Weather and Meteorological Conditions during
Reporting Month |
|
|
|
i.
The
Civil Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii.
This
Monthly EM&A report presents the environmental monitoring and audit works
for the period between 1 July and 31 July 2019. As informed by the Contractor,
major activities in the reporting month were:
Excavation
and laying of drainage pipe and manhole;
Excavation
and ELS construction.
Construction
of SUS structure;
Construction
of District Cooling System;
Construction of Subway
A;
Construction of road
base and road pavement.
Breaches of the Action and Limit Levels
iii.
No Action / Limit
Level exceedance was recorded for 24-hr TSP and construction noise at KTD1a,
KTD2b and KER1b in the reporting month.
Complaint,
Notification of Summons and Successful Prosecution
iv.
No environmental
complaint, notification of summons and successful prosecution were received in
the reporting month.
Reporting
Changes
v.
There was no
reporting change in the reporting month.
Future
Key Issues
vi. The key issues to be considered in the
coming reporting month include:
Potential environmental impacts arising from
the above construction activities are mainly associated with construction dust,
construction noise, water quality, waste management and landscape and visual
impacts.