i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii. This is the eighth
Quarterly EM&A Report presents the environmental monitoring and audit works
for the period between 1 December 2017 and 28 February 2017. As informed by the
Contractor, major activities in the reporting period included:
December 2017 |
January 2018 |
February 2018 |
· Excavation and laying of drainage pipe and
manhole; · Seawall modification works; · Construction of tunnel box structure; · D-wall construction works; · Pumping test; and · Excavation and ELS construction. |
· Excavation and laying of drainage pipe and
manhole; · Seawall modification works; · Construction of tunnel box structure; · D-wall construction works; · Pumping test; and · Excavation and ELS construction. |
· Excavation and laying of drainage pipe and
manhole; · Seawall modification works; · Construction of tunnel box structure; · D-wall construction works; · Pumping test; and · Excavation and ELS construction. |
Breaches of the Action and Limit Levels
iii. No Action and Limit Level exceedance for
24-hr TSP and noise was recorded in the reporting period at all monitoring
stations.
Complaint,
Notification of Summons and Successful Prosecution
iv. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.