Summary of Site Audit in the Reporting Month

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

NA

Noise

NA

Water Quality

 

17 June 2020

 

Observation:

Manholes should be covered to prevent silt and construction materials. (Zone 4)

224 June 2020

224 June 2020

Observation:

Manholes should be proper covered to prevent silt and construction materials direct discharge. (Zone 4)

224 June 2020

 

Chemical and Waste Management

 

NA

Land Contamination

NA

Landscape and Visual Impact

NA

General Condition

NA

Permit / Licenses

17 June 2020

Reminder:

The contractor was reminded the EP and CNP should be provided on the site. (Zone 4)