Table 5.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
|
Air Quality |
7 December 2017 |
Open
stockpile should be covered with impermeable sheeting to facilitate dust
suppression (Portion I). Open stockpile shall be covered with impermeable
sheeting Properly. |
The item was rectified by the
Contractor and inspected on 14 December 2017. |
|
7 December 2017 |
Dusty
materials have accumulated on the ground surface on Portion I. Regular
cleaning should be carried out. |
The item was rectified by the
Contractor and inspected on 14 December 2017. |
||
11 January 2018 |
Broken concrete should be removed promptly (Zone
4). |
The item was rectified by the Contractor
and inspected on 17 January 2018. |
||
17 January 2018 |
The load of dusty materials carried by vehicle
leaving the site should be covered by impervious sheeting. |
The item was rectified by the
Contractor and inspected on 25 January 2018. |
||
8 February 2018 |
Contractor was reminded to conduct frequent
watering on excavation area to suppress dust (Zone 2). |
The item was rectified by the
Contractor and inspected on 14 February 2018. |
||
14 February 2018 |
Open
stockpile were observed (Zone 4). Open stockpile shall be removed or cover
properly. |
The item was rectified by the
Contractor and inspected on 22 February 2018. |
||
Noise |
7 December 2017 |
Acoustic
fabric should be used for the operation of breaking tip (Zone 4). Acoustic
fabric shall be provided to reduce noise. |
The item was rectified by the
Contractor and inspected on 14 December 2017. |
|
28 December 2017 |
When operating breaking tip, acoustic fabric
should be used to reduce noise generation (Zone 2). Acoustic fabric shall be
provided. |
The item was rectified by the
Contractor and inspected on 4 January 2018. |
||
Water Quality |
14 December 2017 |
Untreated
construction runoff was found flow into the drainage (Zone 1). Contractor
should prevent untreated construction runoff discharge into drainage,
mitigation measures shall be carried out. |
The item was rectified by the
Contractor and inspected on 20 December 2017. |
|
11 January 2018 |
Construction
runoff was discharged into drainage without treatment (Zone 1). Sand bag
should be provided to prevent direct discharge of construction runoff. |
The item was rectified by the
Contractor and inspected on 17 January 2018. |
||
22 February 2018 |
Debris
and silt were found near the drainage opening (Zone 2). Sandbag or other
mitigation measures should be provided. |
The item was rectified by the
Contractor and inspected on 1 March 2018. |
||
Chemical and Waste Management |
14 February 2018 |
Leakage
of drip tray was observed (Zone 1). The drip tray shall be removed or
replaced. |
The item was rectified by the
Contractor and inspected on 22 February 2018. |
|
14 February 2018 |
Open stockpile were observed (Zone 4). Open
stockpile shall be removed or cover properly. |
The item was rectified by the
Contractor and inspected on 22 February 2018. |
||
Land Contamination |
NA |
|||
Landscape and Visual Impact |
11 January 2018 |
Broken concrete should be removed promptly (Zone
4). |
The item was rectified by the
Contractor and inspected on 17 January 2018. |
|
14 February 2018 |
Open
stockpile were observed (Zone 4). Open stockpile shall be removed or cover
properly. |
The item was rectified by the
Contractor and inspected on 22 February 2018. |
||
General |
NA |
|||