TABLE OF CONTENTS
2. Summary of EM&A Requirements and
monitoring results
6. ENVIRONMENTAL COMPLAINT AND
NON-COMPLIANCE
7. IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project General
Layout
Figure 2 Air
and Noise Monitoring Locations
LIST OF APPENDICES
Appendix A |
|
Appendix B |
|
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
|
|
|
|
i. The Civil Engineering
and Development Department HKSAR has appointed MateriaLab Consultants Limited
(MCL) to undertake the Environmental Team services for the Project and
implement the EM&A works.
ii. This is the
fifth Quarterly EM&A Report presents the environmental monitoring and audit
works for the period between 1 March 2017 and 31 May 2017. As informed by the
Contractor, major activities in the reporting period included:
March
2017 |
April
2017 |
May
2017 |
· Temporary utility diversion; · Implementation of Temporary
Traffic Arragement (TTA); · Construction of Tunnel
structure; · Construction of Socket
H-piles; · Construction of drainage
works; · Construction of guide walls
and D-walls; and · Construction of District
Cooling System Works. |
· Temporary utility diversion; · Implementation of Temporary
Traffic Arragement (TTA); · Construction of Tunnel
structure; · Construction of Socket
H-piles; · Construction of drainage
works; · Construction of guide walls
and D-walls; · Construction of District
Cooling System Works; and · Installation of temporary
cut-off wall. |
· Temporary utility diversion; · Implementation of Temporary
Traffic Arragement (TTA); · Construction of Tunnel
structure; · Construction of Socket
H-piles; · Construction of drainage
works; · Construction of guide walls
and D-walls; · Construction of District
Cooling System Works; and · Installation of temporary
cut-off wall. |
Breaches of the Action and Limit Levels
iii.
No Action and Limit Level exceedance for 24-hr TSP and noise was
recorded in the reporting period at all monitoring stations.
Complaint, Notification of Summons and Successful Prosecution
iv. A complaint received on 2 May 2017 was
referred from CEDD and summarized as below:
The
notification of complaint was received by ET on 4 May 2017.
v.
No notification of summons and successful prosecution were received in
the reporting period.