9.            FUTURE KEY ISSUES

 

9.1         Construction Programme for the Next Two Months

 

ž   Laying Cable and Construction for Road Lighting

ž   Construction of Street Furniture

ž   Construction of District Cooling System

ž   Landscape works – irrigation systems, tree and shrub planting

ž   Testing and commissioning of irrigation system

 

9.2         Key Issues for the Coming Month

 

9.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management and landscape and visual impact.

 

9.3         Monitoring Schedules for the Next Three Months

 

9.3.1     The tentative schedules for environmental monitoring in the coming three months are provided in Appendix E.