2.            SUMMARY OF EM&A REQUIREMENTS AND MONITORING RESULTS

 

2.1         Monitoring Requirement

 

In accordance with the approved EM&A Manuals, 24-hour Total Suspended Particulates (TSP) level and Leq (30min) at the designated monitoring stations is required. Impact 24-hour TSP monitoring should be carried out at least once every 6 days. In case of complaints, 1-hour TSP monitoring should be carried out at least 3 times per 6 days when the highest dust impacts are likely to occur. Leq (30min) monitoring is conducted for at least once a week during the construction phase between 0700 and 1900 on normal weekdays. The Action and Limit Levels of the air quality monitoring and noise monitoring are given in Appendix C

 

2.2         Monitoring Locations

 

2.2.1     According to the EM&A Manual, three monitoring locations for air quality monitoring and noise monitoring, namely KTD1, KTD2 and KER1, are covered by this Contract within the South Apron Area of Former Kai Tak Airport. The other two air quality monitoring locations and two noise monitoring locations which are identified in Cha Kwo Ling area, are farther than 500m and 300m away from the site boundary respectively and thus not covered by this Contract. The monitoring works in Cha Kwo Ling area are covered by other Contract(s) respectively.

 

2.2.2     According to the approved alternative baseline air quality and noise monitoring locations (EPD reference: EP2/K19/A/21 Pt.5), the original monitoring locations (KTD1, KTD2 and KER1) are proposed to be replaced by alternative monitoring locations (KTD1a, KTD2a and KER1a).

 

2.2.3      According to the approved relocation of monitoring location KER1a (EPD reference: () in EP2/K19/A/21 Pt.5), the monitoring location KER1a are proposed to be relocated by alternative monitoring locations KER1b. 

 

2.2.4     According to the approved relocation of monitoring location KTD2a (EPD reference: () in EP2/K19/A/21 Pt.6), the monitoring location KTD2a are proposed to be relocated by alternative monitoring locations KTD2b.

 

2.2.5      According to the approved relocation of monitoring location KTD2b (EPD reference: () in EP2/K19/A/21 pt.7), the monitoring location KTD2b are proposed to be relocated by alternative monitoring location KTD2c.

 

2.2.6     As informed by the ET of Contract No. ED/2018/04, the monitoring location KTD1a and KER1b have been relocated to KTD1 and KER1 on 3 August 2020.

 

2.2.7      The most updated locations are summarized in Table 2.1 and shown in Figure 2.

 

2.3         Results and Observations

 

2.3.1     Seven Action Level exceedance for 24-hr TSP were recorded in the reporting period. Five exceedance were recorded at KTD2c on 14, 24 October 2020 and 11, 16, 21 November 2020. Two exceedance were recorded at KER1 24 October 2020 and 16 November 2020.

2.3.2     One Limit Level exceedance for 24-hr TSP was recorded in the reporting period. An exceedance was recorded at KTD2c on 5 November 2020.

 

2.3.3     A Limit Level exceedance for construction noise was recorded. Exceedance was recorded at KTD1 on 21 October 2020.

 

2.3.4     No Action / Limit Level exceedance was recorded for construction noise at KTD2c and KER1 in the reporting period.

 

2.3.5     No raining and wind with speed over 5 m/s was observed during noise monitoring according to the onsite observation.

 

2.3.6     Graphical presentation of the monitoring data in the reporting period is presented in Appendix D.

 

2.4         Comparison of Monitoring Results with EIA Predictions

 

2.4.1     The monitoring data was compared with the EIA predictions as summarized in Table 2.2 and Table 2.3.

 

2.4.2     The 24-hour TSP monitoring results at KTD1 in October and KER1 in October and November exceeded the Predicted Maximum 24-hour TSP Concentration in the approved Environmental Impact Assessment (EIA) Report. Seven Action Level exceedance and one Limit Level exceedance were recorded in the reporting period.

 

2.4.3     On 14 October 2020, at KTD2c non-project related construction works were carried out during 24-hr TSP monitoring. Dust was generated from construction site of Trunk Road T2 when C&D materials loading and unloading activities was processing. Thus, it is considered that this exceedance is not project related.

 

2.4.4     On 24 October 2020, at KER1 and KTD2c non-project related construction works were carried out during 24-hr TSP monitoring. Dust arising from the vehicle movement from construction site of Trunk Road T2. Thus, it is considered that this exceedance is not project related.

 

2.4.5     On 24 October 2020, at KTD1 non-project related construction activities at the nearby construction sites of New Acute Hospital and the fluctuation of road traffic along Shing Fung Road which affected the result of 24-hour TSP concentration. Thus, it is considered that this exceedance is not project related.

 

2.4.6     On 5, 11, 16 and 21 November 2020, at KTD2c non-project related construction works were carried out during 24-hr TSP monitoring. Dust was generated from construction site of Trunk Road T2 when C&D materials loading and unloading activities was processing. Thus, it is considered that this exceedance is not project related.

 

2.4.7     On 16 November 2020, at KER1 non-project related construction works were carried out during 24-hr TSP monitoring. Dust arising from the road traffic along Kai Hing Road and the vehicle movement from the adjacent building (Kerry DG Warehouse (Kowloon Bay). Thus, it is considered that this exceedance is not project related.

 

2.4.8     The noise monitoring results at KER1 in the reporting period did not exceed the Maximum Predicted Mitigated Construction Noise Level in the approved Environmental Impact Assessment (EIA) Report and no Action / Limit Level exceedance for KER1 was recorded in the reporting period.

 

2.4.9     The noise monitoring results at KTD1 in October and November exceeded the Maximum Predicted Mitigated Construction Noise Level in the approved Environmental Impact Assessment (EIA) Report. A limit Level exceedance for KTD1 was recorded in the reporting period.

 

2.4.10   On 21 October 2020, at KTD1 a breaker from construction site of New Acute Hospital was operated continuously. The noise generated by the breaker during breaking activity dominates the ambient or background noise. Thus, it is considered that this exceedance is not project related.

 

2.4.11   On 23 November 2020, at KTD1 non-project related construction noise generated from the construction activity at the adjacent construction site (New Acute Hospital at Kai Tak Development Area) and the fluctuations of traffic flow along Shing Fung Road throughout the day. Thus, it is considered that this exceedance is not project related.