Executive Summary   1

1.         INTRODUCTION   2

2.         SUMMARY OF EM&A REQUIREMENTS AND MONITORING RESULTS   4

3.         LANDSCAPE AND VISUAL   7

4.         WASTE MANAGEMENT   8

5.         SITE INSPECTION   9

6.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE   12

7.         IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES   14

8.         Conclusions   15

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Graphical Presentation of Monitoring Data

Appendix E

Waste Flow Table

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

 

 

 

 

 


Executive Summary

 

   i.   The Civil Engineering and Development Department HKSAR has appointed Fugro Technical Services Limited (FTS) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

  ii.   This is the tenth Quarterly EM&A Report presents the environmental monitoring and audit works for the period between 1 June 2018 and 31 August 2018. As informed by the Contractor, major activities in the reporting period included:

 

June 2018

July 2018

August 2018

· Excavation and laying of drainage pipe and manhole;

· Seawall modification works;

· Construction of tunnel box structure;

· D-wall construction works;

· Pumping test; and

· Excavation and ELS construction.

 

· Excavation and laying of drainage pipe and manhole;

· Seawall modification works;

· Construction of tunnel box structure;

· D-wall construction works;

· Pumping test; and

· Excavation and ELS construction.

 

· Excavation and laying of drainage pipe and manhole;

· Construction of tunnel box structure; and

· Excavation and ELS construction.

 

 

 

Breaches of the Action and Limit Levels

 

 iii.   No Action and Limit Level exceedance for 24-hr TSP and noise was recorded in the reporting period at all monitoring stations.

 

 

Complaint, Notification of Summons and Successful Prosecution

 

iv.   No environmental complaint and no notification of summons and successful prosecution were received in the reporting period.