3.1.1
To monitor and audit the implementation of landscape and visual
mitigation measures, 14 weekly Landscape and Visual Site audits were carried
out and 7 of them were carried out by a Registered Landscape Architect. The
weekly Landscape and Visual Impact reports were counter-signed by IEC as
according to the requirement of EM&A Manual (AEIAR-130/2009).
3.1.2 During the Site audit on 1 March 2018, Contractor was reminded that
stockpile at Portion H should be properly covered.
3.1.3 During the site audit on 10 May 2018,
Contractor was reminded to secure the stockpiling cover to avoid blown over by
strong wind.
3.1.4
No non-compliance was recorded in the weekly Landscape and Visual Site
audits in the reporting period.
3.1.5
Observations and recommendations during site audits are summarized in Table 5.1.