3.1.1 To monitor and audit the implementation of
landscape and visual mitigation measures, 13 weekly Landscape and Visual Site
audits were carried out and 7 of them were carried out by a Registered
Landscape Architect. The weekly Landscape and Visual Impact reports were
counter-signed by IEC as according to the requirement of EM&A Manual (AEIAR-130/2009).
3.1.2 Total 1 no. of non-compliance was recorded
in the weekly Landscape and Visual Site audits in the reporting period. Open stockpile
was found to not being covered properly during the landscape and visual impact
site inspection on 24 March 2016. The case was rectified on 30 March 2016 and
during the site inspection on 31 March 2016. Other than this, no non-compliance
of the landscape and visual impact was recorded in the reporting period.