Table
of contents
Page
Summary of Main Works Undertaken and
Key Measures Implemented
Environmental Monitoring Works
Key Information in the Reporting
Month
Construction Activities undertaken
during the Reporting Month
Status of Environmental Licensing and
Permitting
Monitoring
Parameters and Frequency
Comparison of EM&A Result with
EIA Prediction
Monitoring
Parameters, Frequency and Duration
Monitoring Methodology and QA/QC
Procedure
Comparison of EM&A Result with
EIA Prediction
Monitoring Parameters and Frequency
Implementation Status of
Environmental Mitigation Measures
Implementation Status of Event and
Action Plans
13 Environmental
non-conformance
Summary of Complaint, Warning,
Notification of any Summons and Successful Prosecution
15 Conclusions
and recommendations
lIST OF
TABLES
Table I Non-compliance (exceedance) Record for the Project in the Reporting Month
Table III Summary of Complaints Details in Reporting Month
Table IV Summary Table for Site Activities in the next Reporting Period
Table 1.1 Key Project Contacts
Table 1.2 Summary of Environmental License and Permit
Table 2.1 Air Quality Monitoring Locations
Table 2.2 Frequency and Parameters of Air Quality Monitoring
Table 2.3 Air Quality Monitoring Equipment
Table 2.4 Major Dust Source during Air Quality Monitoring
Table 2.5 Comparison of 1-hr TSP Monitoring Data with Predictions in EIA Report
Table 2.6 Comparison of 24-hr TSP Monitoring Data with Predictions in EIA Report
Table 3.1 Noise Monitoring Stations
Table 3.2 Frequency and Parameters of Noise Monitoring
Table 3.3 Noise Monitoring Equipment
Table 3.4 Other Noise Source Identified during Noise Monitoring
Table 3.5 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 3.6 Maximum Predicted Mitigated Construction Noise Levels in EIA Report
Table 10.1 Landfill Gas Monitoring Equipment
Table 12.1 Observations and Recommendations of Site Audit
lIST OF FIGUREs
Figure 1.2 Organizational Structure for Environmental Management
Figure 2 Locations of Air Quality and Construction Noise Monitoring Stations
lIST OF APPENDIces
Appendix A Action and Limit Levels
Appendix
B Copies of
Calibration Certificates
Appendix C Weather Information
Appendix D Environmental Monitoring Schedules
Appendix E 1-hour TSP Monitoring Results and Graphical Presentations
Appendix F 24-hour TSP Monitoring Results and Graphical Presentations
Appendix G Noise Monitoring Results and Graphical Presentations
Appendix
H Waste Generation in the Reporting Month
Appendix I Site Audit Summary
Appendix
J Environmental Mitigation Implementation Schedule
(EMIS)
Appendix K Record
of Landfill Gas Monitoring by Contractor
Appendix L Event
and Action Plans
Appendix
N Summary of Exceedance
Appendix
O Tentative Construction Programme
1.
This is the 11th
Environmental Monitoring and Audit (EM&A) Report prepared by the
Environmental Team (ET), Cinotech Consultants Ltd.,
for Contract No. ED/2018/04 “Trunk Road T2
and Infrastructure Works for Developments at the Former South Apron”.
This report summarized the monitoring results and audits findings of the
EM&A programme under the issued Environmental Permit (EP) No. EP-458/2013/C
and in accordance with the EM&A Manual (AEIAR-173/2013) during the
reporting month of March 2021.
2. The main works undertaken during the
reporting period are as follows:
West Bound – Drill & Break Tunnel
East Bound – Drill & Blast Tunnel
3. Implementation of the key mitigation
measures during the reporting period are as follows:
Construction Noise
Construction activities were scheduled to minimize noise nuisance to the nearby sensitive receiver.
Use of Quality Powered Mechanical Equipment (QPME) on site.
Erected the noise barrier on site.
Air Quality
Regularly watering on site to avoid dust generation.
Landscape and Visual
Tree protection zones were fenced off to protect the existing trees on site.
4. Environmental monitoring for the Project
was performed in accordance with the EM&A Manual and the monitoring results
were checked and reviewed. Site Inspections/Audits were conducted once per
week. The implementation of the environmental mitigation measures, Event Action
Plans and environmental complaint handling procedures were also checked.
5. Summary of the non-compliance (exceedance) in the reporting month for the Project is tabulated in Table I.
Table I Non-compliance (exceedance) Record for the Project in
the Reporting Month
Environmental
Monitoring |
No. of
Non-compliance (Exceedance) |
No. of Non-compliance (Exceedance) due to Construction Activities of this
Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
0 |
0 |
N/A |
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
Groundwater Level Monitoring (Piezometer
Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
Landfill Gas |
N/A(1) |
0 |
N/A(1) |
0 |
N/A |
Note: (1): No Action
Level for Landfill Gas Monitoring. |
Air Quality Monitoring
6. No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded.
7. No Action/Limit Level exceedance for 24-hour TSP monitoring was recorded.
Construction Noise
Monitoring
8. No Action Level exceedance was recorded in this reporting month.
9. No Limit Level exceedance for day time construction noise monitoring were recorded in the reporting month.
Water Quality Monitoring
10. Groundwater quality monitoring had been
suspended since October 2019 upon the agreement by EPD. Further details should be founded at Section 4.1.
11. No marine water quality monitoring is
required as no marine works will be conducted at the Cha Kwo
Ling and Lam Tin areas for this project.
12. As the construction activity is approximately 120m away from the piezometer gate, no piezometer monitoring is required.
Waste Management
13. Wastes generated from this Project include inert construction and demolition (C&D) materials, and non-inert C&D materials. Details of waste management data is presented in Appendix H.
Ecological Monitoring
14. No coral monitoring is required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin areas for this project.
Fisheries Impact Monitoring
15. No specific fisheries monitoring programme
is required during the construction phase.
Monitoring on Cultural
Heritage
16. As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT
at the Eastern Ventilation Building are located more than 100m away from the
Cha Kwo Ling Tin Hau
temple, no monitoring on cultural heritage is required.
Landscape and Visual
Monitoring and Audit
17. The implementation of landscape and visual mitigation measures was checked by a registered landscape architect. Recommended follow-up actions have been discharged by the Contractor. Details of the audit findings and implementation status are presented in Section 12.
Landfill Gas Monitoring
18. Monitoring of landfill gases was commenced in December 2016. Such monitoring was conducted by the Contractor of Agreement No. CE 59/2015 (EP). No Limit Level exceedance was recorded in this reporting month.
Hazard to Life Monitoring
19. No environmental monitoring and audit is required as no hazard assessment was conducted.
Environmental Site Inspection
20. Joint weekly site inspections were conducted by representatives of the Contractor, Engineer and Environmental Team. Details of the audit findings and implementation status are presented in Section 12.
21. Summary of key information in the reporting month is tabulated in Table II
Event |
Event Details |
Action Taken |
Status |
|
Number |
Nature |
|||
Complaints Received |
1 |
Noise |
Details refer to App M |
Closed |
Notifications of any
summons & prosecutions received |
0 |
-- |
N/A |
N/A |
22. Summary of complaints received in the reporting month is tabulated in Table III.
Table
III Summary of Complaints Details in
Reporting Month
Complaint Type |
Investigation Findings |
Follow-up Action / Mitigation Measure |
Ground
borne noise nuisance from the construction activities at the night-time
period (About 3-4 a.m.). |
1.
According
to the investigation result of further complaint, the construction activities
of Trunk Road T2 conducted inside the tunnel area and the construction activities
of TKO-LT Tunnel conducted inside the tunnel section at Kwun Tong Side on the
night-time of the date of complaint are considered as one of the potential
noise source of the ground borne noise nuisance. |
1.
Contractor
is recommended to continue to strictly follow the requirements in the
relevant CNP. 2.
According to the condition 3.d point 5 of the CNP
(GW-RE0071-21), the immediate remedial action shall be
implemented in case adverse ground-borne noise impact on any noise sensitive
receiver is received. 3.
Blast
door was fully enclosed when construction activities were carried out within
tunnel area to prevent, reduce or minimize the emission of airborne noise. |
23. No reporting change in the reporting month.
24. The key works or activities will be
anticipated in the next reporting period are as follows:
Table IV Summary Table
for Site Activities in the next Reporting Period
Site Activities (April 2021) |
Key Environmental Issues |
||
1. West Bound –
Drill & Break Tunnel 2. East Bound –
Dill & Blast Tunnel |
(A) / (B) / (C) / (D) |
||
Note: (A) Dust generation
from haul road, stockpile of
dusty materials, exposed site area, excavation works and rock breaking
activities; (B) Noisy construction activity such as
rock-breaking activities and piling works; (C) Runoff from exposed slope or site area;
and (D) Wastewater and runoff discharge from site. |
1.1
In 2009, Civil
Engineering and Development Department (CEDD) commissioned a Kai Tak Development (KTD) – Trunk Road T2 and
Infrastructure at South Apron Investigation. The
assignment covers the provision of the Trunk Road T2 and its connections with
the Central Kowloon Route (CKR) at the north apron area and the Tseung Kwan O – Lam Tin Tunnel (TKOLTT) to the south in the
Cha Kwo Ling area.
1.2
The Trunk Road T2
Project is one of the designated Projects under Schedule 2 of the EIAO proposed in the KTD. CEDD submitted the Project
Profile (No. PP-379/2009) on 24 March 2009 for application for an EIA study
brief for the Trunk Road T2 Project under the EIAO. Accordingly, an EIA Study
Brief (ESB-203/2009) for the Trunk Road T2 Project was issued on 30 April 2009. The Environmental Impact Assessment (EIA) Report for
the Trunk Road T2 Project was approved under the Environmental Impact
Assessment Ordinance (EIAO) on 19 September 2013. The corresponding
Environmental Permit (EP) was issued on 19 September 2013 (EP no.:
EP-451/2013).
1.3
The Contract No.
ED/2018/04 is the main contract of Trunk Road T2 (“T2 Main Works”) which
comprises mainly the design and construction of a dual two-lane trunk road of
approximately 3.0km long with about 2.7km of the trunk road in form of tunnel;
ventilation and administration buildings, environmental protection and
mitigation works and etc. The EM&A programme
under this Contract is governed by the two EPs (EP-451/2013 and EP-458/2013/C)
and two EM&A Manuals (AEIAR-174/2013 and AEIAR-173/2013). The work areas of
the T2 Main Works are shown in Figure 1
and the works to be executed under this Contract and corresponding EPs are
summarized as follows:
Environmental Permit |
Works Description |
EP-451/2013 –
Trunk Road T2 |
Trunk Road T2 · Construction of highway and sub-sea tunnel
connecting between Central Kowloon Route and Cha Kwo
Ling Tunnel · Western & Eastern Ventilation Buildings |
EP-458/2013/C – Tseung Kwan O – Lam Tin Tunnel (TKOLTT) and Associated
Works |
Cha Kwo Ling Tunnel Construction of
Cha Kwo Ling Tunnel from the end of Trunk Road T2
to the TKOLTT at the Eastern Ventilation Building |
Monitoring Works in Lam Tin under
EP-458/2013/C
1.4 Under Agreement No. CE 59/2015 (EP) – Tseung Kwan O – Lam Tin Tunnel (TKOLLT) and Associated Works, the baseline monitoring works in Lam Tin under the EM&A Manual (AEIAR-173/2013) were conducted by the Environmental Team (ET) for the Agreement No. CE 59/2015 (EP) at the approved monitoring locations, namely AM1, AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5. Impact monitoring within the Lam Tin area shall be conducted by the ET of Contract No. ED/2018/04 upon cessation of Agreement No. CE 59/2015 (EP). The data obtained from the impact monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be adopted in this report.
1.5
Cinotech Consultants Ltd. was designated as the
Environmental Team (ET) to undertake the EM&A works for “Trunk Road T2 and Infrastructure Works for
Developments at the Former South Apron” (hereinafter called the
“Project”).
1.6
This
is the 11th Monthly EM&A Report which summarises
the impact monitoring results and audit findings for the EM&A programme during the reporting period in March 2021.
1.7 Different Parties with different levels of involvement in the Project organization include:
Permit Holder – Civil Engineering and Development Department (CEDD)
Supervisor Representative – Hyder-Meinhardt Joint Venture (HMJV)
Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
Independent Environmental Checker (IEC) – Ramboll Hong Kong Limited (Ramboll)
Contractor – Bouygues Travaux Publics (BTP)
1.8 The key contacts of the Project are shown in Table 1.1.
Table 1.1 Key Project Contacts
Party |
Role |
Contact Person |
Phone No. |
CEDD |
Permit Holder |
Mr. Wong Chi Wai, Tommy |
3842 7111 |
HMJV |
Supervisor Representative |
Mr. Joe Nam |
5183 0830 |
Cinotech |
Environmental Team |
Mr. KS Lee (ETL) |
2151 2091 |
Ms. Karina Chan |
2157 3880 |
||
Ramboll |
Independent Environmental Checker |
Mr. Manson Yeung |
3465 2888 |
BTP |
Contractor |
Mr. Bryan Lee |
5588 3891 |
|
1.9
The Organizational Structure for Environmental Management is shown in Figure 1.2.
1.10 The major site activities undertaken in the reporting month included:
West Bound – Drill & Break
Tunnel
East Bound – Drill & Blast
Tunnel
1.11 The EM&A programme requires construction noise, air quality monitoring and environmental site audit, etc. The EM&A requirements for each parameter are described in the following sections, including:
All monitoring parameters;
Action and Limit levels for all environmental parameters;
Event Action Plans;
Environmental mitigation measures, as recommended in the Project EIA Report.
1.13 This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the monitoring parameters of the required environmental monitoring works and audit works for the Project in March 2021.
1.14 All permits/licenses obtained for the Project are summarized in Table 1.2.
Table
1.2 Summary of Environmental License
and Permit
Permit
/ License No. |
Valid Period |
Status |
|
From |
To |
||
Environmental
Permit (EP) |
|||
EP-451/2013 |
19 Sep 2013 |
N/A |
Valid |
EP-458/2013/C |
20 Jan 2017 |
N/A |
Valid |
Notification pursuant to Air Pollution
(Construction Dust) Regulation |
|||
Ref. No.: 451120 |
20 Nov 2019 |
N/A |
Valid |
Billing Account for Construction Waste
Disposal |
|||
A/C No.: 7036016 |
09 Dec 2019 |
N/A |
Valid |
Construction Noise Permit |
|||
CNP No. (For Portion T1): GW-RE0071-21 |
28 Jan 2021 |
27 May 2021 |
Valid |
CNP No. (For Portion Q): GW-RE0917-20 |
08 Nov 2020 |
07 May 2021 |
Valid |
CNP No. (For Portion Q): GW-RE0251-20 |
24 Mar 2021 |
23 Sep 2021 |
Valid |
Wastewater Discharge License |
|||
WT00036699-2020 |
14 Jan 2021 |
31 Jan 2026 |
Valid |
Chemical Waste Producer License |
|||
WPN: 5213-286-B2557-03 |
09 Mar 2020 |
N/A |
Valid |
2.1 According to Section 2.2.4 of the EM&A Manual (AEIAR-173/2013), 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was conducted to monitor the air quality for this Project. For regular impact monitoring, a sampling frequency of at least once in every six days at all of the monitoring stations for 1-hour and 24-hour TSP monitoring. Appendix A shows the established Action/Limit Levels for the environmental monitoring works.
2.2 Five designated monitoring stations were selected for air quality monitoring programme. Table 2.1 describes the air quality monitoring locations, which are also depicted in Figure 2.
Table 2.1 Air Quality Monitoring Locations
Location |
Location of Measurement |
|
AM1 |
Tin Hau
Temple |
Ground Level |
AM2 |
Sai Tso Wan Recreation Ground |
Ground Level |
AM3 |
Yau Lai Estate Bik Lai House |
Rooftop (41/F) |
AM4(1) |
Sitting-out Area at Cha Kwo Ling Village |
Ground Level |
AM4(A)(2) (*) |
Cha Kwo
Ling Public Cargo Working Area Administrative Office |
Rooftop (3/F) |
Remarks:
(1) For 1-hour TSP monitoring;
(2) For 24-hour TSP monitoring
(*) Air quality monitoring at designated
station AM4 (24-hr TSP) was rejected by the premise owners.
Therefore, baseline and impact air quality monitoring
works were carried out at alternative air quality monitoring stations AM4 (A)
(24-hr TSP only)
2.3
Table 2.2 summarizes the monitoring
parameters, monitoring period and frequencies of impact air quality monitoring.
The monitoring schedule is shown in
Appendix D.
Table 2.2 Frequency and Parameters of Air Quality
Monitoring
Monitoring
Stations |
Parameter |
Period |
Frequency |
AM1, AM2, AM3, AM4 |
1-hour TSP |
0700 – 1900 |
3
times per 6 days |
AM1, AM2, AM3, AM4(A) |
24-hour TSP |
24 hours |
Once every 6 days |
2.4 High Volume Samplers (HVS) in compliance with the specification stipulated in the EM&A Manual (AEIAR-173/2013), Section 2.3.1, were used to carry out 24-hour TSP monitoring. Direct reading dust meter were also used to measure 1-hour average TSP levels. The 1-hour sampling was determined by HVS to check the validity and accuracy of the results measured by direct reading method.
2.5 Wind data monitoring equipment was set at rooftop (about 41/F) of Yau Lai Estate Bik Lai House for logging wind speed and wind direction such that the wind sensors are clear of obstructions or turbulence caused by building. The wind data monitoring equipment is re-calibrated at least once every six months and the wind directions are divided into 16 sectors of 22.5 degrees each. The location is shown in Figure 2. This weather information for the reporting month is summarized in Appendix C.
2.6 Table 2.3 summarizes the equipment used for air quality monitoring by the ET for Contract No. CE 59/2015 (EP). Copies of calibration certificates are attached in Appendix B.
Table
2.3 Air Quality Monitoring
Equipment
Equipment |
Model
|
Quantity |
1-hour TSP Dust
Meter |
Sibata
Model No. LD-5R (Serial No.: 8Y2373, 8Y2374, 972781, 972780, 972778,972779) |
6 |
HVS Sampler |