i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and
implement the EM&A works.
ii. This is the
seventh Quarterly EM&A Report presents the environmental monitoring and
audit works for the period between 1 September 2017 and 30 November 2017. As
informed by the Contractor, major activities in the reporting period included:
September
2017 |
October
2017 |
November
2017 |
·
Excavation and laying of drainage pipe and manhole; ·
Seawall modification works; ·
Construction of tunnel box structure; ·
D-wall construction works; ·
Pumping test; and ·
Excavation and ELS construction. |
·
Excavation and laying of drainage pipe and manhole; ·
Seawall modification works; ·
Construction of tunnel box structure; ·
D-wall construction works; ·
Pumping test; and Excavation and ELS construction. |
·
Excavation and laying of drainage pipe and manhole; ·
Seawall modification works; ·
Construction of tunnel box structure; ·
D-wall construction works; ·
Pumping test; and Excavation and ELS construction. |
Breaches of the Action and Limit Levels
iii. No Action and Limit Level exceedance for
24-hr TSP and noise was recorded in the reporting period at all monitoring
stations.
Complaint, Notification of Summons and Successful Prosecution
iv. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.