i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii. This is the fourteenth
Quarterly EM&A Report presents the environmental monitoring and audit works
for the period between 1 June 2019 and 31 August 2019. As informed by the
Contractor, major activities in the reporting period included:
June 2019 |
July 2019 |
August 2019 |
·
Excavation and laying of drainage pipe and manhole; ·
Excavation and ELS construction. ·
Construction of SUS structure; and ·
Construction of District Cooling System. ·
Construction of Subway A. ·
Construction of road base and road pavement. |
·
Excavation and laying of drainage pipe and manhole; ·
Excavation and ELS construction. ·
Construction of SUS structure; and ·
Construction of District Cooling System. ·
Construction of Subway A. ·
Construction of road base and road pavement. |
·
Excavation and laying of drainage pipe and manhole; ·
Excavation and ELS construction. ·
Construction of SUS structure; and ·
Construction of District Cooling System. ·
Construction of Subway A. ·
Construction of road base and road pavement. |
Breaches of the Action and Limit Levels
iii. No Action and Limit Level exceedance for
24-hr TSP and noise was recorded in the reporting period at all monitoring
stations.
Complaint, Notification of Summons and Successful Prosecution
iv. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.