1.1.1
The Kai Tak
Development is located in the south-eastern part of Kowloon Peninsula of the
HKSAR, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma
Tau Kok, Kowloon Bay, Kwun
Tong and Cha Kwo Ling.
1.1.2
Contract No. KL/2014/03 is the works package to
construct an approximately 420m long supporting underground structure (SUS)
underneath Shing Cheong Road and Cheung Yip Street.
The EM&A programme under this Contract is
governed by three EPs (EP-337/2009, EP-339/2009/A and EP-451/2013) and two
EM&A Manuals (AEIAR-130/2009 and AEIAR-174/2013). The Works to be executed
under this Contract and corresponding EPs include but not be limited to the
following main items:
EP-451/2013 – Trunk
Road T2
(i)
Construction of approximately 420m long
supporting underground structure (SUS) including diaphragm walls, barrettes,
piled foundation, top and bottom slabs, end wall and adits
underneath Shing Cheong Road and Cheung Yip Street;
EP-337/2009 – New
Distributor Roads Serving the Planned Kai Tak
Development
(ii)
Widening and re-alignment of Cheung Yip Street
of approximately 330m long and associated footpaths;
(iii)
Demolition, reconstruction and widening of Shing Cheong Road of approximately 410m long and associated
footpaths;
(iv)
Construction of drainage outfall and
modification of existing seawall;
(v)
Construction of ancillary works including
surface drainage, sewerage, water, fire fighting,
street lighting, street furniture, road marking, road signage, utilities and
services, irrigation and landscape works.
EP-339/2009/A
– Decommissioning of the Remaining Parts (Ex-GFS Building, Radar Station and
Hong Kong Aviation Club) of the former Kai Tak
Airport
(vi)
Demolition of RADAR Tower and guard house;
Other works not covered
by any EP
(vii)
Construction of two subways between Phase II of
New Acute Hospital (Site A) and Hong Kong Children’s Hospital (Site C), and
between Phase I of New Acute Hospital (Site B) and Site C;
(viii)
Construction of District Cooling System (DCS)
along Cheung Yip Street and Shing Cheong Road
1.1.3
The location and boundary of the site is shown
in Figure
1.
1.2.1
The project proponent was the Civil Engineering
and Development Department, HKSAR (CEDD). Hyder Meinhardt Joint Venture (HMJV) was commissioned by CEDD as
the Engineer for the Project. Ramboll Hong Kong
Limited was commissioned as the Independent Environmental Checker (IEC). China
Road and Bridge Corporation (Hong Kong) (CRBC) was appointed as the main
contractor for the construction works under the contract KL/2014/03. MateriaLab Consultants Limited (MCL) was appointed as the
Environmental Team (ET) by CEDD to implement the EM&A programme
for the Project.
1.2.2
The organization structure is shown in Appendix
B. The key personnel contact names and numbers for the Project are
summarized in Table 1.1.
1.3.1
The construction of the Project commenced in
February 2016 and is expected to complete in 2020. The construction programme is shown in Appendix A.
1.3.2
A summary of the major construction activities undertaken in the reporting
month were:
Utility
laying
Construction
of road base and road pavement
Landscape
works – irrigation systems, tree and shrub planting
Laying Cable
and Construction for Road Lighting
1.4.1 According to
the construction activities in the construction programme
mentioned in Section 1.3.2, the following environmental protection/ mitigation
measures including Air Quality Impact, Construction Noise Impact, Water Quality
Impact, Chemical and Waste Management, Landscape and Visual Impact shall be
implemented:
Sufficient
watering of the works site with the active dust emitting activities;
Limitation
of the speed for vehicles on unpaved site roads;
Properly
cover or enclosure of the stockpiles and dusty materials;
Good site
practices on loading dusty materials;
Good
maintenance to the plant and equipment;
Use of
quieter plant and Quality Powered Mechanical Equipment (QPME);
Using the
approved Non-road Mobile Machineries (NRMMs);
Proper
storage and handling of chemical;
Onsite waste
sorting and implementation of trip ticket system;
Training of
the site personnel in proper waste management and chemical waste handling procedures;
Proper
storage of the construction materials;
Strictly
following the Environmental Permits and Licenses;
Provide sufficient mitigation measures as recommended in Approved EIA Reports.
1.5.1
A summary of the relevant environmental
licenses, permits and/or notifications on environmental protection for this
Contract is presented in Table 1.2.