4.1.1 As per the Trunk Road T2 EM&A Manual,
the landscape and visual mitigation measures during the construction phase
shall be audited by a Registered Landscape Architect, as a member of the Environmental
Team, at least once every two weeks to ensure compliance with the intended aims
of the measures.
4.1.2 According to the Kai Tak Development
EM&A Manual, measures to mitigate landscape and visual impacts during
construction should be checked to ensure compliance with the intended aims of
the measures. The progress of the engineering works shall be regularly reviewed
onsite to identify the earliest practical opportunities for the landscape works
to be undertaken. The ET shall report on the Contractor’s compliance on a
weekly basis.
4.2.1 To monitor and audit the implementation of
landscape and visual mitigation measures, three weekly landscape and visual
site audits were carried out on 8, 15 and 30 July 2020 and two of them 8 and 30
July 2020 were carried out by a Registered Landscape Architect. The weekly
landscape and visual impact reports were counter-signed by IEC as according to
the requirement of EM&A Manual (AEIAR-130/2009).
4.2.2 From 20 July 2020 to 24 July 2020, due to
the suspected COVID 19 case from HMJV colleague, no landscape and visual audit
was conducted to reduce the risk of the spread of COVID 19.
4.2.3 Should non-compliance of the landscape and
visual impact occur, action in accordance to the event action plan presented in
Appendix
H shall be carried out.