6.            COMMENTS, CONCLUSIONS AND RECOMMENDATIONS

 

6.3         Comments on Overall EM&A Programme

 

6.3.1      The EM&A programme requires construction phase monitoring for air quality, construction noise and environmental site audit. Timely implementation of mitigation measures was carried out according to the environmental monitoring data obtained during this project.

 

6.3.2      According to the email and the completion certification provided by HMJV, the major works of Contract No. KL/2014/03 has been completed substantially on 31 December 2019. The remaining outstanding construction works are those minor ancillary works that no Powered Mechanical Equipment (PME) will be involved. No significant adverse environmental impacts are anticipated in the remaining construction works. The proposal for Termination of EM&A Programme under this Contract was certified by the ET Leader, verified by the IEC on 15 December 2020, approved by EPD on 18 March 2021.

 

6.3.3      The weekly site inspections were effective to ensure the implementation and efficiency of the mitigation measures. As a result, an environmental nuisance to the public could be reduced to a minimum.

 

6.3.4      Therefore, the overall performance of the monitoring methodology adopted and environmental management system in the project was effective.

 

6.4         Overall EM&A Data

 

6.4.1      Impact air quality and construction noise were conducted at the designated monitoring stations in accordance with the Manual.

 

6.4.2      The overall trends of the monitored parameters at the monitoring period were presented in Appendix D. Due to the construction activity was increasing from the construction site of Trunk Road T2, an increasing trends of 24hr-TSP concentration and construction noise level were observed since August 2020.

 

6.4.3      Total 17 Action Level and 2 Limit Level exceedances for 24-hr TSP were recorded in the reporting period. Total 3 Limit Level exceedance for construction noise were recorded in the reporting period. Base on the investigation, the occasional exceedances were non-project related. In general, the monitoring parameters were within the range of the baseline levels.

 

6.4.4      Weekly environmental site inspections were carried out in the reporting period. Recommendations on mitigation measures for air quality, noise, water quality, waste management, landscape and visual and permit / licenses were given to the Contractor for remediating the deficiencies identified during the site inspections. No non-compliance was found during the reporting period.

 

6.5         Conclusions and Recommendations

 

6.5.1      The recommended environmental mitigation measures, as proposed in the EIA reports and EM&A Manuals shall be effectively implemented to minimize the potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental impacts generated from the construction activities and ensure the proper implementation of mitigation measures.

 

6.5.2      With the success of the overall EM&A programme, the deterioration of the environment caused by the Project was cost-effectively identified and necessary prompt effective mitigation measures were implemented to avoid any unacceptable impacts. In conclusion, the Project was environmentally acceptable.