2 According to the environmental audit performed in
the reporting month, the following recommendations were made:
Air Quality Impact
l Dusty
material should be covered.
Construction Noise Impact
l No
specific observation was identified in the reporting month.
Water Quality Impact
l No
specific observation was identified in the reporting month.
Chemical
and Waste Management
l No
specific observation was identified in the reporting month.
Land Contamination
l No
specific observation was identified in the reporting month.
Landscape and Visual Impact
l No
specific observation was identified in the reporting month.
General Condition
l No
specific observation was identified in the reporting month.
Permit / Licenses
l No
specific observation was identified in the reporting month.