6.1.1
Site inspections were carried out weekly to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. A summary of the mitigation measures implementation
schedule is provided in Appendix J.
6.1.2
In the reporting month, three site inspections were
carried out 8, 15 and 30 July
2020. Two of them, held on 8 and 15 July 2020 was the joint inspections with
the IEC, ER, the Contractor and the ET.
6.1.3 From 20 July 2020 to 24 July 2020, due to
the suspected COVID 19 case from HMJV colleague, no site inspection was
conducted to reduce the risk of the spread of COVID 19.
6.1.4
No outstanding issues were reported during the
reporting month. Details of observations recorded during the site inspections
are summarized in Appendix M.
6.1.5
All the follow-up actions requested by
Contractor’s ET and IEC during the site inspections were undertaken as reported
by the Contractor and confirmed in the following weekly site inspection
conducted during the reporting month.