3.1.1
To monitor and audit the implementation of landscape and visual
mitigation measures, 12 weekly Landscape and Visual Site audits were carried
out and 6 of them were carried out by a Registered Landscape Architect. The
weekly Landscape and Visual Impact reports were counter-signed by IEC as
according to the requirement of EM&A Manual (AEIAR-130/2009). During the Site audit on 1 March 2018, Contractor was reminded that
stockpile at Portion H should be properly covered.
3.1.2 During the Site audit on 11 January 2018, it was observed that broken concrete
should be removed promptly in Zone 1. During the Site audit on 14 February
2018, it was observed that stockpiling at the end of zone 4 were not properly
covered, contractor should cover the stockpile ASAP for the holiday.
3.1.3
No non-compliance was recorded in the weekly Landscape and Visual Site
audits in the reporting period.
3.1.4
Observations and recommendations during site audits are summarized in Table 5.1.