8.1.1
Seven Action Level exceedance for 24-hr TSP
were recorded in the reporting period. Five exceedance were recorded at KTD2c
on 14, 24 October 2020 and 11, 16, 21 November 2020. Two exceedance were
recorded at KER1 on 24 October 2020 and 16 November 2020.
8.1.2
One Limit Level exceedance for 24-hr TSP was
recorded in the reporting period. An exceedance was recorded at KTD2c on 5
November 2020.
8.1.3
A Limit Level exceedance for construction noise
was recorded. Exceedance was recorded at KTD1 on 21 October 2020.
8.1.4
No Action / Limit Level exceedance was recorded
for construction noise at KTD2c and KER1 in the reporting period.
8.1.5 13 weekly environmental
site inspections were carried out in the reporting period. Recommendations on
mitigation measures on chemical and waste management were given to the
Contractor for remediating the deficiencies identified during the site
inspections.
8.1.6 13 weekly Landscape and Visual Site audits were
carried out on in the reporting period and 6 of them were carried out by a
Registered Landscape Architect in the reporting period. The weekly Landscape
and Visual Impact reports were counter-signed by IEC as according to the
requirement of EM&A Manual (AEIAR-130/2009). No non-compliance was recorded
in the weekly Landscape and Visual Site audits in the reporting period.
8.1.7
Referring
to the Contractor’s information, no notification of summons and successful
prosecution was received in the reporting period.
8.2.1 The recommended environmental mitigation measures,
as proposed in the EIA reports and EM&A Manuals shall be effectively
implemented to minimize the potential environmental impacts from the Project. The
EM&A programme would effectively monitor the environmental impacts generated
from the construction activities and ensure the proper implementation of
mitigation measures.
8.2.2 According to the environmental audit performed in
the reporting period, the following recommendations were made:
Air Quality Impact
l No
specific observation was identified in the reporting period.
Construction Noise Impact
l No
specific observation was identified in the reporting period.
Water Quality Impact
l No
specific observation was identified in the reporting period.
Chemical
and Waste Management
l General
refuse and construction waste was reminded to clear up regularly to prevent
accumulation.
Land Contamination
l No
specific observation was identified in the reporting period.
Landscape and Visual Impact
l No
specific observation was identified in the reporting period.
General Condition
l No
specific observation was identified in the reporting period.
Permit / Licenses
l No
specific observation was identified in the reporting period.