10.1.1
24-hour TSP impact monitoring and construction
noise monitoring were carried out in the reporting month.
10.1.2
No Action / Limit Level exceedance was recorded for 24-hr TSP at KTD1,
KTD2c and KER1 in the reporting month.
10.1.3 No Action /
Limit Level exceedance was recorded for construction noise at KTD1, KTD2c and
KER1 in the reporting month.
10.1.4
No complaint of air
quality was received. Therefore, no impact 1-hour TSP monitoring was conducted
in the reporting month.
10.1.5 Three environmental
site inspections were carried out in the reporting month. No recommendation was
given to the Contractor for remediating the deficiencies identified during the
site inspections.
10.1.6
Three weekly
Landscape and Visual Site audits were carried out 3, 9 and 17 March 2021 and one of them 9
March 2021 were carried out by a Registered
Landscape Architect in the reporting month. The weekly Landscape and Visual
Impact reports were counter-signed by IEC as according to the requirement of
EM&A Manual (AEIAR-130/2009).
10.1.7
Referring
to the Contractor’s information, no environmental complaint, notification of
summons and successful prosecution was received in the reporting month.
10.2
Comment and Recommendations
10.2.1 The recommended environmental mitigation measures,
as proposed in the EIA reports and EM&A Manuals shall be effectively
implemented to minimize the potential environmental impacts from the Project. The
EM&A programme would effectively monitor the
environmental impacts generated from the construction activities and ensure the
proper implementation of mitigation measures.
10.2.2 According to the environmental audit performed in
the reporting month, the following recommendations were made:
Air Quality Impact
l No
specific observation was identified in the reporting month.
Construction Noise Impact
l No specific
observation was identified in the reporting month.
Water Quality Impact
l No
specific observation was identified in the reporting month.
Chemical
and Waste Management
l No
specific observation was identified in the reporting month.
Land Contamination
l No
specific observation was identified in the reporting month.
Landscape and Visual Impact
l No
specific observation was identified in the reporting month.
General Condition
l No
specific observation was identified in the reporting month.
Permit / Licenses
l No
specific observation was identified in the reporting month.