TABLE OF CONTENTS

 

Executive Summary  

1.         INTRODUCTION  

2.         SUMMARY OF EM&A REQUIREMENTS AND MONITORING RESULTS  

3.         LANDSCAPE AND VISUAL  

4.         WASTE MANAGEMENT  

5.         SITE INSPECTION  

6.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE  

7.         IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES  

8.         Conclusions  

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Graphical Presentation of Monitoring Data

Appendix E

Waste Flow Table

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

 

 

 

 

 


Executive Summary

 

   i.   The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

  ii.   This is the eighth Quarterly EM&A Report presents the environmental monitoring and audit works for the period between 1 December 2017 and 28 February 2017. As informed by the Contractor, major activities in the reporting period included:

 

December 2017

January 2018

February 2018

· Excavation and laying of drainage pipe and manhole;

· Seawall modification works;

· Construction of tunnel box structure;

· D-wall construction works;

· Pumping test; and

· Excavation and ELS construction.

 

· Excavation and laying of drainage pipe and manhole;

· Seawall modification works;

· Construction of tunnel box structure;

· D-wall construction works;

· Pumping test; and

· Excavation and ELS construction.

 

· Excavation and laying of drainage pipe and manhole;

· Seawall modification works;

· Construction of tunnel box structure;

· D-wall construction works;

· Pumping test; and

· Excavation and ELS construction.

 

 

 

Breaches of the Action and Limit Levels

 

 iii.   No Action and Limit Level exceedance for 24-hr TSP and noise was recorded in the reporting period at all monitoring stations.

 

 

Complaint, Notification of Summons and Successful Prosecution

 

iv.   No environmental complaint and no notification of summons and successful prosecution were received in the reporting period.