i. The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to
undertake the Environmental Team services for the Project and implement the
EM&A works.
ii. This is the First Quarterly EM&A
Report presents the environmental monitoring and audit works for the period
between 1 June 2016 and 31 August 2016. As informed by the Contractor, major
activities in the reporting period included:
June 2016 |
July 2016 |
August 2016 |
· Carrying out pre-drilling; · Construction of guide walls and D-walls at Zone
2; · Construction of H piles at Zone 1, 3 & 4; · Demolition of foundation at Zone 4; · Construction of temporary utility diversion at
Zone 1; · Construction of subway B at Zone 1; · Implementation of Temporary Traffic Arrangement
(TTA) along Cheung Yip Street and Shing Cheong Road; · Erection of scaffolding at Radar Tower; · Removal of Asbestos materials at Radar Tower; and · Construction of temporary road at Zone 4. |
· Carrying out pre-drilling; · Construction of guide walls and D-walls at Zone
2; · Construction of H piles at Zone 1 to Zone 4; · Demolition of foundation at Zone 4; · Construction of temporary utility diversion at
Zone 1,3 & 4; · Erection and installation of Earth Lateral
Support (ELS) of subway B at Zone 1; · Erection of scaffolding at Radar Tower; · Setting up stockpiling area at Portion I and K; · Construction of temporary road at Zone 4 and · Installation of bulkhead wall at Zone 1. |
· Carrying out pre-drilling; · Rebar bending; · Construction of guide walls and temporary D-walls; · Construction of Socketed H piles; · Pumping test; · Temporary utility diversion; · Excavation and Earth Lateral Support (ELS)
construction; · Demolition of Radar Tower; · Implementation of Temporary Traffic Arrangement;
and · Construction of temporary road. |
Breaches of the Action and Limit Levels
iii.
No Action and Limit
Level exceedance for 24-hr TSP and noise was recorded in the reporting period
at all monitoring stations.
Complaint,
Notification of Summons and Successful Prosecution
iv.
No environmental
complaint and no notification of summons and successful prosecution were
received in the reporting period.