8.1.1 No Action
and Limit Level exceedance for 24-hr TSP and noise was recorded in the
reporting period at all monitoring stations.
8.1.2 No complaint of air quality was received. Therefore, no impact 1-hour TSP
monitoring was conducted in the reporting period.
8.1.3 13 weekly environmental
site inspections were carried out in the reporting period. Recommendations on
mitigation measures on air quality, noise quality, water quality, chemical and waste
management, landscape and visual impact were given to the Contractor for
remediating the deficiencies identified during the site inspections.
8.1.4 13 weekly Landscape and Visual Site audits were
carried out on in the reporting period and 6 of them were carried out by a
Registered Landscape Architect in the reporting period. The weekly Landscape
and Visual Impact reports were counter-signed by IEC as according to the
requirement of EM&A Manual (AEIAR-130/2009). No non-compliance was recorded
in the weekly Landscape and Visual Site audits in the reporting period.
8.1.5
Referring
to the Contractor’s information, no notification of summons and successful
prosecution was received in the reporting period.
8.2.1 The recommended environmental mitigation measures,
as proposed in the EIA reports and EM&A Manuals shall be effectively
implemented to minimize the potential environmental impacts from the Project. The
EM&A programme would effectively monitor the environmental impacts generated
from the construction activities and ensure the proper implementation of
mitigation measures.
8.2.2 According to the environmental audit performed in
the reporting period, the following recommendations were made:
Air Quality Impact
l Watering
on dusty materials should be carried out regularly for dust suppression.
l The
sheeting of stockpile should be check after typhoon weather.
l Backfilling
materials should be properly covered.
l Dust
was observed on the ground. Contractor should clean up the dust.
Construction Noise Impact
l Contractor
was reminded to use acoustic fabric during breaking.
Water Quality Impact
l Sediments
inside the sedimentation tank should be removed regularly.
l Contractor
was reminded to clear the sediments in the sedimentation tank regularly.
l Broken
water pipe shall be repaired as soon as possible.
Chemical
and Waste Management
l Chemical
containers should be placed in drip tray.
Land Contamination
l No
specific observation was identified in the reporting period.
Landscape and Visual Impact
l Check
and properly cover all stockpiling after typhoon.
l Backfilling
materials should be properly covered.
General Condition
l No
specific observation was identified in the reporting period.
Permit / Licenses
l No
specific observation was identified in the reporting period.