5.1.1 Site inspections were carried out weekly
to monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. A summary of the mitigation measures implementation
schedule is provided in Appendix F.
5.1.2 In the reporting quarter, 12 site
inspections were carried out. 4 of them were the joint inspections with the
IEC, ER, the Contractor and the ET.
5.1.3
From
29 January 2020 to 31 January 2020, no site inspection was conducted due to the
site was close under the government’s special arrangement to reduce the risk of
the spread of the novel coronavirus in the community.
5.1.4 All the follow-up actions requested by
Contractor’s ET and IEC during the site inspections were undertaken as reported
by the Contractor and confirmed in the following weekly site inspection
conducted during the reporting month.
5.1.5 Details of observations recorded during
the site inspections are presented in Table 5.1.