Table 5.1 Observations and
Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
|
Air Quality |
1 June 217 |
Regular watering to the site working
area shall be provided to suppress dust emission. (Zone 1) |
The item was rectified by the
Contractor and inspected on 8 June 2017. |
|
15 June 2017 |
Open stockpiles of excavated material
shall be covered properly with impervious sheeting to avoid dust emission.
(Zone 1) |
The item was rectified by the
Contractor and inspected on 23 June 2017 |
||
6 July 2017 |
Stockpile of excavated materials shall be covered
with impervious sheeting. (Zone 4) |
The item was rectified by the
Contractor and inspected on 13 July 2017 |
||
13 July 2017 |
Spent bags of cement shall be stored properly.
(Zone 3) |
The item was rectified by the
Contractor and inspected on 19 July 2017. |
||
24 August 2017 |
Contractor was reminded to cover stockpiles with
impervious sheetings properly. (Portion I) |
The item was rectified by the
Contractor and inspected on 31 August 2017. |
||
31 August 2017 |
Open stockpiling of C&D materials shall be
covered properly. Impermeable sheeting shall be provided. (Zone 1) |
The item was rectified by the
Contractor and inspected on 7 September 2017. |
||
Noise |
27 July 2017 |
Contractor was reminded to close the door of the
air compressor to reduce noise emission. (Zone 4) |
The item was rectified by the
Contractor and inspected on 3 August 2017. |
|
31 August 2017 |
Appropriate noise absorption material shall be
provided to the operating breaker. (Zone 4) |
The item was rectified by the
Contractor and inspected on 7 September 2017. |
||
Water Quality |
1 June 2017 |
The mud at mud tank shall be removed
to prevent overflow of storm water at the mud tank. (Zone 1) |
The item was rectified by the
Contractor and inspected on 8 June 2017. |
|
6 July 2017 |
Seepage of muddy water shall be
prevented. (Portion I) |
The item was rectified by the
Contractor and inspected on 13 July 2017. |
||
3 August 2017 |
Waste water treatment system shall be improved to
prevent the accumulation of muddy water and water seepage at the low lying
area at Portion I. Contractor was recommended to separate the discharge point
and the desilting pond, seal the concrete blocks, and provide additional
pumps. (Portion I) |
The item was rectified by the
Contractor and inspected on 10 August 2017. |
||
Chemical and Waste Management |
8 June 2017 |
Chemical containers
shall be stored on drip tray. (Zone 1) |
The item was rectified by the
Contractor and inspected on 15 June 2017. |
|
8 June 2017 |
General
refuse shall be stored properly and removed regularly. (Zone 2) |
The item was rectified by the
Contractor and inspected on 15 June 2017. |
||
15 June 2017 |
General
refuse, spent chemical containers and used bags of cement shall be stored
properly. (Zone 2) |
The item was rectified by the
Contractor and inspected on 23 June 2017. |
||
6 July 2017 |
Chemical containers
shall be stored on drip tray. (Zone 2) |
The item was rectified by the
Contractor and inspected on 13 July 2017. |
||
13 July 2017 |
Chemical containers shall be stored on drip tray.
(Zone 4) Chemical containers shall be stored in good
conditions. (Zone 1) |
The item was rectified by the
Contractor and inspected on 19 July 2017. |
||
10 August 2017 |
Cement residue was found in the public haul road.
Impermeable sheeting shall be provided when loading the cement. (Zone 2) |
The item was rectified by the
Contractor and inspected on 17 August 2017. |
||
Land Contamination |
NA |
|||
Landscape and Visual Impact |
8 June 2017 |
Debris and
concrete shall be properly covered. (Zone 4) |
The item was rectified by the
Contractor and inspected on 15 June 2017. |
|
15 June 2017 |
Excavated materials shall be properly covered by
impervious sheeting. (Zone 4) |
The item was rectified by the
Contractor and inspected on 23 June 2017. |
||
6 July 2017 |
Stockpile of excavated materials shall be covered
with impervious sheeting. (Zone 4) |
The item was rectified by the
Contractor and inspected on 13 July 2017. |
||
3 August 2017 |
Decorative hoardings shall be provided along
Shing Cheong Road. |
The item was rectified by the
Contractor and inspected on 17 August 2017. |
||
24 August 2017 |
Contractor was reminded to cover stockpiles with
impervious sheetings properly. (Portion I) |
The item was rectified by the
Contractor and inspected on 31 August 2017. |
||
31 August 2017 |
Open stockpiling of C&D materials shall be
covered properly. Impermeable sheeting shall be provided. (Zone 1) |
The item was rectified by the
Contractor and inspected on 7 September 2017. |
||
General |
23 June 2017 |
Stagnant water shall be removed.
(Portion I and Portion O) |
The item was rectified by the
Contractor and inspected on 29 June 2017. |
|
19 July 2017 |
Stagnant water was observed at Portion I and Zone
1. Contractor shall remove stagnant water frequently. (Portion I and Zone 1) |
The item was rectified by the
Contractor and inspected on 27 July 2017. |
||
17 August 2017 |
Contractor was reminded that the low-lying area
at Portion I shall be kept clear of silt, dusty or muddy materials. (Portion
I) |
The item was rectified by the
Contractor and inspected on 24 August 2017. |
||