5.1.1
Site inspections were carried out weekly to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. A summary of the mitigation measures implementation
schedule is provided in Appendix F.
5.1.2
In the reporting quarter, 13 site inspections
were carried out. 6 of them were the joint inspections with the IEC, ER, the
Contractor and the ET.
5.1.3
One outstanding issue was reported on September
2019, contractor was recommended that hoarding should be erected around the
site area in Zone 4. The issue was rectified in the following weekly site
inspection on 2 October 2019.
5.1.4
All the follow-up actions requested by
Contractor’s ET and IEC during the site inspections were undertaken as reported
by the Contractor and confirmed in the following weekly site inspection
conducted during the reporting month.
5.1.5
Details of observations recorded during the
site inspections are presented in Table 5.1.