The Civil Engineering and Development Department
HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the
Environmental Team services for the Project and implement the EM&A works.
ii.
This Monthly EM&A report presents the
environmental monitoring and audit works for the period between 1 July and 31
July 2020. As informed by the Contractor, major activities in the reporting
month were:
Excavation and laying of
drainage pipe and manhole;
Construction of District
Cooling System;
Utility laying;
Construction
of road base and road pavement;
Landscape
works – Irrigation system, tree and shrub planting;
Laying
Cable and Construction for Road Lighting.
Breaches of the Action and Limit Levels
iii. No Action / Limit Level exceedance was
recorded for 24-hr TSP and construction noise at KTD1a, KTD2c and KER1b in the
reporting month.
Complaint, Notification of Summons and Successful Prosecution
iv. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
v. There was no reporting change in the
reporting month.
Future Key Issues
vi. The key issues to be considered in the
coming reporting month include:
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, water quality, waste management and
landscape and visual impacts.