i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and
implement the EM&A works.
ii. This is the
fifteenth Quarterly EM&A Report presents the environmental monitoring and
audit works for the period between 1 September 2019 and 30 November 2019. As
informed by the Contractor, major activities in the reporting period included:
September 2019 |
October 2019 |
November 2019 |
·
Excavation and laying of drainage pipe and
manhole; ·
Excavation and ELS construction. ·
Construction of SUS structure; ·
Construction of District Cooling System; ·
Construction of road base and road
pavement. |
· Excavation
and laying of drainage pipe and manhole; · Excavation
and ELS construction. · Construction
of SUS structure; · Construction
of District Cooling System; · Construction
of road base and road pavement; · Utility
laying. |
· Excavation
and laying of drainage pipe and manhole; · Construction
of SUS structure; · Construction
of District Cooling System; · Construction
of road base and road pavement; · Utility
laying; · Demolition
of the barging point. |
Breaches of the Action and Limit Levels
iii. No Action and Limit Level exceedance for
24-hr TSP and noise was recorded in the reporting period at all monitoring
stations.
Complaint, Notification of Summons and Successful Prosecution
iv. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.