Executive Summary   I

1.         INTRODUCTION   1

2.         Summary of EM&A Requirements and monitoring results   4

3.         LANDSCAPE AND VISUAL   8

4.         WASTE MANAGEMENT   9

5.         SITE INSPECTION   10

6.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE   13

7.         IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES   15

8.         Conclusions   16

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Graphical Presentation of Monitoring Data

Appendix E

Waste Flow Table

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

 

 

 


Executive Summary

 

 i.    The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

ii.    This is the First Quarterly EM&A Report presents the environmental monitoring and audit works for the period between 1 June 2016 and 31 August 2016. As informed by the Contractor, major activities in the reporting period included:

 

June 2016

July 2016

August 2016

· Carrying out pre-drilling;

· Construction of guide walls and D-walls at Zone 2;

· Construction of H piles at Zone 1, 3 & 4;

· Demolition of foundation at Zone 4;

· Construction of temporary utility diversion at Zone 1;

· Construction of subway B at Zone 1;

· Implementation of Temporary Traffic Arrangement (TTA) along Cheung Yip Street and Shing Cheong Road;

· Erection of scaffolding at Radar Tower;

· Removal of Asbestos materials at Radar Tower; and

· Construction of temporary road at Zone 4.

 

· Carrying out pre-drilling;

· Construction of guide walls and D-walls at Zone 2;

· Construction of H piles at Zone 1 to Zone 4;

· Demolition of foundation at Zone 4;

· Construction of temporary utility diversion at Zone 1,3 & 4;

· Erection and installation of Earth Lateral Support (ELS) of subway B at Zone 1;

· Erection of scaffolding at Radar Tower;

· Setting up stockpiling area at Portion I and K;

· Construction of temporary road at Zone 4 and

· Installation of bulkhead wall at Zone 1.

 

· Carrying out pre-drilling;

· Rebar bending;

· Construction of guide walls and temporary D-walls;

· Construction of Socketed H piles;

· Pumping test;

· Temporary utility diversion;

· Excavation and Earth Lateral Support (ELS) construction;

· Demolition of Radar Tower;

· Implementation of Temporary Traffic Arrangement; and

· Construction of temporary road.

 

 

 

Breaches of the Action and Limit Levels

 

iii.    No Action and Limit Level exceedance for 24-hr TSP and noise was recorded in the reporting period at all monitoring stations.

 


Complaint, Notification of Summons and Successful Prosecution

 

iv.    No environmental complaint and no notification of summons and successful prosecution were received in the reporting period.