1.1.1
The Kai Tak
Development is located in the south-eastern part of Kowloon Peninsula of the
HKSAR, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma
Tau Kok, Kowloon Bay, Kwun
Tong and Cha Kwo Ling.
1.1.2
Contract No. KL/2014/03 is the works package
to construct an approximately 420m long supporting underground structure (SUS)
underneath Shing Cheong Road and Cheung Yip Street.
The EM&A programme under this Contract is governed by three EPs (EP-337/2009, EP-339/2009/A and
EP-451/2013) and two EM&A Manuals (AEIAR-130/2009 and AEIAR-174/2013). The
Works to be executed under this Contract and corresponding EPs include but not
be limited to the following main items:
EP-451/2013 – Trunk
Road T2
(i)
Construction of approximately 420m long
supporting underground structure (SUS) including diaphragm walls, barrettes,
piled foundation, top and bottom slabs, end wall and adits
underneath Shing Cheong Road and Cheung Yip Street;
EP-337/2009 – New
Distributor Roads Serving the Planned Kai Tak
Development
(ii)
Widening and re-alignment of Cheung Yip
Street of approximately 330m long and associated footpaths;
(iii)
Demolition, reconstruction and widening of Shing Cheong Road of approximately 410m long and associated
footpaths;
(iv)
Construction of drainage outfall and
modification of existing seawall;
(v)
Construction of ancillary works including
surface drainage, sewerage, water, fire fighting,
street lighting, street furniture, road marking, road signage, utilities and
services, irrigation and landscape works.
EP-339/2009/A
– Decommissioning of the Remaining Parts (Ex-GFS Building, Radar Station and
Hong Kong Aviation Club) of the former Kai Tak
Airport
(vi)
Demolition of RADAR Tower and guard house;
Other works not
covered by any EP
(vii)
Construction of two subways between Phase II
of New Acute Hospital (Site A) and Hong Kong Children’s Hospital (Site C), and
between Phase I of New Acute Hospital (Site B) and Site C;
(viii)
Construction of District Cooling System (DCS)
along Cheung Yip Street and Shing Cheong Road
1.1.3
The location and boundary of the site is
shown in Figure 1.
1.2.1
The project proponent was the Civil
Engineering and Development Department, HKSAR (CEDD). Hyder
Meinhardt Joint Venture (HMJV) was commissioned by
CEDD as the Engineer for the Project. Ramboll Environ
Hong Kong Limited was commissioned as the Independent Environmental Checker
(IEC). China Road and Bridge Corporation (Hong Kong) (CRBC) was appointed as
the main contractor for the construction works under the contract KL/2014/03. MateriaLab Consultants Limited (MCL) was appointed as the
Environmental Team (ET) by CEDD to implement the EM&A programme
for the Project.
1.2.2
The organization structure is shown in Appendix B. The key personnel contact
names and numbers for the Project are summarized in Table
1.1.
Table
1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Project Proponent (CEDD) |
Co-ordinator |
Ms. Amy Chu |
3106
3172 |
2369
4980 |
Engineer’s Representative (HMJV) |
Chief Resident Engineer |
Mr. W. K., Chris Wong |
2911
2233 |
2805
5028 |
IEC (Ramboll Environ
Hong Kong Limited) |
Independent Environmental Checker |
Mr. F. C. Tsang |
3465
2888 |
3465
2899 |
Main Contractor (CRBC) |
Site Agent |
Mr. Chan See Wai, Arnold |
9380
4110 |
2283
1689 |
Environmental Officer |
Mr. Wong Tan Tat |
9492
5918 |
2283
1689 |
|
ET (MCL) |
Environmental Team Leader |
Mr. Colin Yung |
3565
4114 |
3565
4160 |
1.3.1
The construction of the Project commenced in
February 2016 and is expected to complete in 2020. The construction programme is shown in Appendix A.
1.3.2
A summary of the major construction activities undertaken in the
reporting period were:
June
2016 |
July
2016 |
August
2016 |
·
Carrying out pre-drilling; ·
Construction of guide walls and D-walls at Zone 2; ·
Construction of H piles at Zone 1, 3 & 4; ·
Demolition of foundation at
Zone 4; ·
Construction of temporary utility diversion
at Zone 1; ·
Construction of subway B at Zone 1; ·
Implementation of Temporary
Traffic Arrangement (TTA) along Cheung Yip Street and Shing Cheong Road; ·
Erection of scaffolding at Radar Tower; ·
Removal of Asbestos materials
at Radar Tower; and Construction of temporary road at Zone 4. |
·
Carrying out pre-drilling; ·
Construction of guide walls and D-walls at Zone 2; ·
Construction of H piles at Zone 1 to Zone 4; ·
Demolition of foundation at
Zone 4; ·
Construction of temporary utility diversion
at Zone 1,3 & 4; ·
Erection and installation of Earth Lateral Support (ELS) of subway
B at Zone 1; ·
Erection of scaffolding at Radar Tower; ·
Setting up stockpiling area at Portion I and
K; ·
Construction of temporary road at Zone 4 and ·
Installation of bulkhead wall
at Zone 1. |
·
Carrying out pre-drilling; ·
Rebar bending; ·
Construction of guide walls and temporary D-walls; ·
Construction of Socketed H piles; ·
Pumping test; ·
Temporary utility diversion; ·
Excavation and Earth Lateral
Support (ELS) construction; ·
Demolition of Radar Tower; ·
Implementation of Temporary
Traffic Arrangement; and ·
Construction of temporary road. |