5.            SITE INSPECTION

 

5.1         Site Inspection

 

5.1.1     Site inspections were carried out weekly to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. A summary of the mitigation measures implementation schedule is provided in Appendix F.

 

5.1.2     In the reporting quarter, 13 site inspections were carried out. 6 of them were the joint inspections with the IEC, ER, the Contractor and the ET.

 

5.1.3     One outstanding issue was reported on September 2019, contractor was recommended that hoarding should be erected around the site area in Zone 4. The issue was rectified in the following weekly site inspection on 2 October 2019.

 

5.1.4     All the follow-up actions requested by Contractor’s ET and IEC during the site inspections were undertaken as reported by the Contractor and confirmed in the following weekly site inspection conducted during the reporting month.

 

5.1.5     Details of observations recorded during the site inspections are presented in Table 5.1.