5.1.1
Site inspections were carried out weekly to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. A summary of the mitigation measures
implementation schedule is provided in Appendix F.
5.1.2
In the reporting quarter, 14 site inspections
were carried out. 6 of them were the joint inspections with the IEC, ER, the
Contractor and the ET.
5.1.3
No outstanding issues were reported during the
reporting period.
5.1.4
All the follow-up actions requested by
Contractor’s ET and IEC during the site inspections were undertaken as reported
by the Contractor and confirmed in the following weekly site inspection
conducted during the reporting month.
5.1.5
Details of observations recorded during the
site inspections are presented in Table 5.1.
Table 5.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
|
Air Quality |
1 March 2018 |
Mud and silt deposits were found at the entrance
of Portion I. Contractor should clean the ground regularly. |
The item was rectified by the
Contractor and inspected on 8 March 2018. |
|
Contractor
was reminded to apply dust suppression measures such as water spraying to
open stockpile. (Portion H) |
The item was rectified by the
Contractor and inspected on 8 March 2018. |
|||
8 March 2018 |
Dark smoke
were emitted from plant. Contractor should maintain the machine/plant
regularly to prevent dark smoke emission. |
The item was rectified by the
Contractor and inspected on 15 March 2018. |
||
14 March 2018 |
Excavated
earth material were brought to road by unfully
washed wheels (Portion K). Contractor should clean the road ASAP. |
The item was rectified by the
Contractor and inspected on 21 March 2018. |
||
4 April 2018 |
Contractor was reminded to provide sufficient
watering on stockpile to suppress dust (Radar Tower). |
The item was rectified by the
Contractor and inspected on 12 April 2018. |
||
18 April 2018 |
Contractor was reminded to replace the
NRMM label of mobile crane shall be replaced with proper label color (Zone 3). |
The item was rectified by the
Contractor and inspected on 26 April 2018. |
||
26 April 2018 |
Contractor was reminded that NRMM
label on mobile crane shall be replaced with proper label color
(Zone 2). |
The item was rectified by the
Contractor and inspected on 3 May 2018. |
||
3 May 2018 |
Dark smoke was emitted from machine plant (Zone
2). Contractor should maintain plant/equipment regularly to prevent dark
smoke emission. |
The item was rectified by the
Contractor and inspected on 10 May 2018. |
||
10 May 2018 |
Contractor was reminded that stockpile
should be covered properly with impermeable sheeting (Zone 1) |
The item was rectified by the
Contractor and inspected on 16 May 2018. |
||
31 May 2018 |
Contractor was reminded to remove the
stockpile to avoid dust (Zone 2) |
The item was rectified by the
Contractor and inspected on 7 June 2018. |
||
Noise |
NA |
|||
Water Quality |
8 March 2018 |
Contractor was reminded to take
precaution measures at any time of year when rainstorm is likely. |
The item was rectified by the
Contractor and inspected on 15 March 2018. |
|
21 March 2018 |
Stagnant water were accumulating in
Portion K. Contractor should complete the pumping system ASAP. |
The item was rectified by the
Contractor and inspected on 26 March 2018. |
||
26 March 2018 |
Sediments and stagnant water were
found in the u-channel (Zone 2). Sediments and stagnant water shall be
removed regularly. |
The item was rectified by the
Contractor and inspected on 4 April 2018. |
||
12 April 2018 |
Slurry was observed accumulating in
the U-Channel (Zone 2). Contractor should clean the U-Channel regularly to
prevent accumulation of slurry. |
The item was rectified by the
Contractor and inspected on 18 April 2018. |
||
18 April 2018 |
Contractor was reminded to clean the
sediments inside the sedimentation tank regularly (Zone 1). |
The item was rectified by the
Contractor and inspected on 26 April 2018. |
||
3 May 2018 |
Contractor was reminded that stagnant
water shall be removed (Zone 3). |
The item was rectified by the
Contractor and inspected on 10 May 2018. |
||
16 May 2018 |
Contractor was reminded to provide
concrete bunding at site exits to prevent leakage
of muddy water to public areas (Zone 3 and 4). |
The item was rectified by the
Contractor and inspected on 24 May 2018. (Zone 3) |
||
24 May 2018 |
Contractor was reminded to provide
concrete bunding at site exits to prevent leakage
of muddy water to public areas (Zone 4). |
The item was rectified by the
Contractor and inspected on 31 May 2018. |
||
31 May 2018 |
The mud in wheel washing facility
should be removed (Portion I). |
The item was rectified by the
Contractor and inspected on 7 June 2018. |
||
Chemical and Waste Management |
1 March 2018 |
Oil
Stain was found on ground at Zone 2. Contractor should clean the oil stain
and dispose the waste as chemical waste. |
The item was rectified by the
Contractor and inspected on 8 March 2018. |
|
26 March 2018 |
Chemical
container shall be stored and labelled properly (Zone 1). Drip tray and
labels shall be provided |
The item was rectified by the Contractor
and inspected on 4 April 2018. |
||
26 March 2018 |
Chemical
container shall be orderly and carefully stored (Zone 1). Drip tray and
labels shall be provided |
The item was rectified by the
Contractor and inspected on 4 April 2018. |
||
16 May 2018 |
Chemical containers shall be placed on
drip tray (Zone 2 and 3). Drip tray shall be provided. |
The item was rectified by the
Contractor and inspected on 24 May 2018. |
||
Land Contamination |
1 March 2018 |
Oil stain
was found on ground at Zone 2. Contractor should clean the oil stain and
dispose the waste as chemical waste. |
The
item was rectified by the Contractor and inspected on 8 March 2018. |
|
Landscape and Visual Impact |
26 March 2018 |
Construction material shall be orderly and
carefully stored (Zone 1). |
The item was rectified by the
Contractor and inspected on 4 April 2018. |
|
10 May 2018 |
Contractor was reminded that stockpile
should be covered properly with impermeable sheeting (Zone 1) |
The item was rectified by the
Contractor and inspected on 16 May 2018. |
||
General |
NA |
|||