Table 5.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
|
Air Quality |
21 June 2018 |
Observation: Unused construction materials and construction
wastes should be removed or covered properly (Zone 1 and Zone 2). |
The item was rectified by the
Contractor and inspected on 28 June 2018. |
|
1 August 2018 |
Reminder: Contractor was reminded to water the
bare soil ground surface regularly to suppress dust. (Zone 4) |
NA |
||
15 August 2018 |
Reminder: Proper label color
should be used for NRMM label. (Zone 2) |
NA |
||
Noise |
NA |
|||
Water Quality |
14 June 2018 |
Reminder: Contractor
was reminded that the surrounding of discharge point be kept clear of silt,
dusty or muddy materials (Portion I). |
NA |
|
4 July 2018 |
Observation: Chemical should be added to the
sedimentation tank to facilitate the sedimentation of muddy water (Zone 1). |
The item was rectified by the Contractor
and inspected on 18 July 2018. Emulsified polymer and coagulant agent (PAFC)
have been added to enhance solid removal efficiency of WetSep.
|
||
11 July 2018 |
Observation: Chemical should be added to the
sedimentation tank to facilitate the sedimentation (Zone 1). |
The item was rectified by the Contractor
and inspected on 18 July 2018. Emulsified polymer and coagulant agent (PAFC)
have been added to enhance solid removal efficiency of WetSep. |
||
11 July 2018 |
Observation: Sediment in the sedimentation tank
should be cleared regularly (Zone 4). |
As informed by contractor, the item
will be rectified before 15 August 2018. |
||
25 July 2018 |
Observation: Stagnant water was observed (Zone 2).
Contractor should remove the stagnant water and treat the waste water
properly before discharge. |
The item was rectified by the
Contractor and inspected on 1 August 2018. |
||
15 August 2018 |
Observation: The gully should be sealed by concrete
bund. Sediments and stagnant water inside the gully should be removed
regularly. (Zone 2) |
The item was rectified by the
Contractor and inspected on 22 August 2018. |
||
Chemical and Waste Management |
21 June 2018 |
Observation: Unused
construction materials and construction wastes should be removed or covered
properly (Zone 1 and Zone 2). |
The item was rectified by the Contractor
and inspected on 28 June 2018. |
|
1 August 2018 |
Reminder: Contractor was reminded to remove
construction waste properly. (Zone 1) |
NA |
||
15 August 2018 |
Observation: Chemical containers should be placed
on the drip tray. (Zone 3) |
The item was rectified by the
Contractor and inspected on 22 August 2018. |
||
29 August 2018 |
Observation: Different types of waste shall be
segregated and handled properly. Unused waste shall be removed
regularly. (Zone 1) |
The item was rectified by the
Contractor and inspected on 5 September 2018. |
||
Land Contamination |
NA |
|||
Landscape and Visual Impact |
21 June 2018 |
Observation: Unused construction materials and construction
wastes should be removed or covered properly (Zone 1 and Zone 2). |
The item was rectified by the
Contractor and inspected on 28 June 2018. |
|
1 August 2018 |
Reminder: Contractor should remove the construction waste
at zone 1 as soon as possible. |
NA |
||
General |
NA |
|||