i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii. This is the sixth
Quarterly EM&A Report presents the environmental monitoring and audit works
for the period between 1 June 2017 and 31 August 2017. As informed by the
Contractor, major activities in the reporting period included:
June 2017 |
July 2017 |
August 2017 |
Temporary utility diversion works;
Temporary diversion for CLP cable at CH6+560;
Temporary diversion for sewage rising main;
Construction of temporary diversion road for Shing Cheong
Road (TTA Stage 2);
Setup of temporary barging point;
Drainage works (CH100 to CH240);
Excavation of drainage pipe and manhole (M206 to M213);
Seawall Modification Works;
Construction of tunnel box structure;
D-wall construction works;
Construction of socket H-pile;
Pumping test for Zone 3;
Excavation and ELS construction; and
Installation of dewatering, observation and recharging
wells. |
Temporary diversion for drainage works;
Temporary diversion for CLP cable at CH6+560;
Temporary diversion for sewage rising main;
Construction of temporary diversion road for Shing Cheong
Road (TTA Stage 2);
Setup of temporary barging point;
Excavation of drainage pipe and manhole (M206 to M207);
Seawall Modification Works;
Construction of tunnel box structure;
D-wall construction works;
Guide wall construction works;
Construction of socket H-pile;
Pumping test for Zone 3;
Excavation and ELS construction; and
Installation of dewatering, observation and recharging
wells. |
Excavation and laying of drainage pipe and manhole;
Seawall modification works;
Construction of tunnel box structure;
D-wall construction works;
Pumping test;
Excavation and ELS construction; and
Setup of temporary barging point. |
Breaches of the Action and Limit Levels
iii.
No Action and Limit Level exceedance for 24-hr TSP and noise was recorded
in the reporting period at all monitoring stations.
Complaint, Notification of Summons and Successful Prosecution
iv. A complaint received on 16 July 2017 was referred from the 1823
regarding the muddy water discharge at Kai Tak River by CEDD project. The
notification of complaint was received by ET on 27 July 2017.
v.
No notification of summons and successful prosecution were received in
the reporting period.