TABLE OF CONTENTS
2. SUMMARY
OF EM&A REQUIREMENTS AND MONITORING RESULTS
6. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
7. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project General Layout
Figure
2 Air and Noise Monitoring
Locations
LIST OF APPENDICES
|
|
|
|
i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii. This is the
thirteenth Quarterly EM&A Report presents the environmental monitoring and
audit works for the period between 1 March 2019 and 31 May 2019. As informed by
the Contractor, major activities in the reporting period included:
March 2019 |
April 2019 |
May 2019 |
· Excavation and laying of drainage
pipe and manhole; · Excavation and ELS
construction. · Construction of SUS
structure; and · Construction of District
Cooling System. |
· Excavation and laying of
drainage pipe and manhole; · Excavation and ELS
construction. · Construction of SUS
structure; and · Construction of District
Cooling System. |
· Excavation and laying of
drainage pipe and manhole; · Excavation and ELS
construction. · Construction of SUS
structure; and · Construction of District
Cooling System. · Construction of Subway A. · Construction of Subway B. · Construction of road base
and road pavement. |
Breaches of the Action and Limit Levels
iii. No Action and Limit Level exceedance for
24-hr TSP was recorded in the reporting period at all monitoring stations.
iv. A Limit Level exceedance was recorded for construction
noise at KTD 2b on 22 March 2019. No Action / Limit Level exceedance was
recorded for construction noise at KTD 1a and KER 1b in the reporting period.
Complaint, Notification of Summons and
Successful Prosecution
v. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.